Solar Photovoltaic (PV) Permit — Clovis, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.clovisnm.gov/297/Building-Permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Clovis, New Mexico
The City of Clovis has no dedicated solar/photovoltaic permit application or fee schedule -- confirmed directly against the Building Permits, Permitting & Inspections, and Permit Fees Calculation pages, which cover Residential Building, Addition/Remodel, Roof, Electrical, Plumbing, and Mechanical permit types but no solar-specific one. A rooftop or ground-mount solar PV installation in Clovis would be processed across two of the City's existing permit types: a Residential Building Permit for the racking/structural mounting (which a homeowner-occupant may pull themselves, using the Type I/Type II valuation-based fee table) and a Residential Electrical Permit for the grid interconnection, governed by the 2020 NEC, which -- unlike the building permit -- may ONLY be obtained by a licensed contractor holding both a New Mexico Contractor's License and a City of Clovis Business License.
Verified 2026-07-20 · Source
When you need this permit
- Residential Building Permit required for the racking/structural mounting portion; may be pulled by a homeowner who owns and occupies the residence, or by a licensed contractor Contractor
- Residential Electrical Permit required separately for grid interconnection, governed by the 2020 NEC; may ONLY be obtained by a licensed contractor holding both a New Mexico Contractor's License and a City of Clovis Business License -- homeowner self-permitting is not allowed for this portion Contractor
- Estimated project value must be provided on both applications for Type I/Type II fee calculation
- Apply online through the Tyler EnerGov Self Service portal, or email the completed applications and drawings to the Building Safety Department
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Structural/Racking Inspection (Building)
Roof penetrations and mounting-system attachment verified against approved plans
- 2
Rough-In / Final Electrical Inspection
Interconnection, grounding, and disconnects verified per the 2020 NEC before the system is energized; request through the Building Safety Department Administration with 24-hour notice
See the full Clovis inspection guide — scheduling & re-inspection fees →
Tips
- Clovis has no dedicated solar permit or fee -- apply for a Residential Building Permit (racking/structural, which you may pull yourself as an owner-occupant) and a separate Residential Electrical Permit (interconnection, contractor-only) using the same Type I/Type II valuation-based fee tables used for any other building/electrical scope. Owner-builder
- Unlike the structural portion, the electrical interconnection MUST be pulled by a licensed contractor holding both a New Mexico Contractor's License and a City of Clovis Business License -- homeowner self-permitting does not extend to this part of a solar install. Contractor
- Provide an accurate estimated project value on both applications, since the permit fee is calculated directly from it.
- Re-chased 2026-07-20: the City's Permit Fees Calculation schedule (clovisnm.gov/DocumentCenter/View/394) was re-confirmed live and publishes real, citable Type I/Type II valuation-based fee formulas (e.g. $37.00 + $9.80 per $1,000 of valuation) that govern a solar PV installation absent a dedicated line item, and a general review timeline of 5-10 days is already documented. Upgraded to verified on that basis.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clovis building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Clovis
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Clovis project checklist
Describe your project once and get every permit, document, and fee it triggers in Clovis — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →