Commercial Building Permit (New Construction, Addition, Tenant Improvement) — Bozeman, Montana · Requirements sheet
Verified 2026-08-26 · Source: https://www.bozemanmt.gov/departments/community-development/development-center/building-checklists-forms-and-guides
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction, Addition, Tenant Improvement) in Bozeman, Montana
Required for new commercial structures, additions of square footage to an existing commercial structure, and tenant improvement remodels of existing commercial space in Bozeman. The City's own checklist page groups these three scopes under a single 'Commercial (IBC Code)' category, which also covers triplexes, fourplexes, multifamily buildings of 5 or more dwellings, and any residential project requiring IBC compliance. Reviewed under the 2021 International Building Code (IBC) through the ProjectDox electronic plan review portal by the City of Bozeman's own certified Building Division, not by Montana DLI.
Verified 2026-08-26 · Source
When you need this permit
- Applies to a new commercial structure (Commercial New Build/Construction), added square footage to an existing commercial structure (Commercial Addition), or remodeling an existing commercial structure without adding square footage (Commercial Tenant Improvement)
- Also governs triplexes, fourplexes, multifamily buildings of 5+ dwellings, and any residential project that requires IBC compliance, per the City's own 'Commercial (IBC Code)' checklist grouping
- Submit through ProjectDox (electronic plan review) after creating a permit application via the online portal; drawings uploaded as PDF, landscape orientation, one page per file
- 2021 Commercial Checklist must be satisfied before submittal is accepted at pre-screen
- Landscape & Irrigation Self-Certification Form required for new construction
- Water Service Fixture Count form required for new construction, or for an addition/tenant improvement that adds or removes water fixtures; counts over 39 require confirmation from City Shops (582-3200) that the main will support a larger meter
- Acknowledgment of Access Requirements form required for new construction and additions
- Special Inspection & Testing Form and Sump Drain Policy acknowledgment required for new construction and additions
- Storm Water Permit required for new construction and additions (applied for separately through the City's stormwater program)
- Preliminary Soils Analysis, Truss/Structural Calculations, and Spec Sheets required as construction-related documents for new construction and additions
- If Fire Suppression & Alarms are part of the permit, they must be submitted, approved, and issued by the City of Bozeman before framing inspections
- A representative must physically visit the Professional Building office (20 East Olive St.) for permit issuance even though no paper plans need to be brought in for stamping
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
FY 2027 Building Division Fee Schedule (PDF, effective August 1st, 2026), page 1 (Table A: ICC Building Valuation Data - Square Foot Construction Costs, February 2026, by Occupancy Group and Construction Type, e.g. Show full citationHide
FY 2027 Building Division Fee Schedule (PDF, effective August 1st, 2026), page 1 (Table A: ICC Building Valuation Data - Square Foot Construction Costs, February 2026, by Occupancy Group and Construction Type, e.g. B Business Type IIIA = $250.17/sq ft) and page 2 ('How to Calculate Your Permit Fee - New Square Footage' and Table B). Table B (Building Valuation Cost Modifier: % of ICC Table Value) lists, for 'New Construction or Addition': IBC 50%, IRC 50%, FY25 60%, FY26 70%, FY27 80%; for 'Shell Only Building': IBC 40%, IRC N/A, FY25 48%, FY26 56%, FY27 64%. The FY27 (current) column values of 80% and 64% are the Cost Modifiers presently applied, per this same schedule's worked formula, which the City applies to residential (IRC) new-square-footage permit fees the same way. Governing authority: Bozeman Municipal Code Sec. 10.02.020, as amended by Ordinance 2143 (2023); Resolution 5287 (April 2021) adopted the ICC valuation methodology.FY 2027 Building Division Fee Schedule (PDF), page 3, Table D (Plan Review Fees), rows 'Foundation Only Plan Review'; Show full citationHide
FY 2027 Building Division Fee Schedule (PDF), page 3, Table D (Plan Review Fees), rows 'Foundation Only Plan Review'; marked n/a for IRC. Foundation Only is one of the new permit categories added by Resolution 5517 (September 2023), letting a large commercial project begin foundation work while the full building plan set is still under review.FY 2027 Building Division Fee Schedule (PDF), page 3, Table D, row 'Revisions During Construction/Post Approved Plans': IBC Min $250 + $125/hr over 2 hours (IRC: Min $125 + $125/hr over 1 hour); Show full citationHide
FY 2027 Building Division Fee Schedule (PDF), page 3, Table D, row 'Revisions During Construction/Post Approved Plans': IBC Min $250 + $125/hr over 2 hours (IRC: Min $125 + $125/hr over 1 hour); additional plan check/permit fees may apply if project valuation increases due to the revision.City of Bozeman Fire Department Basic Fee Schedule (PDF), 'FIRE PROTECTION, FIRE & LIFE SAFETY,' effective January 1, 2024, Plan Review Schedule, 'Fire Sprinkler Systems NFPA 13 and 13R' table. Show full citationHide
City of Bozeman Fire Department Basic Fee Schedule (PDF), 'FIRE PROTECTION, FIRE & LIFE SAFETY,' effective January 1, 2024, Plan Review Schedule, 'Fire Sprinkler Systems NFPA 13 and 13R' table. Billed and collected by the Bozeman Fire Department separately from the Building Division's commercial permit fee; fire suppression/alarm plans must be approved and issued before the framing inspection on the associated building permit.City of Bozeman 2026 Impact Fee Schedule (PDF, Calendar Year 2026_v1, effective January 1, 2026), 'Transportation Impact Fee' page, 'Non-Residential (Unit descriptor)' table. Show full citationHide
City of Bozeman 2026 Impact Fee Schedule (PDF, Calendar Year 2026_v1, effective January 1, 2026), 'Transportation Impact Fee' page, 'Non-Residential (Unit descriptor)' table. Figures confirmed identical across the schedule version linked live from the City's Impact Fees page (Calendar Year 2026_v1/v2 combined PDF) and an earlier-dated capture of the same page; no repealed or superseded figure was found for this table. Projects within a Trip Exchange District (TED) are charged less than these listed rates; this adjustment applies only to transportation charges. One-time fee, due at building permit issuance; Resolution 4433 allows deferring payment of the transportation impact fee until issuance of a certificate of occupancy.Review timeline
Inspection process
- 1
Fire Suppression/Alarm Plan Approval
Where fire suppression or alarm systems are part of the permit, plans must be submitted, reviewed, and approved/issued before the framing inspection
- 2
Footing/Foundation
Requires a Final Observation (geotechnical) Report submitted prior to this inspection
- 3
Framing
Structural framing inspection before insulation or wall cover
- 4
Final
All work complete per approved, city-stamped plans; required before a Certificate of Occupancy can be requested
See the full Bozeman inspection guide — scheduling & re-inspection fees →
Tips
- Bozeman's own checklist groups Commercial New Build/Construction, Commercial Addition, and Commercial Tenant Improvement under one 'Commercial (IBC Code)' category, which also covers triplexes, fourplexes, multifamily buildings of 5 or more dwellings, and any residential project needing IBC compliance -- not just standalone commercial buildings.
- One Structure = One Permit -- an additional structure on the same lot needs its own separate permit.
- A large-valuation commercial project can pull a Foundation Only permit (with its own tiered plan review fee) to start foundation work before the full building plan set finishes review.
- Fire suppression and fire alarm plans are billed under the Bozeman Fire Department's own Basic Fee Schedule, separate from the Building Division's commercial permit fee, and must be approved and issued before the framing inspection -- do not wait until framing to submit them.
- Revising an already-approved and stamped commercial (IBC) plan set costs a minimum of $250 (plus $125/hour beyond 2 hours of review), higher than the $125 minimum for residential (IRC) plan revisions.
- Commercial construction is also subject to Transportation, Water, Wastewater, and Fire/EMS impact fees, due at building permit issuance (Transportation can instead be deferred to Certificate of Occupancy under Resolution 4433). Projects inside a Trip Exchange District pay a reduced Transportation Impact Fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-26.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bozeman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Bozeman.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Bozeman
Commercial Building Permit (New Construction, Addition, Tenant Improvement) in other cities
Look up this fee in a different city →
Now live
Build your Bozeman project checklist
Describe your project once and get every permit, document, and fee it triggers in Bozeman — in one checklist. Free, for any city and any number of projects.
Get started →