Solar Photovoltaic (PV) Permit in Albuquerque, New Mexico

Verified

Required for roof-mounted, ground-mounted, or awning-mounted photovoltaic system installations in Albuquerque. Both a building permit and an electrical permit are required. Roof-mounted residential systems under 50 kW are eligible for same-day Express Permitting.

Verified 2026-07-02 · Source

From$8.00Solar collector installation (mechanical/HVAC-related fee, including related piping/ductwork/regulating devices) — see all 3 fees below

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Solar collector installation (mechanical/HVAC-related fee, including related piping/ductwork/regulating devices)Up to 1,000 sq ft: $8.00; 1,001–2,000 sq ft: $8.00; more than 2,000 sq ft: $8.00 plus $1.50 per 1,000 sq ft or fraction over 2,000 sq ft2024 City of Albuquerque Uniform Administrative Code, Table 112-C, item 20
Building Permit Fee (Table 112-A, valuation-based)Same Table 112-A formula as other building permits, based on project valuation with applicable regional modifierUAC Section 112.2 / Table 112-A; solar PV installations require a building permit priced on this schedule in addition to the electrical permit and any mechanical solar-collector fee
Electrical Permit FeePer UAC Table 112-B (administrative charge $47.00 plus applicable per-item charges for panels, disconnects, and equipment installed)UAC Table 112-B

Review timeline

013 business days

Albuquerque’s published plan-review target

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Re-Roof and Solar Inspection (Building)

    Made after installation is complete; a certified Building Inspector may review drone photos of the permitted work, with on-site follow-up if necessary

  3. 3

    Electrical Final

    When all electrical equipment is installed and wiring is completed

Tips

Frequently asked questions

How fast can I get a solar permit in Albuquerque?
Roof-mounted residential solar PV permits under 50 kW are eligible for the City's Express Permitting System, allowing same-day issuance. Larger or ground-mounted systems go through standard plan review; both a building permit and an electrical permit are required in all cases.

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Albuquerque building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Albuquerque

Solar Photovoltaic (PV) Permit in other cities

Compare solar photovoltaic (pv) permit fees across New Mexico

Project checklist — coming soon