Certificate of Occupancy / Change of Use / Final Routing — Bozeman, Montana · Requirements sheet
Verified 2026-07-22 · Source: https://www.bozemanmt.gov/departments/community-development/development-center/occupancy-process
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Certificate of Occupancy / Change of Use / Final Routing in Bozeman, Montana
Bozeman's Certificate of Occupancy (CO) and Final Routing process. A CO is required for new commercial construction, a Change In Use, buildings with 5 or more dwelling units, and buildings that are 3 or more stories. Residential single-family homes, townhomes, or duplexes of 3 stories or less do not go through this process — they request a standard final inspection instead. Administered by the Building Division with sign-off routed to applicable city departments.
Verified 2026-07-22 · Source
When you need this permit
- A Certificate of Occupancy (CO) is required for: New Commercial Construction, Change In Use, buildings with 5 or more dwelling units, and buildings that are 3 or more stories
- Residential Single Family Homes, Townhomes, or Duplexes of 3 stories or less do NOT go through the CO/Occupancy process — instead request a standard final inspection via the Inspection Request Form
- Occupancy/Final Routing must be requested a minimum of 4 weeks before intended occupancy, using the Final Routing / Occupancy Request Form
- Step 1: All Final Building and Fire Inspections must be scheduled and approved via the Inspection Request Form before occupancy can be requested
- Step 2: Submit the Final Routing / Occupancy Request Form; the request routes to applicable departments based on building type and scope, each of which conducts an onsite review
- Certification letters are required from the project's architect, civil engineer, and landscape architect/design professional, confirming all work was inspected and completed to approved plans; emailed to planningtech@bozemanmt.gov referencing the planning project number, before the city's site inspections
- A Water Backflow and Sprinkler Backflow test is required for any project needing a CO
- Step 3 (if applicable): An Improvement Agreement (IA) can financially guarantee completion of incomplete minor site improvements (e.g., landscaping/hardscape); IA approval averages two weeks and must be recorded with the County Clerk and Recorder before occupancy sign-off
- Any changes from the approved plan require a Modification Application, approved by the Planning Division prior to sign-off
- Final Routing (a lighter process than a full CO) applies to building permits that don't require a CO but previously went through Planning/Zoning review (e.g., Site Plan, Subdivision, PDZ)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Building and Fire Inspections
Scheduled via the Inspection Request Form; occupancy is contingent on ALL final inspections being conducted and approved
- 2
Department Onsite Reviews
Each applicable city department (varies by building type/scope) conducts an onsite review and either approves or issues a corrections list
- 3
Water Backflow and Sprinkler Backflow Test
Required for all projects needing a Certificate of Occupancy
See the full Bozeman inspection guide — scheduling & re-inspection fees →
Tips
- Submit the Final Routing/Occupancy Request Form a minimum of 4 weeks before your intended occupancy date — the process cannot be compressed after the fact.
- Get certification letters from your architect, civil engineer, and landscape architect emailed to planningtech@bozemanmt.gov (referencing the planning project number) BEFORE the city's site inspections — they're a prerequisite, not a formality.
- If minor site improvements like landscaping aren't finished yet, ask about an Improvement Agreement (IA) rather than delaying occupancy — but budget about two weeks for IA approval and recording with the County Clerk and Recorder.
- Once every department has signed off, the Building Department allows itself 5 business days to actually issue the Certificate of Occupancy — plan your move-in date accordingly.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bozeman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bozeman
Certificate of Occupancy / Change of Use / Final Routing in other cities
Compare certificate of occupancy / change of use / final routing fees across Montana →
Look up this fee in a different city →
Now live
Build your Bozeman project checklist
Describe your project once and get every permit, document, and fee it triggers in Bozeman — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →