Solar PV / Alternative Energy Permit (State-Issued) in City of Deer Lodge, Montana
Required for installation of grid-tied residential or commercial rooftop/ground-mounted solar photovoltaic systems in the City of Deer Lodge. Because Deer Lodge (City) is DLI-certified for Building (B) RESIDENTIAL ONLY and holds no Electrical certification, the electrical/interconnection portion of any solar PV installation is issued directly by the Montana DLI Building Codes Bureau in Helena as an Application for Alternative Energy Permit — the same statewide form used for solar, wind, and hydro systems, already cited as a document option on this file's electrical-permit entry — not by the City of Deer Lodge. The City's own permit portal confirms electrical permits generally are reviewed by the State, not the City. Roof-mounted racking/structural attachment on a RESIDENTIAL structure may separately require the City's own Residential Building Permit; commercial solar structural work falls to the state, since Deer Lodge's Building certification does not extend to commercial.
Verified 2026-07-20 · Source
When you need this permit
- Complete the state's Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25): identify the alternative energy type as Solar and the system type (PV String System, Generator, or Micro Inverter/AC Module System)
- If the system will produce 90 or more volts, the electrical work must be performed by a Montana-licensed electrical contractor unless the homeowner is doing the work on their own private house
- If the project involves a grid-tied alternative energy generator (virtually all net-metered residential/commercial solar), a licensed electrical contractor must obtain an ADDITIONAL permit for the final utility interconnection — stated directly on the state application form
- Apply online at https://aca-prod.accela.com/bcb/ or mail the paper application with payment to: Department of Labor & Industry, Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517
- Because Deer Lodge's own Building certification is residential-only, a separate City Residential Building Permit application may also be required for the roof-mount racking/structural attachment portion of a residential rooftop system; commercial solar structural work is state-administered since Deer Lodge holds no commercial Building certification
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In (Electrical)
Conduit runs, wire sizing, disconnect placement before covering/energizing; must be requested with 48 hours' notice
- 2
Final Interconnection
Per the state application form, a licensed electrical contractor must obtain and complete an additional permit/inspection for the final grid-tied utility connection before Permission to Operate
See the full City of Deer Lodge inspection guide — scheduling & re-inspection fees →
Tips
- Solar PV in Deer Lodge is NOT processed by the City for the electrical portion — the City's own permit portal confirms electrical permits are reviewed by the State, and this extends to the Alternative Energy Permit used for solar/wind/hydro systems.
- A grid-tied system (virtually all residential net-metered solar) requires a licensed electrical contractor to obtain a SEPARATE additional permit for the final utility connection, per the state form's own certification language.
- The residential flat fee of $45 applies under the 'Residential Change of Service' line item on the same Alternative Energy Permit form; commercial projects are billed on the same tiered valuation schedule already documented for other state-issued electrical work in Deer Lodge.
- Because Deer Lodge's Building certification is residential-only, the structural/racking attachment for a residential rooftop system may separately need a City Residential Building Permit; commercial solar structural work is entirely state-administered.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Deer Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of Deer Lodge
Solar PV / Alternative Energy Permit (State-Issued) in other cities
Compare solar pv / alternative energy permit (state-issued) fees across Montana →
Look up this fee in a different city →
Now live
Build your City of Deer Lodge project checklist
Describe your project once and get every permit, document, and fee it triggers in City of Deer Lodge — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →