Hamilton building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Hamilton, Montana.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 920 New York Ave, Hamilton, MT 59840
- Phone
- (406) 363-3316
- Office hours
- City Hall: 223 S. 2nd Street, Hamilton, MT 59840, main line (406) 363-2101. Building Department / Public Works office: 920 New York Ave, (406) 363-3316 or (406) 363-6717. Building Inspector Tim Netzley: (406) 880-5832, inspector@constructmt.com. Inspection scheduling line: (406) 552-3238. Inspections scheduled Monday & Wednesday 1pm-4pm and Fridays 8am-12pm per the Roof Permit Application; 24 hours' notice required for plumbing inspections per the Plumbing Permit Application.
- Website
- Official site
Published scheduling rules
- Call the Building Inspection line, (406) 880-5832 (also listed as 406-552-3238 for scheduling), to schedule required inspections. (Residential Building Permit (New Construction / Addition / Remodel))
- 24 hours' notice required to schedule all plumbing inspections, at (406) 363-3316 (Plumbing Permit)
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU) / Detached Accessory Structure Permit
- 1
Foundation/Footing
Before concrete pour for detached ADU foundations
- 2
Framing
Structural framing per approved plans
- 3
Final
Completed ADU verified against approved plans and zoning setback compliance
Applies to: Residential Building Permit (New Construction / Addition / Remodel)
- 1
Foundation/Footing
Before concrete pour — foundation plan, footing details, depth, embedded hardware and reinforcing steel per submitted plans
- 2
Framing
Structural framing per approved plans before walls are closed
- 3
Final
Completed work verified against approved plans; Building Official sign-off required before occupancy
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and service connections before walls are closed
- 2
Final
Devices installed, panel labeled, protections verified per 2020 NEC
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
Wiring and box placement before walls are closed, where applicable
- 2
Final
Charger circuit, disconnect, and breaker protections verified per 2020 NEC before energizing
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork, gas piping, and mechanical equipment rough-in before walls closed
- 2
Final
Equipment operational, clearances and venting verified
Applies to: Plumbing Permit
- 1
Rough-In
After pipes installed, before walls closed; requires 24 hours' notice to schedule
- 2
Final
All fixtures connected, water heater and venting verified, no leaks
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement verified before energizing
- 2
Final Inspection
Racking/roof-penetration attachment, electrical connections, and interconnection point verified
Applies to: Swimming Pool / Spa Permit
- 1
Pre-Gunite/Pre-Backfill
Before pool shell concrete pour or backfill, per adopted ISPSC structural and barrier requirements
- 2
Final
Pool barrier/fencing, equipment bonding, and electrical safety verified per adopted ISPSC and NEC before use
Final inspection only: Roof Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hamilton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Hamilton building permits
Get alerts for Hamilton
We'll email you when Hamilton's fees, documents, or codes change — not often.