Bernalillo has no standalone, separately-applied-for 'change of use' permit product. Per the Town's own Building and Property Standards Ordinance No. 318 (adopted 4/26/21), Section 12, no building or structure may be used or occupied, and no change in its existing occupancy classification may be made, until the Building Official has issued a Certificate of Occupancy (site-built/modular structures) or the Town has issued a Certificate of Compliance (manufactured/mobile homes). Where the occupancy change requires construction, reconstruction, alteration, repair, or conversion work, that work must go through the same CID-routed Building Permit process documented elsewhere in this file; the CO/Certificate of Compliance is the gating condition attached to that process, not a separate application.

Verified 2026-07-22 · Source

When you need this permit

  • No building or structure shall be used or occupied and no change in the existing occupancy classification of a building or structure, or portion thereof, shall be made until the Building Official has issued a Certificate of Occupancy or the Town has issued a Certificate of Compliance, as applicable — Town of Bernalillo Ordinance No. 318, Section 12.A
  • It is unlawful to commence the construction, reconstruction, alteration, repair, conversion, maintenance, removal, or demolition of a building or structure without first obtaining a Building Permit, if one is required by CID — Ordinance No. 318, Section 10.A; a change of occupancy classification that requires such work must be routed through the same CID Building Permit process (Alteration/Repairs/Demolition) as new construction, including the Town's mandatory zoning/floodplain pre-review sign-off
  • For site-built or modular buildings, structures, or housing units, a Certificate of Occupancy is signed by the Building Official upon completion and verification of all inspections and requirements, per Ordinance No. 318, Section 12.B; the CID Building Permit Guide for Commercial Construction independently confirms no change in existing occupancy classification is permitted until the building official issues a certificate of occupancy, per 14.5.3.13 NMAC
  • For manufactured or mobile homes, a Certificate of Compliance is issued by the Town instead, upon completion and verification of all inspections and requirements and prior to expiration of the time period required for skirting — Ordinance No. 318, Section 12.C
  • Issuance of a Certificate of Occupancy or Certificate of Compliance is not construed as approval of any violation of a Building Code or Town ordinance, and the Building Official (or the Town, for a Certificate of Compliance) may suspend or revoke it in writing if the building, structure, or housing unit is later found in violation — Ordinance No. 318, Section 12.D
  • No distinct standalone fee is published by the Town or CID for a 'change of use' or Certificate of Occupancy application itself — per Ordinance No. 318, Section 9.A, fees for inspection/permitting services performed on the Town's behalf by an entity such as CID follow that entity's own fee schedule, which is the same ICC valuation-based Building Permit fee documented in this file's Residential/Commercial Building Permit entries

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Certificate of Occupancy / Certificate of ComplianceTown of Bernalillo Ordinance No. 318, Section 9.A — fees for permitting/inspection services performed on the Town's behalf by CID follow CID's own fee schedule; CO/Certificate of Compliance issuance is already priced within the underlying Building Permit's ICC valuation-based fee documented in this file's Residential/Commercial Building Permit entries. No distinct standalone change-of-occupancy fee is published.
No separate fee

Review timeline

Plan review
Not published — contact the department

How long did your Change of Occupancy / Certificate of Occupancy permit actually take in Bernalillo?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection / Certificate of Occupancy Issuance

    Verification of all inspections and requirements under the applicable Building Code and Town ordinances, upon which the Building Official signs the Certificate of Occupancy (or the Town issues a Certificate of Compliance for manufactured/mobile homes), per Ordinance No. 318, Section 12.B-C.

See the full Bernalillo inspection guide — scheduling & re-inspection fees →

Tips

  • Bernalillo has no standalone Change-of-Use application separate from its Building Permit — if the new occupancy classification requires construction work, that work must go through the same CID-routed Building Permit process documented elsewhere in this file, and the Certificate of Occupancy is issued as its final step.
  • Manufactured and mobile homes receive a Town-issued Certificate of Compliance instead of a CID-issued Certificate of Occupancy, tied to the Placement Permit process documented elsewhere in this file.
  • A previously issued Certificate of Occupancy or Certificate of Compliance is not a one-time, irrevocable approval — Ordinance No. 318 lets the Building Official (or the Town) suspend or revoke it in writing if a later violation is found.

Frequently asked questions

Bernalillo requires a change of occupancy / certificate of occupancy permit for: No building or structure shall be used or occupied and no change in the existing occupancy classification of a building or structure, or portion thereof, shall be made until the Building Official has issued a Certificate of Occupancy or the Town has issued a Certificate of Compliance, as applicable — Town of Bernalillo Ordinance No. 318, Section 12.A; It is unlawful to commence the construction, reconstruction, alteration, repair, conversion, maintenance, removal, or demolition of a building or structure without first obtaining a Building Permit, if one is required by CID — Ordinance No. 318, Section 10.A; a change of occupancy classification that requires such work must be routed through the same CID Building Permit process (Alteration/Repairs/Demolition) as new construction, including the Town's mandatory zoning/floodplain pre-review sign-off; For site-built or modular buildings, structures, or housing units, a Certificate of Occupancy is signed by the Building Official upon completion and verification of all inspections and requirements, per Ordinance No. 318, Section 12.B; the CID Building Permit Guide for Commercial Construction independently confirms no change in existing occupancy classification is permitted until the building official issues a certificate of occupancy, per 14.5.3.13 NMAC; For manufactured or mobile homes, a Certificate of Compliance is issued by the Town instead, upon completion and verification of all inspections and requirements and prior to expiration of the time period required for skirting — Ordinance No. 318, Section 12.C; Issuance of a Certificate of Occupancy or Certificate of Compliance is not construed as approval of any violation of a Building Code or Town ordinance, and the Building Official (or the Town, for a Certificate of Compliance) may suspend or revoke it in writing if the building, structure, or housing unit is later found in violation — Ordinance No. 318, Section 12.D; No distinct standalone fee is published by the Town or CID for a 'change of use' or Certificate of Occupancy application itself — per Ordinance No. 318, Section 9.A, fees for inspection/permitting services performed on the Town's behalf by an entity such as CID follow that entity's own fee schedule, which is the same ICC valuation-based Building Permit fee documented in this file's Residential/Commercial Building Permit entries. If your project isn't listed, confirm with Town of Bernalillo Planning and Zoning Department at (505) 771-7118 (Planning and Zoning); (505) 867-3311 (Town Hall general information); fax (505) 867-0481 before starting work.

In Bernalillo, the published Certificate of Occupancy / Certificate of Compliance is: No separate fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Bernalillo does not publish a plan-review timeline for this permit. Contact Town of Bernalillo Planning and Zoning Department at (505) 771-7118 (Planning and Zoning); (505) 867-3311 (Town Hall general information); fax (505) 867-0481 for current turnaround.

You'll need: Certificate of Occupancy. Depending on your project, Bernalillo may also ask for: CID Multi-Purpose Building Application (Alteration/Repairs/Demolition); Certificate of Compliance. See the required-documents checklist on this page for details on each.

Bernalillo requires 1 inspection(s) for a change of occupancy / certificate of occupancy permit, in order: Final Inspection / Certificate of Occupancy Issuance. Schedule each through Town of Bernalillo Planning and Zoning Department ((505) 771-7118 (Planning and Zoning); (505) 867-3311 (Town Hall general information); fax (505) 867-0481).

Apply through Town of Bernalillo Planning and Zoning Department at 829 S. Camino del Pueblo, Bernalillo, NM 87004 (mail: P.O. Box 638, Bernalillo, NM 87004). Phone: (505) 771-7118 (Planning and Zoning); (505) 867-3311 (Town Hall general information); fax (505) 867-0481, email: pzdept@tobnm.gov. Office hours: Not separately published by the Planning and Zoning Department as of 2026-07-18; the department directs applicants to submit electronically to pzdept@tobnm.gov. General Town Hall information line: (505) 867-3311.. Official information: https://www.tobnm.gov/departments/planning_zoning/index.php.

No distinct standalone permit exists. Per Town of Bernalillo Ordinance No. 318, Section 12, no change in the existing occupancy classification of a building may be made until the Building Official issues a Certificate of Occupancy (or the Town issues a Certificate of Compliance for manufactured/mobile homes) — this is achieved through the same Building Permit/Alteration process used for construction work, not a separate application.

For site-built or modular buildings, the Building Official (New Mexico CID, acting as the Town's Certified Building Official) signs the Certificate of Occupancy after verifying all inspections and requirements. For manufactured and mobile homes, the Town itself issues a Certificate of Compliance instead. Source: Town of Bernalillo Ordinance No. 318, Section 12.

Sources & verification

Verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bernalillo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.