Certificate of Occupancy / Change of Occupancy in Albuquerque, New Mexico
Required before any building, structure, or portion thereof may be used or occupied in Albuquerque, and before any change in the existing occupancy classification or use of a building may be made. Issued by the Building Official under UAC Section 115 after final inspection approvals are secured from every City department or division involved in code enforcement (Building Safety trades, Zoning, Hydrology, Solid Waste, Environmental Health, and the Fire Marshal's Office, as applicable).
Verified 2026-07-22 · Source
When you need this permit
- Buildings or structures shall not be used or occupied, nor shall a change in the existing occupancy classification of a building or structure (or portion thereof) be made, until the Building Official has issued a Certificate of Occupancy (UAC Section 115.1)
- Changes in the character or use of a building shall not be made except as specified in the Building Code (UAC Section 115.2, 'Change in Use')
- A request for a Certificate of Occupancy is made by the owner or agent after final inspection approvals have been secured from all City departments/divisions involved in enforcement of pertinent codes, ordinances, or laws (UAC Section 115.3)
- A Certificate of Shell Completion (where applicable) must be issued before a Certificate of Occupancy or Temporary Certificate of Occupancy can be issued (UAC Section 115.5)
- The Certificate of Occupancy must be posted in a conspicuous place on the premises and may not be removed except by the Building Official (UAC Section 115.6)
- A permit becomes null and void if the permittee has not requested a Certificate of Occupancy within 180 days of the final inspection (UAC Section 111.4); operating without a valid Certificate of Occupancy may result in penalties under Section 9 of the Uniform Administrative Code
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Building/Trade Inspections
Building, electrical, plumbing, and mechanical final inspections completed and approved
- 2
Fire Marshal Final Inspection
Fire/life safety issues, fire protection systems, exiting, sanitary facilities, parking spaces, and accessibility provisions confirmed compliant (required before a Temporary Certificate of Occupancy per UAC Section 115.4)
- 3
Certificate of Occupancy Verification
Planning Research Coordinator verifies that all required City department/division approvals are recorded before preparing and issuing the Certificate of Occupancy
See the full Albuquerque inspection guide — scheduling & re-inspection fees →
Tips
- Schedule your Certificate of Occupancy appointment through the City's online portal in advance to reduce wait times, per the Building Safety Division's Commercial Inspections guidance.
- A Temporary Certificate of Occupancy is valid for 30 days and can be extended in 30-day increments up to a maximum of 12 months total; an additional Temporary CO fee is due for each extension.
- If your project was permitted as a shell building, a Certificate of Shell Completion must be issued before a Certificate of Occupancy or Temporary Certificate of Occupancy can be granted.
- A change of use or change of occupancy classification is processed through the same Certificate of Occupancy mechanism, not a separate 'change of use permit' product — but any construction needed to accomplish the change still requires its own building permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Albuquerque building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Albuquerque
Certificate of Occupancy / Change of Occupancy in other cities
Compare certificate of occupancy / change of occupancy fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Albuquerque project checklist
Describe your project once and get every permit, document, and fee it triggers in Albuquerque — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →