Certificate of Occupancy in Manhattan, Montana

Required before occupancy of any residential or commercial building or structure in Manhattan following construction, addition, remodel, or other building-permitted work. Issued by the Building Department after a final inspection confirms the work complies with the approved plans and permit. Manhattan has no standalone 'change of use' permit application distinct from this Certificate of Occupancy / final-inspection process and the zoning-use compliance check built into the Town's Building Permit Zoning Review form.

Reviewed 2026-07-22 · Source

When you need this permit

  • Builders must notify the Building Department for final inspection of all projects (residential and commercial) before occupancy of the structure, per the Town's 'How To Obtain A Building Permit' guide
  • For commercial projects, the Building Department must be notified two weeks prior to the desired occupancy date
  • Most lending institutions require a final inspection and Certificate of Occupancy from the Building Department prior to final release of construction funds
  • The Building Official may, at his discretion, approve a temporary Certificate of Occupancy for a commercial building — allowing the owner to open to the public before all conditions of approval are met, generally where only landscaping improvements remain outstanding; in such cases, some improvements may need to be financially guaranteed
  • Change of use / change of occupancy for an existing building without new construction is not addressed by a standalone Town application; the Town's Building Permit Zoning Review form (used for the zoning-permit component of the combined building permit) includes a 'Use: Permitted / Not Permitted / Requires Conditional Use Permit' determination made by the Zoning Administrator, which is the closest documented mechanism for a use-compliance review — but no separate 'Change of Use Permit' product, application, or fee was found published

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Certificate of Occupancy permit actually take in Manhattan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Building Official confirms completed work matches approved plans and permit before issuing a Certificate of Occupancy; commercial projects require two weeks' advance notice to the Building Department

See the full Manhattan inspection guide — scheduling & re-inspection fees →

Tips

  • Manhattan has no standalone 'Change of Use' permit or application — a use change on an existing building is evaluated through the 'Use: Permitted / Not Permitted / Requires Conditional Use Permit' determination on the Town's Building Permit Zoning Review form, and/or through the Certificate of Occupancy final-inspection process if paired with any building work.
  • Commercial occupants must notify the Building Department at least two weeks before their desired occupancy date — plan the final inspection request accordingly.
  • A temporary Certificate of Occupancy is available at the Building Official's discretion for commercial buildings with only minor outstanding items (commonly landscaping) — ask directly rather than assuming it isn't available.
  • Lenders commonly require a final inspection and Certificate of Occupancy before releasing construction funds — factor this into project financing timelines.

Frequently asked questions

For commercial projects, the Town's guide asks that the Building Department be notified two weeks before the desired occupancy date. No separate advance-notice period is published for residential final inspections beyond the Town's general rule that inspections be requested by phone no later than 4:30 PM the day before.

Manhattan does not publish a plan-review timeline for this permit. Contact Town of Manhattan Building Division at (406) 284-3235 for current turnaround.

You'll need: Final Inspection Request. See the required-documents checklist on this page for details on each.

Manhattan requires 1 inspection(s) for a certificate of occupancy permit, in order: Final Inspection. Schedule each through Town of Manhattan Building Division ((406) 284-3235).

Apply through Town of Manhattan Building Division at 207 South Sixth Street (P.O. Box 96), Manhattan, MT 59741. Phone: (406) 284-3235, email: townofmanhattan@gmail.com. Office hours: Town Office, 207 S. 6th St., Manhattan, MT 59741, Monday-Friday 8:30 AM - 5:00 PM (Town Office/Zoning: 406-284-3235; Building Official Brandon Yung: 406-595-9300, byung.town@gmail.com). Official information: https://www.townofmanhattan.com/building-zoning.

Manhattan, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code (building, plumbing, electrical, mechanical, swimming pool, etc.); non-certified areas/trades fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list (bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf) and Current Codes page (bsd.dli.mt.gov/building-codes-permits/current-codes).; Manhattan is a Montana DLI-certified jurisdiction for Building (B), Mechanical (M), Plumbing (P), Electrical (E), AND Swimming Pool (SP) within Manhattan town limits — full certification across all five trade categories, matching Billings and Belgrade. Certified building official on file with DLI: Brandon Yung. Verified directly against the DLI's official 'Certified City, County and Town Programs' roster (PDF, updated 2026-04-22): the Manhattan row reads 'Manhattan | B, M, P, E, SP | Brandon Yung | | City Limits'. Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf; Manhattan Town Code section 12-1-1 (Adoption Of The Model Technical Codes And Administrative Rules): 'The current editions of the model uniform technical codes, to include, but not be limited to, building, plumbing, electrical and mechanical, and all accompanying appendices, amendments and modifications adopted or required to be adopted by the building codes bureau, Montana department of labor and industry (or its successor) as set out in the administrative rules of Montana, as amended from time to time by the building codes bureau, are adopted by reference.' This incorporates the same statewide code editions used by other DLI-certified Montana jurisdictions (2021 IBC, 2021 IRC, 2021 IMC, 2021 IFGC, 2021 IEBC, 2021 UPC, 2021 IECC, 2021 ISPSC, 2020 NEC, ICC A117.1-2017), automatically updated as the Building Codes Bureau amends ARM Title 24, Chapter 301 (effective 60 days after a signed mayoral administrative order per 12-1-1.C). Source: Manhattan Town Code 12-1-1, https://codelibrary.amlegal.com/codes/manhattanmt/latest/manhattan_mt/0-0-0-6397 (Ord. 287, 2-10-2004; amd. Ord. 299, 11-9-2004; Ord. 06-007, 6-13-2006; Ord. 24-005, 5-9-2024); Manhattan Town Code section 12-1-2.C: 'Plans shall be reviewed and inspections made in accordance with the rules and procedures of the Bozeman city building code enforcement division.' This is a notable local arrangement — Manhattan's own Building Official (Brandon Yung) issues permits locally under Manhattan's DLI certification, but plan review and inspection procedure follows the City of Bozeman Building Division's rules and procedures. Source: Manhattan Town Code 12-1-2, https://codelibrary.amlegal.com/codes/manhattanmt/latest/manhattan_mt/0-0-0-6411 (Ord. 297, 8-9-2004; amd. Ord. 24-005, 5-9-2024); Manhattan Town Code Title 12, Chapter 1 (Building Codes) is available at https://codelibrary.amlegal.com/codes/manhattanmt/latest/manhattan_mt/0-0-0-6392; Manhattan Town Code Title 10, Chapter 2 (Administration and Enforcement / Zoning Permit) at https://codelibrary.amlegal.com/codes/manhattanmt/latest/manhattan_mt/0-0-0-3289. Local amendments apply — see the Manhattan overview page for the full list.

No standalone Change of Use permit application, fee, or checklist was found published by the Town. Use compliance for an existing building is assessed through the 'Use: Permitted / Not Permitted / Requires Conditional Use Permit' section of the Town's Building Permit Zoning Review form and/or the Certificate of Occupancy final-inspection process if the change involves any building work.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Manhattan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.