Change of Occupancy / Certificate of Occupancy — Bernalillo, New Mexico · Requirements sheet
Verified 2026-07-22 · Source: https://www.tobnm.gov/document_center/Public%20Notices/TC%20Packet%20-%20Ord%20No%20318%20-%20Building%20and%20Property%20Standards%20Ordinance.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Occupancy / Certificate of Occupancy in Bernalillo, New Mexico
Bernalillo has no standalone, separately-applied-for 'change of use' permit product. Per the Town's own Building and Property Standards Ordinance No. 318 (adopted 4/26/21), Section 12, no building or structure may be used or occupied, and no change in its existing occupancy classification may be made, until the Building Official has issued a Certificate of Occupancy (site-built/modular structures) or the Town has issued a Certificate of Compliance (manufactured/mobile homes). Where the occupancy change requires construction, reconstruction, alteration, repair, or conversion work, that work must go through the same CID-routed Building Permit process documented elsewhere in this file; the CO/Certificate of Compliance is the gating condition attached to that process, not a separate application.
Verified 2026-07-22 · Source
When you need this permit
- No building or structure shall be used or occupied and no change in the existing occupancy classification of a building or structure, or portion thereof, shall be made until the Building Official has issued a Certificate of Occupancy or the Town has issued a Certificate of Compliance, as applicable — Town of Bernalillo Ordinance No. 318, Section 12.A
- It is unlawful to commence the construction, reconstruction, alteration, repair, conversion, maintenance, removal, or demolition of a building or structure without first obtaining a Building Permit, if one is required by CID — Ordinance No. 318, Section 10.A; a change of occupancy classification that requires such work must be routed through the same CID Building Permit process (Alteration/Repairs/Demolition) as new construction, including the Town's mandatory zoning/floodplain pre-review sign-off
- For site-built or modular buildings, structures, or housing units, a Certificate of Occupancy is signed by the Building Official upon completion and verification of all inspections and requirements, per Ordinance No. 318, Section 12.B; the CID Building Permit Guide for Commercial Construction independently confirms no change in existing occupancy classification is permitted until the building official issues a certificate of occupancy, per 14.5.3.13 NMAC
- For manufactured or mobile homes, a Certificate of Compliance is issued by the Town instead, upon completion and verification of all inspections and requirements and prior to expiration of the time period required for skirting — Ordinance No. 318, Section 12.C
- Issuance of a Certificate of Occupancy or Certificate of Compliance is not construed as approval of any violation of a Building Code or Town ordinance, and the Building Official (or the Town, for a Certificate of Compliance) may suspend or revoke it in writing if the building, structure, or housing unit is later found in violation — Ordinance No. 318, Section 12.D
- No distinct standalone fee is published by the Town or CID for a 'change of use' or Certificate of Occupancy application itself — per Ordinance No. 318, Section 9.A, fees for inspection/permitting services performed on the Town's behalf by an entity such as CID follow that entity's own fee schedule, which is the same ICC valuation-based Building Permit fee documented in this file's Residential/Commercial Building Permit entries
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection / Certificate of Occupancy Issuance
Verification of all inspections and requirements under the applicable Building Code and Town ordinances, upon which the Building Official signs the Certificate of Occupancy (or the Town issues a Certificate of Compliance for manufactured/mobile homes), per Ordinance No. 318, Section 12.B-C.
See the full Bernalillo inspection guide — scheduling & re-inspection fees →
Tips
- Bernalillo has no standalone Change-of-Use application separate from its Building Permit — if the new occupancy classification requires construction work, that work must go through the same CID-routed Building Permit process documented elsewhere in this file, and the Certificate of Occupancy is issued as its final step.
- Manufactured and mobile homes receive a Town-issued Certificate of Compliance instead of a CID-issued Certificate of Occupancy, tied to the Placement Permit process documented elsewhere in this file.
- A previously issued Certificate of Occupancy or Certificate of Compliance is not a one-time, irrevocable approval — Ordinance No. 318 lets the Building Official (or the Town) suspend or revoke it in writing if a later violation is found.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bernalillo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bernalillo
Change of Occupancy / Certificate of Occupancy in other cities
Compare change of occupancy / certificate of occupancy fees across New Mexico →
Look up this fee in a different city →