Inspection sequence, scheduling, and re-inspection fees for building permits in Carlin, Nevada.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
820 Oak Street, PO Box 340, Carlin, NV 89822
Phone
(775) 754-6515
Office hours
Not published on the City of Carlin website; the Building Department's Permit Application Procedures document states that all inspections are performed Tuesday through Thursday, and that inspection arrangements must be made at least 24 hours in advance by calling (775) 754-6515. The Building Official is Anna Penola. The department is part of the City's Public Works Department; permit applications are submitted online via the GovWell portal (app.govwell.com/carlin-nv), accompanied by two complete sets of 11x17 wet-stamped plans plus one set through GovWell.

Published scheduling rules

  • Inspections are performed Tuesday through Thursday only; arrangements must be made at least 24 hours in advance by calling (775) 754-6515. (Residential Building Permit (New Construction / Addition / Remodel))

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footings

    Verify reinforcing steel location and footing size before concrete pour

  2. 2

    Foundation

    Verify reinforcing steel location and footing size for the foundation

  3. 3

    4-Way

    Verify framing, nailing, rough electrical, rough plumbing, and rough mechanical

  4. 4

    Insulation

    Verify installation of all insulation

  5. 5

    Sheet Rock

    Verify all sheet rock nailing

  6. 6

    Final

    Verify all finishes, final electrical, final plumbing, final mechanical, and completion of the building

Applies to: Residential Building Permit (New Construction / Addition / Remodel)

  1. 1

    Footings

    One inspection to verify location of reinforcing steel (horizontal and vertical) and size of footings; all reinforcing steel must be in place at time of inspection

  2. 2

    Foundation

    One inspection to verify location of reinforcing steel (horizontal and vertical) and size of footings for the foundation

  3. 3

    4-Way

    One inspection to verify all framing, nailing, rough electrical, rough plumbing, and rough mechanical

  4. 4

    Insulation

    One inspection to verify installation of all insulation

  5. 5

    Sheet Rock

    One inspection to verify all sheet rock nailing

  6. 6

    Final

    One inspection to verify all finishes, final electrical, final plumbing, final mechanical, and completion of the building; posting the building address is required prior to the final inspection

Applies to: Detached Garage / Storage Building Permit

  1. 1

    Footings

    Verify footing size/Detail A or B selection, reinforcing steel placement, and frost-protection compliance (or 600/400 sq ft exemption) before concrete pour

  2. 2

    Framing

    Verify wall studs, headers, bracing, roof framing/trusses, and anchor bolt placement per the City's header schedule and rafter span tables

  3. 3

    Final

    Verify completed structure, electrical, plumbing, and mechanical installations against approved plans

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Structural/Racking

    Roof penetrations and mounting-system attachment verified, consistent with the general framing-inspection step for a residential building permit

  2. 2

    Final Electrical

    Grid interconnection, grounding, and disconnects verified per the 2017 National Electrical Code before the system is energized

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Carlin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Carlin building permits

Get alerts for Carlin

We'll email you when Carlin's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.