Bernalillo building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Bernalillo, New Mexico.

Verified 2026-07-18 · Source

How to schedule

Inspections are requested through the building department below.

Address
829 S. Camino del Pueblo, Bernalillo, NM 87004 (mail: P.O. Box 638, Bernalillo, NM 87004)
Phone
(505) 771-7118 (Planning and Zoning); (505) 867-3311 (Town Hall general information); fax (505) 867-0481
Office hours
Not separately published by the Planning and Zoning Department as of 2026-07-18; the department directs applicants to submit electronically to pzdept@tobnm.gov. General Town Hall information line: (505) 867-3311.

Inspection sequence

Applies to: Commercial Building Permit (CID)

  1. 1

    Foundation Inspection

    After excavations for footings are complete and required reinforcing steel is in place.

  2. 2

    Concrete Slab / Under-Floor Inspection

    After in-slab or under-floor service equipment is in place, before concrete is placed or floor sheathing installed.

  3. 3

    Frame Inspection

    After roof, framing, fire blocking, and bracing are complete and rough electrical, plumbing, and heating are approved.

  4. 4

    Weather-Resistive Barrier Inspection

    After installation of the weather-resistive barrier, before it is covered.

  5. 5

    Final Inspection

    After finish grading and completion; final electrical, plumbing, and mechanical inspections must be conducted before the final general construction inspection. CID issues the Certificate of Occupancy after approval.

Applies to: Residential Building Permit (CID)

  1. 1

    Foundation Inspection

    After excavation for footings is complete and required reinforcing steel is in place, before concrete is placed.

  2. 2

    Concrete Slab / Under-Floor Inspection

    After in-slab or under-floor service equipment, conduit, and piping are in place, before concrete is placed or the subfloor is installed.

  3. 3

    Frame Inspection

    After roof, framing, fire blocking, and bracing are in place and rough electrical, plumbing, and heating are complete and approved.

  4. 4

    Weather-Resistive Barrier Inspection

    After installation of the weather-resistive barrier, before it is covered.

  5. 5

    Final Inspection

    After finish grading and completion; final electrical, plumbing, and mechanical inspections must be conducted first. CID issues the Certificate of Occupancy after approving the final inspection.

Applies to: Fire Sprinkler & Fire Alarm Permit (State Fire Marshal's Office)

  1. 1

    Pre-Test

    Once fire protection systems are installed per the approved plans, a full pre-test is conducted in accordance with NFPA standards; failures must be corrected and re-tested until the system passes.

  2. 2

    Final Acceptance Test

    A State Fire Inspector is dispatched to conduct a Final Acceptance Test at a scheduled date/time; approved/stamped plans, manufacturer specifications, testing documentation, and a representative from each system being tested must be on site.

Applies to: Placement Permit (Manufactured/Mobile Home & Small Structures)

  1. 1

    Placement/Setback Verification

    Zoning approval confirms placement meets required setbacks before the permit is finalized; the applicant is responsible for relocating the structure if setbacks are not met.

  2. 2

    Skirting Inspection (manufactured/mobile homes)

    Scheduled 30 days from the date of occupancy, per the Placement Permit application.

Applies to: Sign Permit

  1. 1

    Building and Safety Inspection

    Conditionally required if the sign uses steel or reinforced footings other than concrete, per the Sign Permit Application's Official Use Only section.

  2. 2

    Electrical Inspection

    Required separately through CID if the sign utilizes electricity; the Sign Permit Application refers the applicant to CID for a separate Electrical Permit.

Re-inspection fees

Residential Building Permit (CID)Re-Inspection Fee · Town of Bernalillo Fee Schedule, updated 7/8/24.
$25.00
Commercial Building Permit (CID)Re-Inspection Fee · Town of Bernalillo Fee Schedule, updated 7/8/24.
$25.00
Solar PV PermitRe-Inspection Fee · Town of Bernalillo Fee Schedule, updated 7/8/24
$25.00
EV Charger / EVSE Installation PermitRe-Inspection Fee · Town of Bernalillo Fee Schedule, updated 7/8/24
$25.00

Bernalillo building permits