Albuquerque building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Albuquerque, New Mexico.
Verified 2026-07-02 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Plaza Del Sol Building, 600 2nd St. NW, Suite 190, Albuquerque, NM 87102
- Phone
- (505) 924-3320
- Office hours
- Building Permits & Plan Review: 8:00 AM – 5:00 PM, Monday–Friday. Building/Electrical/Plumbing/Mechanical Inspections & Trade Permits: 7:30 AM – 4:30 PM, Monday–Friday. The Building Safety permit counter is closed every Friday from 7:30 AM to 11:30 AM.
- Website
- Official site
Published scheduling rules
- All permit applications are submitted online through ABQ-PLAN. The Building Safety permit counter (Plaza Del Sol, Suite 190, 600 2nd St. NW) is closed every Friday from 7:30 AM to 11:30 AM, but ABQ-PLAN and inspection scheduling remain available. (General)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation Inspection
After excavation for footings is complete and required reinforcing steel is in place; forms in place for concrete foundations
- 2
Foundation Insulation Inspection
After insulation has been installed around the perimeter of slab-on-grade floors
- 3
Frame Inspection
After roof decking/underlayment, all framing, fire blocking, draft stopping, bracing, and framed openings are in place, and pipes, wiring, chimneys, ductwork, and vents are approved
- 4
Frame Insulation Inspection
After insulation and vapor barriers have been installed in frame walls, floors, and ceilings or roofs
- 5
Exterior Lath / Wallboard Inspection
After exterior lathing is in place but before plastering; wallboard inspection on firewalls, wet areas, and shear walls before joints/fasteners are taped and finished
- 6
Final Inspection
After the building is completed and ready for occupancy, called for by the permit holder before occupancy
Applies to: Accessory Dwelling Unit (ADU / Casita) Permit
- 1
Foundation
Footings and foundation before concrete pour
- 2
Framing
Structural framing complete
- 3
Insulation
Insulation installed before wall cover
- 4
Electrical / Plumbing / Mechanical
Trade rough-ins inspected under their respective trade permits
- 5
Final Inspection
All work complete and ready for occupancy
Applies to: Electrical Permit
- 1
Underground
After underground conduits, cables, and conductors are installed and before covering
- 2
Slab
After conduits, boxes, grounding electrode conductors, or electrical equipment installed within a concrete slab, before pour
- 3
Rough-In
After conduits, cables, wires, cabinets, and boxes are installed and before insulation or wall/ceiling cover; splicing complete, neutrals/grounds terminated
- 4
Pre-Final
Service equipment, conduits, conductors, bonding jumpers, and points of attachment installed; at least one grounding electrode installed
- 5
Final
When all electrical equipment is installed and wiring is completed
Applies to: Plumbing / Mechanical Permit
- 1
Building or House Sewer
Sewer inspected before backfill, minimum depth 12 inches, properly graded, per Uniform Plumbing Code Table 717.1
- 2
Sanitary Rough-In
All drain/waste/vent piping below first floor tested (water fill or 5 psi air test, 15 minutes)
- 3
Rough Piping / Heating Top-Out
After piping and ductwork installed, before covering or concealment; includes gas line test
- 4
Plumbing / Mechanical Final
When all plumbing/mechanical equipment is complete, fixtures installed and ready for use
Applies to: Residential Addition / Alteration / Remodel Permit
- 1
Frame Inspection
After framing, fire blocking, bracing, and framed openings are complete and MEP rough-ins are approved
- 2
Frame Insulation Inspection
After insulation and vapor barriers installed
- 3
Exterior Lath / Wallboard Inspection
Before plastering or before wallboard joints/fasteners are taped and finished on firewalls, wet areas, and shear walls
- 4
Final Inspection
After work is complete and ready for occupancy
Applies to: Certificate of Occupancy / Change of Occupancy
- 1
Final Building/Trade Inspections
Building, electrical, plumbing, and mechanical final inspections completed and approved
- 2
Fire Marshal Final Inspection
Fire/life safety issues, fire protection systems, exiting, sanitary facilities, parking spaces, and accessibility provisions confirmed compliant (required before a Temporary Certificate of Occupancy per UAC Section 115.4)
- 3
Certificate of Occupancy Verification
Planning Research Coordinator verifies that all required City department/division approvals are recorded before preparing and issuing the Certificate of Occupancy
Applies to: Fire Alarm & Automatic Sprinkler System Permit (Albuquerque Fire Rescue)
- 1
Rough-In / Underground Inspection
Sprinkler underground piping and rough-in, and fire alarm wiring/device rough-in, inspected before concealment
- 2
Fire Protection System Acceptance Test
Functional/acceptance test of the completed fire alarm and/or sprinkler system, witnessed by the Fire Marshal's Office; contact 505-924-3611 for new-construction inspections or fire protection system acceptance tests
- 3
Final Inspection
Fire Marshal final sign-off required before a Temporary or final Certificate of Occupancy can be issued (UAC Section 115.4 requires all fire/life-safety and fire protection system approvals before a Temporary CO)
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Re-Roof and Solar Inspection (Building)
Made after installation is complete; a certified Building Inspector may review drone photos of the permitted work, with on-site follow-up if necessary
- 3
Electrical Final
When all electrical equipment is installed and wiring is completed
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
After conduits, cables, wires, cabinets, and boxes are installed and before insulation or wall/ceiling cover
- 2
Final
Charger installed, circuit complete, unit energized
Applies to: Sign Permit
- 1
Footing Inspection
Required for all signs having footings
- 2
Final Inspection
Required for all signs
Applies to: Wall / Fence Permit
- 1
Footing Inspection
Required before concrete pour for footings supporting the wall or fence
- 2
Final Inspection
After construction complete
Final inspection only: Demolition Permit, Re-Roof Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Albuquerque building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Albuquerque building permits
Get alerts for Albuquerque
We'll email you when Albuquerque's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.