Carlin building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Carlin, Nevada.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 820 Oak Street, PO Box 340, Carlin, NV 89822
- Phone
- (775) 754-6515
- permits@carlinnv.gov
- Office hours
- Not published on the City of Carlin website; the Building Department's Permit Application Procedures document states that all inspections are performed Tuesday through Thursday, and that inspection arrangements must be made at least 24 hours in advance by calling (775) 754-6515. The Building Official is Anna Penola. The department is part of the City's Public Works Department; permit applications are submitted online via the GovWell portal (app.govwell.com/carlin-nv), accompanied by two complete sets of 11x17 wet-stamped plans plus one set through GovWell.
- Website
- Official site
Published scheduling rules
- Inspections are performed Tuesday through Thursday only; arrangements must be made at least 24 hours in advance by calling (775) 754-6515. (Residential Building Permit (New Construction / Addition / Remodel))
Inspection sequence
Applies to: Commercial Building Permit
- 1
Footings
Verify reinforcing steel location and footing size before concrete pour
- 2
Foundation
Verify reinforcing steel location and footing size for the foundation
- 3
4-Way
Verify framing, nailing, rough electrical, rough plumbing, and rough mechanical
- 4
Insulation
Verify installation of all insulation
- 5
Sheet Rock
Verify all sheet rock nailing
- 6
Final
Verify all finishes, final electrical, final plumbing, final mechanical, and completion of the building
Applies to: Residential Building Permit (New Construction / Addition / Remodel)
- 1
Footings
One inspection to verify location of reinforcing steel (horizontal and vertical) and size of footings; all reinforcing steel must be in place at time of inspection
- 2
Foundation
One inspection to verify location of reinforcing steel (horizontal and vertical) and size of footings for the foundation
- 3
4-Way
One inspection to verify all framing, nailing, rough electrical, rough plumbing, and rough mechanical
- 4
Insulation
One inspection to verify installation of all insulation
- 5
Sheet Rock
One inspection to verify all sheet rock nailing
- 6
Final
One inspection to verify all finishes, final electrical, final plumbing, final mechanical, and completion of the building; posting the building address is required prior to the final inspection
Applies to: Detached Garage / Storage Building Permit
- 1
Footings
Verify footing size/Detail A or B selection, reinforcing steel placement, and frost-protection compliance (or 600/400 sq ft exemption) before concrete pour
- 2
Framing
Verify wall studs, headers, bracing, roof framing/trusses, and anchor bolt placement per the City's header schedule and rafter span tables
- 3
Final
Verify completed structure, electrical, plumbing, and mechanical installations against approved plans
Applies to: Solar Photovoltaic (PV) Permit
- 1
Structural/Racking
Roof penetrations and mounting-system attachment verified, consistent with the general framing-inspection step for a residential building permit
- 2
Final Electrical
Grid interconnection, grounding, and disconnects verified per the 2017 National Electrical Code before the system is energized
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Carlin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Carlin building permits
Get alerts for Carlin
We'll email you when Carlin's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.