Solar PV Permit in Bernalillo, New Mexico
The Town of Bernalillo has no local building-inspection staff or dedicated solar permit type; building and electrical permitting statewide, including for solar PV installations, is issued directly by the New Mexico Construction Industries Division (CID) under N.M. Admin. Code 14.5.2.8(F), which sets detailed statewide licensing and submittal requirements for solar PV installers. The Town's own role is limited to a Zoning Review and administrative processing under its published Fee Schedule.
Verified 2026-07-20 · Source
When you need this permit
- Installers must hold a valid CID license with the EE-98, EL-1, or ER-1 classification, as applicable — N.M. Admin. Code 14.5.2.8(F)(1)
- Building Permit (CID) fee is 'ICC — Based on Valuation,' per the Town of Bernalillo Fee Schedule (updated 7/8/24); the CID calculates the valuation and fee directly under NMAC 14.5.5.10 — the Town does not set or collect this fee
- Town Zoning Review fee of $25.00 applies to residential development, per the Town of Bernalillo Fee Schedule
- Submittal documents required by CID include a site plan, PV panel layout, one-line diagram identifying all system components and conductor sizes, mounting-system listing documentation, utility interconnection details, and grounding system documentation — N.M. Admin. Code 14.5.2.8(F)(2)
- A structural analysis by a New Mexico-licensed professional engineer is required if the added dead load exceeds statutory thresholds (5 lbs/sq ft, 45 lbs point load, or 200 lbs added dead load), per N.M. Admin. Code 14.5.2.8(F)
- Commencing work without a permit doubles the applicable permit fee, per the Town of Bernalillo Fee Schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Bernalillo inspection guide — scheduling & re-inspection fees →
Tips
- Bernalillo has no local building department — solar PV building and electrical permits are issued directly by the New Mexico Construction Industries Division (CID), the same statewide agency that permits solar in other small NM towns without their own CID-certified program.
- The Town's own fee is limited to a $25 Zoning Review; the substantive permit fee (ICC valuation-based) is set and collected by CID, not the Town.
- Starting work before a permit is issued doubles the applicable permit fee under the Town's Fee Schedule.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bernalillo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bernalillo
Solar PV Permit in other cities
Compare solar pv permit fees across New Mexico →
Look up this fee in a different city →