Required for roof-mounted, ground-mounted, or awning-mounted photovoltaic system installations in Albuquerque. Both a building permit and an electrical permit are required. Roof-mounted residential systems under 50 kW are eligible for same-day Express Permitting.

Verified 2026-07-02 · Source

When you need this permit

  • Building permit and electrical permit both required for all PV installations (roof-mounted, ground-mounted, and awning-mounted)
  • Roof-mounted solar permits under 50 kW are eligible for the Express Permitting System (same-day issuance)
  • Historic Preservation District approval required as a pre-requisite if the property is within a historic overlay district
  • Site plan to scale showing PV array configuration, all supporting equipment, sub-panels, and main electrical service location
  • Electrical one-line diagram required; three-line diagram required if the system exceeds 10 kW
  • Systems exceeding 200 amps must have plans prepared and stamped by a New Mexico-licensed electrical engineer
  • Ground-mounted and awning systems require an engineering letter/calculations and foundation design certified and stamped by a New Mexico-licensed engineer
  • Documentation of a New Mexico structural engineer's review of the existing roof structure required for residential roof-mounted systems when there is more than one existing roof covering or added dead/point loads exceed specified thresholds

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Solar collector installation (mechanical/HVAC-related fee, including related piping/ductwork/regulating devices)2024 City of Albuquerque Uniform Administrative Code, Table 112-C, item 20 (rendered directly from the PDF page to confirm — a prior version of this record had $8.00 for the (b) and (c) tiers; the raw PDF text extraction shifts values by one row here, the same trap as the demolition fee on Table 112-A)
Up to 1,000 sq ft: $8.00; 1,001–2,000 sq ft: $12.00; more than 2,000 sq ft: $12.00 plus $1.50 per 1,000 sq ft or fraction over 2,000 sq ft
Building Permit Fee (Table 112-A, valuation-based)UAC Section 112.2 / Table 112-A; solar PV installations require a building permit priced on this schedule in addition to the electrical permit and any mechanical solar-collector fee
Same Table 112-A formula as other building permits, based on project valuation with applicable regional modifier
Electrical Permit FeeUAC Table 112-B
Per UAC Table 112-B (administrative charge $47.00 plus applicable per-item charges for panels, disconnects, and equipment installed)

Review timeline

Plan reviewAlbuquerque’s published plan-review target
0–13 business days

How long did your Solar Photovoltaic (PV) Permit permit actually take in Albuquerque?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Re-Roof and Solar Inspection (Building)

    Made after installation is complete; a certified Building Inspector may review drone photos of the permitted work, with on-site follow-up if necessary

  3. 3

    Electrical Final

    When all electrical equipment is installed and wiring is completed

See the full Albuquerque inspection guide — scheduling & re-inspection fees →

Tips

  • Roof-mounted solar permits under 50 kW are eligible for the Express Permitting System — same-day issuance.
  • Both a building permit and an electrical permit are required for every PV installation, roof- or ground-mounted.
  • Commercial projects must additionally follow the Albuquerque Fire Department Solar Photovoltaic System Installation Guidelines for access pathway clearances.
  • Confirm whether the property sits in a Historic Preservation District before applying — approval from that office is a pre-requisite if so.

Frequently asked questions

Albuquerque requires a solar photovoltaic (pv) permit for: Building permit and electrical permit both required for all PV installations (roof-mounted, ground-mounted, and awning-mounted); Roof-mounted solar permits under 50 kW are eligible for the Express Permitting System (same-day issuance); Historic Preservation District approval required as a pre-requisite if the property is within a historic overlay district; Site plan to scale showing PV array configuration, all supporting equipment, sub-panels, and main electrical service location; Electrical one-line diagram required; three-line diagram required if the system exceeds 10 kW; Systems exceeding 200 amps must have plans prepared and stamped by a New Mexico-licensed electrical engineer; Ground-mounted and awning systems require an engineering letter/calculations and foundation design certified and stamped by a New Mexico-licensed engineer; Documentation of a New Mexico structural engineer's review of the existing roof structure required for residential roof-mounted systems when there is more than one existing roof covering or added dead/point loads exceed specified thresholds. If your project isn't listed, confirm with City of Albuquerque Planning Department — Building Safety Division at (505) 924-3320 before starting work.

In Albuquerque, the published Solar collector installation (mechanical/HVAC-related fee, including related piping/ductwork/regulating devices) is: Up to 1,000 sq ft: $8.00; 1,001–2,000 sq ft: $12.00; more than 2,000 sq ft: $12.00 plus $1.50 per 1,000 sq ft or fraction over 2,000 sq ft. Additional published fees: Building Permit Fee (Table 112-A, valuation-based) — Same Table 112-A formula as other building permits, based on project valuation with applicable regional modifier; Electrical Permit Fee — Per UAC Table 112-B (administrative charge $47.00 plus applicable per-item charges for panels, disconnects, and equipment installed). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Albuquerque's published plan-review target for a solar photovoltaic (pv) permit is 0–13 business days.

You'll need: Building Permit Application (Solar PV); Site Plan (to scale); Electrical One-Line (or Three-Line) Diagram; Equipment Schedule. See the required-documents checklist on this page for details on each.

Albuquerque requires 3 inspection(s) for a solar photovoltaic (pv) permit, in order: Rough Electrical, Re-Roof and Solar Inspection (Building), Electrical Final. Schedule each through City of Albuquerque Planning Department — Building Safety Division ((505) 924-3320).

Apply through City of Albuquerque Planning Department — Building Safety Division at Plaza Del Sol Building, 600 2nd St. NW, Suite 190, Albuquerque, NM 87102. Phone: (505) 924-3320. Office hours: Building Permits & Plan Review: 8:00 AM – 5:00 PM, Monday–Friday. Building/Electrical/Plumbing/Mechanical Inspections & Trade Permits: 7:30 AM – 4:30 PM, Monday–Friday. The Building Safety permit counter is closed every Friday from 7:30 AM to 11:30 AM.. Official information: https://www.cabq.gov/planning/building-safety-division.

Albuquerque, New Mexico has adopted: 2021 New Mexico Commercial Building Code — adopted statewide by the NM Construction Industries Commission (NMAC Title 14), effective in Albuquerque December 14, 2023; 2021 New Mexico Residential Building Code — adopted statewide by the NM Construction Industries Commission (NMAC Title 14), effective in Albuquerque December 14, 2023; 2021 New Mexico Existing Building Code — effective in Albuquerque December 14, 2023; 2020 New Mexico Electrical Code — effective in Albuquerque September 28, 2023; 2021 New Mexico Mechanical Code, including Appendixes A, B, C, and D; 2021 New Mexico Plumbing Code, including Appendixes A, B, C, D, E, F, I, K, and L; 2012 New Mexico Swimming Pool, Spa and Hot Tub Code; 2012 New Mexico Solar Energy Code; 2021 New Mexico Residential Energy Conservation Code (includes EV-charging-readiness requirements adopted by the Construction Industries Commission, required on new construction starting July 30, 2024); 2021 New Mexico Commercial Energy Conservation Code (includes EV-charging-infrastructure parking requirements, required on new construction starting July 30, 2024); 2021 New Mexico Earthen Building Materials Code; 2021 New Mexico Historic Earthen Buildings Code; New Mexico Boiler Code; 2023 Uniform Administrative Code of the City of Albuquerque (ROA 1994, Chapter 14, Article 1) — the City's local administrative amendment governing permitting, fees, and inspections; effective February 2, 2024; a 2024 edition (Exhibit A) is the current administrative chapter on file with Building Safety; City of Albuquerque Ordinance O-2022-024 (Council Bill O-22-23) — adopted the Uniform Administrative Code and technical codes, repealing the prior Chapter 14, Article 1, ROA 1994. Local amendments apply — see the Albuquerque overview page for the full list.

Roof-mounted residential solar PV permits under 50 kW are eligible for the City's Express Permitting System, allowing same-day issuance. Larger or ground-mounted systems go through standard plan review; both a building permit and an electrical permit are required in all cases.

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Albuquerque building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.