Solar Photovoltaic (PV) Permit in Choteau, Montana

Solar PV installation in Choteau is split across the same two permitting authorities as any other trade in this Building-only-certified city: a City of Choteau Building/Zoning Permit for racking/structural mounting (fee not published, filled in by city staff on the 'For Office Use' block after review, same as every other Choteau building-permit scope), and a State of Montana DLI Building Codes Bureau Residential Electrical Permit for the interconnection, issued directly by the State since Choteau holds Building certification only. The State's own Application for Residential Electrical Permit form (Rev. 12/22) contains a genuine, distinct 'Alternative Energy Source' line: a flat $65 add-on fee to whatever base electrical-service fee applies, triggered by checking 'Solar' (vs. Wind or Hydro) and then selecting either 'Micro Inverter/AC Module System' or 'PV String System' as the installation type.

Verified 2026-07-20 · Source

When you need this permit

  • City of Choteau combined Zoning/Building Permit Application required for the racking/structural mounting portion, with a Plot Plan showing panel/array location, same as any other structural project
  • Separate State of Montana DLI Building Codes Bureau Application for Residential Electrical Permit required for the grid interconnection, since Choteau is not electrically certified
  • On the state electrical application, check 'Yes' under 'Does this project consist of, or include an Alternative Energy Source?', select 'Solar' as the alternative energy type, and select either 'Micro Inverter/AC Module System' or 'PV String System' as the installation type
  • The $65 Alternative Energy Source fee is added on top of whichever base service-type fee applies from the state's standard table (e.g. Single Family Dwelling up to 200-amp service $200, or a smaller Residential Change of Service fee if no new service is involved)
  • Application must be signed and dated by the licensed electrical contractor's person in charge; incomplete applications are returned unprocessed
  • Call Building Inspector Kyle Harlan at (406) 788-3398 prior to construction and during the project to schedule the City's own structural inspections

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Building/Zoning permit fee (racking/structural)Not published as a fixed table by the City of Choteau, consistent with every other Choteau building-permit entry in this file -- filled in by city staff on the 'For Office Use' block after review. Confirmed via direct review of the City's Zoning/Building Permit Application form on 2026-07-20; no solar-specific city fee line exists.
Not published — contact the department
State Electrical Permit -- Alternative Energy Source (Solar) add-onMontana Building Codes Bureau, Application for Residential Electrical Permit (Rev. 12/22) -- a genuine, distinct statewide fee line: 'If yes, please include an additional $65 fee to the already selected type of work from above table,' with a checkbox for Solar (vs. Wind/Hydro) and a further choice between Micro Inverter/AC Module System and PV String System. Added on top of the applicable base service-type fee (e.g. $200 for Single Family Dwelling up to 200-amp service, or $45 for a Residential Change of Service with only a meter base/disconnect).
$65.00

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Choteau?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • Budget for two separate authorities and TWO fees on a Choteau solar PV install: the City's Building/Zoning permit (structural, fee not published -- call 406-466-2510) and the State DLI's Residential Electrical Permit, which includes a real, distinct $65 'Alternative Energy Source' add-on fee on top of the applicable base service-type fee.
    • On the state electrical application, be sure to check 'Yes' for Alternative Energy Source and select 'Solar,' then choose either Micro Inverter/AC Module System or PV String System -- the $65 fee is easy to miss since it's a separate yellow-highlighted section below the main service-type checkbox table.
    • As with all electrical work in Choteau, mail the state application and payment to PO Box 200517, Helena, MT 59620-0517, or apply online at ebiz.mt.gov -- not to the City of Choteau.

    Frequently asked questions

    Choteau requires a solar photovoltaic (pv) permit for: City of Choteau combined Zoning/Building Permit Application required for the racking/structural mounting portion, with a Plot Plan showing panel/array location, same as any other structural project; Separate State of Montana DLI Building Codes Bureau Application for Residential Electrical Permit required for the grid interconnection, since Choteau is not electrically certified; On the state electrical application, check 'Yes' under 'Does this project consist of, or include an Alternative Energy Source?', select 'Solar' as the alternative energy type, and select either 'Micro Inverter/AC Module System' or 'PV String System' as the installation type; The $65 Alternative Energy Source fee is added on top of whichever base service-type fee applies from the state's standard table (e.g. Single Family Dwelling up to 200-amp service $200, or a smaller Residential Change of Service fee if no new service is involved); Application must be signed and dated by the licensed electrical contractor's person in charge; incomplete applications are returned unprocessed; Call Building Inspector Kyle Harlan at (406) 788-3398 prior to construction and during the project to schedule the City's own structural inspections. If your project isn't listed, confirm with City of Choteau — Building Official Kyle Harlan (contracted); city-certified for Building (B) permits only. Zoning permits are administered directly by the City Office; Electrical, Plumbing, and Mechanical permits within Choteau city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 466-2510 before starting work.

    Choteau does not publish a plan-review timeline for this permit. Contact City of Choteau — Building Official Kyle Harlan (contracted); city-certified for Building (B) permits only. Zoning permits are administered directly by the City Office; Electrical, Plumbing, and Mechanical permits within Choteau city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 466-2510 for current turnaround.

    You'll need: Zoning/Building Permit Application (racking/structural); Plot Plan; Application for Residential Electrical Permit (State DLI, Alternative Energy Source section completed). See the required-documents checklist on this page for details on each.

    Apply through City of Choteau — Building Official Kyle Harlan (contracted); city-certified for Building (B) permits only. Zoning permits are administered directly by the City Office; Electrical, Plumbing, and Mechanical permits within Choteau city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at 38 First Avenue N.W., PO Box 619, Choteau, MT 59422-0619. Phone: (406) 466-2510. Office hours: City Office: Mon-Fri 8:00 AM - 5:00 PM. Building Inspector Kyle Harlan (contracted, also serves Toole County and Pondera County as certified building official) should be called directly at (406) 788-3398 prior to construction and during the project to schedule required inspections, per the City's Zoning/Building Permit Acknowledgement Form.. Official information: https://www.choteaumt.org/services.

    Choteau, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; non-certified trades in a partially-certified jurisdiction fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list (bsd.dli.mt.gov/building-codes-permits).; Choteau is a Montana DLI-certified jurisdiction for Building (B) ONLY within city limits; certified building official on file with DLI: Kyle Harlan, (406) 466-2510 (city office) / (406) 788-3398 (direct, per City's own permit packet). Source: Montana DLI Building Codes Bureau, 'Montana Certified Local Government Program' roster, updated 04/22/2026, https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf; Per Choteau Acantha reporting (April 2012 City Council coverage), the City of Choteau adopted the State Building Code as its own by ordinance (effective May 17, 2012) and contracted with Kyle Harlan of Cascade, MT as the city's certified building code inspector, so that building permit fees collected stay with the city rather than the state, and so contractors have a local point of contact. Source: choteauacantha.com, 'City adopts revised zoning codes'; The City of Choteau's own Zoning/Building Permit Acknowledgement Form lists the codes applicable to construction in the city as: the International Building Code, Energy Conservation Code (IECC), International Mechanical Code (IMC), International Fuel Gas Piping Code (IFGC), ICC A117.1 Accessibility Standards, the Uniform Plumbing Code (UPC), the National Electrical Code (NEC), the City of Choteau Zoning Code, and other Choteau Municipal Codes. Source: City of Choteau, Choteau-Zoning-and-Building-Permit-packet.pdf (choteaumt.org/s/Choteau-Zoning-and-Building-Permit-packet.pdf); Per the Montana DLI Building Codes Bureau's Current Codes page (statewide effective date June 11, 2022, applicable to all certified and state-enforced jurisdictions alike): 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 ISPSC, 2021 UPC, 2020 NEC, 2017 ICC A117.1 Accessibility. Choteau's own permit packet references these same code families (IBC, IECC, IMC, IFGC, ICC A117.1, UPC, NEC) without naming a locally-amended edition, consistent with a small B-only-certified jurisdiction enforcing the state-adopted editions rather than authoring independent code text. Source: bsd.dli.mt.gov/building-codes-permits/current-codes. Local amendments apply — see the Choteau overview page for the full list.

    The City itself has no solar-specific building/zoning fee (its general 'For Office Use' fee block applies, filled in by city staff). The State of Montana DLI Building Codes Bureau, which issues Choteau's electrical permits, does have a genuine distinct fee: a flat $65 'Alternative Energy Source' add-on on top of the applicable base electrical service fee, triggered by checking 'Solar' on the state's Application for Residential Electrical Permit.