Commercial Building Permit (New Construction & Additions) — Albuquerque, New Mexico · Requirements sheet
Verified 2026-08-01 · Source: https://www.cabq.gov/planning/building-safety-division
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction & Additions) in Albuquerque, New Mexico
Required for new commercial buildings, commercial additions, and first-time or change-of-occupancy projects in Albuquerque. Issued by the City's Building Safety Division under the Uniform Administrative Code, which locally administers the statewide 2021 New Mexico Commercial Building Code. Plans are routed through a formal multi-division review (IBC/building, Zoning, Fire Prevention, Solid Waste, Environmental Health, Transportation Development, and Hydrology) and applications are submitted through the ABQ-PLAN electronic plan review portal.
Verified 2026-08-01 · Source
When you need this permit
- All new commercial construction, additions, and first-time or change-of-occupancy projects require a building permit and full plan review under the Uniform Administrative Code and the New Mexico Commercial Building Code
- All construction plans must be certified by a Registered New Mexico Professional Architect and/or Engineer — documents must be signed, sealed, and dated by the professional who prepared them
- Permit is issued only to a general contractor holding a New Mexico GB-98 license; out-of-state contractors may need a TS-43 surety bond verification form signed by NM Taxation and Revenue Contractor
- Plans are routed to seven review divisions: IBC (building code, structural, accessibility), Zoning (IDO compliance, parking, landscaping, setbacks), Fire Prevention (IFC/NFPA — separate 'Fire 1' site plan and 'Fire 2' floor plan sheets), Solid Waste (refuse enclosure, collection-vehicle access), Environmental Health (food, pool, air quality), Transportation Development (site access, parking circulation, drive-throughs), and Hydrology (flood zone, grading and drainage)
- Energy Code checklist is required on all submittals; code data sheet must state occupancy, separated/non-separated use, type of construction, square footage of each building/tenant space, allowable area calculation, and energy code path
- Local design criteria: ground snow load 20 psf, frost line depth 16 inches, wind speed 115 mph (3-second gust); seismic design category determined by the engineer
- Electrical plans must be sealed by a NM-registered PE when the installation exceeds 200A; mechanical plans when mechanical valuation exceeds $50,000 or the building exceeds 2 stories; plumbing plans when fixture units exceed the capacity of a 4-inch building drain (UPC Table 7-3) or the building exceeds 2 stories
- Phase projects require a phase plan clearly indicating the work of each individual phase; each phase is assigned a separate permit number and fees per Table 112-A
- If a Traffic Circulation Layout (TCL) plan or a Grading and Drainage plan is required, it should be approved by Transportation Development / Hydrology before submitting the building permit set
- Application expires if no permit is issued within 180 days of submittal (UAC Section 110.5); one 180-day extension may be granted on written request
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 11 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation Inspection
First interim inspection during construction, called in by the contractor
- 2
Framing Inspection
Structural framing inspection before concealment
- 3
Plumbing Inspection
Rough plumbing inspection under the associated trade permit
- 4
Mechanical Inspection
Rough mechanical/HVAC inspection under the associated trade permit
- 5
Electrical Inspection
Rough electrical inspection under the associated trade permit
- 6
Insulation Inspection
After insulation is installed, before covering
- 7
Structural Inspection
Structural systems inspection per the approved plans
- 8
Fire Protection Inspection
Fire protection systems inspection
- 9
Final Inspections — Five City Agencies
After construction is complete, Zoning, Solid Waste, Environmental Health, Hydrology, and the Fire Marshal each inspect and approve the final construction; the Certificate of Occupancy is then prepared and must be posted conspicuously in the business
See the full Albuquerque inspection guide — scheduling & re-inspection fees →
Tips
- Schedule inspections through the Building Inspections office at (505) 924-3320 (Plaza Del Sol, Basement, Suite 190, 7:30 AM–4:30 PM Mon–Fri) or via your ABQ-PLAN dashboard.
- The City's Permit Timeline dashboard reports commercial building permits averaging 18 business days to issuance; FasTrax expedited review (3x plan review fee, $1,000 minimum) averages about 10 days for the initial review with a guaranteed completion date.
- Submit any required Traffic Circulation Layout (TCL) plan to Transportation Development and any required Grading and Drainage plan to Hydrology for approval before submitting the building permit set — building permit approval depends on them.
- A Certificate of Shell Completion (UAC Section 115.5) is available for shell buildings; individual tenant spaces are then finished under separate tenant improvement permits, with first-time occupancy of a space reviewed under the new-commercial/change-of-occupancy track.
- A Temporary Certificate of Occupancy ($100) is valid for 30 days and can be extended in 30-day increments up to 12 months total, with all fire/life-safety, exiting, sanitary, parking, and accessibility provisions approved for the occupied portion.
- The City's New Commercial Construction handout (last revised 2019) lists superseded code editions — the currently enforced technical codes are the 2021 New Mexico suite (Commercial Building, Mechanical, Plumbing, Energy Conservation Codes, and the 2020 NM Electrical Code); the handout's submittal and routing requirements remain the published process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Albuquerque building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Albuquerque.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Albuquerque
Commercial Building Permit (New Construction & Additions) in other cities
Compare commercial building permit (new construction & additions) fees across New Mexico →
Look up this fee in a different city →