Required for commercial construction, additions, and alterations within Carlin city limits. Plans must be designed by a Nevada State Registered Architect, Registered Engineer, or Licensed Contractor per Nevada State Law, and reviewed against the 2018 IBC (with Appendices C, E, I, J and amendments) plus routing to the Nevada State Fire Marshal and, for certain use types, the Nevada State Division of Health.

Verified 2026-07-03 · Source

When you need this permit

  • Nevada State Law requires all commercial-use plans to be designed by a Nevada State Registered Architect, Registered Engineer, or Licensed Contractor Contractor
  • All commercial occupancies (and all residential occupancies greater than a duplex) must have plans submitted to and approved by the Nevada State Fire Marshal, with a copy of the approval provided to the City of Carlin at time of application
  • Certain use types (food establishments, subdivisions, commercial/private septic systems, public pools/spas, public water systems, dairies/milk plants, drug/cosmetic plants, bottled water plants, hotels/motels, RV parks, cemeteries/mausoleums, meat/fish/poultry processors, labor/man camps) require Nevada State Division of Health plan approval submitted to the City at application
  • Landscape plans are required for all Commercial/Industrial projects (not required for residential) as part of the grading plan submittal
  • Two (2) complete sets of 11x17 wet-stamped plans plus one set via GovWell are required
  • Applicants should allow 21 days for review of commercial permits

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan reviewCarlin’s published plan-review target
21–21 business days

How long did your Commercial Building Permit permit actually take in Carlin?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings

    Verify reinforcing steel location and footing size before concrete pour

  2. 2

    Foundation

    Verify reinforcing steel location and footing size for the foundation

  3. 3

    4-Way

    Verify framing, nailing, rough electrical, rough plumbing, and rough mechanical

  4. 4

    Insulation

    Verify installation of all insulation

  5. 5

    Sheet Rock

    Verify all sheet rock nailing

  6. 6

    Final

    Verify all finishes, final electrical, final plumbing, final mechanical, and completion of the building

See the full Carlin inspection guide — scheduling & re-inspection fees →

Tips

  • No fee schedule for commercial building permits is published anywhere on the City of Carlin website or in its downloadable PDFs. Contact the Building Department directly at (775) 754-6515 or permits@carlinnv.gov for current fee information.
  • Plans approved for construction shall be marked 'APPROVED' and shall not be changed, modified, or altered without authorization from the building official.
  • Every permit expires 180 days from issuance if work is not completed; one written extension may be granted for just cause.

Frequently asked questions

Carlin requires a commercial building permit for: Nevada State Law requires all commercial-use plans to be designed by a Nevada State Registered Architect, Registered Engineer, or Licensed Contractor; All commercial occupancies (and all residential occupancies greater than a duplex) must have plans submitted to and approved by the Nevada State Fire Marshal, with a copy of the approval provided to the City of Carlin at time of application; Certain use types (food establishments, subdivisions, commercial/private septic systems, public pools/spas, public water systems, dairies/milk plants, drug/cosmetic plants, bottled water plants, hotels/motels, RV parks, cemeteries/mausoleums, meat/fish/poultry processors, labor/man camps) require Nevada State Division of Health plan approval submitted to the City at application; Landscape plans are required for all Commercial/Industrial projects (not required for residential) as part of the grading plan submittal; Two (2) complete sets of 11x17 wet-stamped plans plus one set via GovWell are required; Applicants should allow 21 days for review of commercial permits. If your project isn't listed, confirm with City of Carlin Building Department at (775) 754-6515 before starting work.

Carlin's published plan-review target for a commercial building permit is 21–21 business days.

You'll need: Building Permit Application; Nevada State Fire Marshal Approval; Construction Drawings (Architect/Engineer/Contractor stamped). Depending on your project, Carlin may also ask for: Nevada State Division of Health Approval. See the required-documents checklist on this page for details on each.

Carlin requires 6 inspection(s) for a commercial building permit, in order: Footings, Foundation, 4-Way, Insulation, Sheet Rock, Final. Schedule each through City of Carlin Building Department ((775) 754-6515).

Apply through City of Carlin Building Department at 820 Oak Street, PO Box 340, Carlin, NV 89822. Phone: (775) 754-6515, email: permits@carlinnv.gov. Office hours: Not published on the City of Carlin website; the Building Department's Permit Application Procedures document states that all inspections are performed Tuesday through Thursday, and that inspection arrangements must be made at least 24 hours in advance by calling (775) 754-6515. The Building Official is Anna Penola. The department is part of the City's Public Works Department; permit applications are submitted online via the GovWell portal (app.govwell.com/carlin-nv), accompanied by two complete sets of 11x17 wet-stamped plans plus one set through GovWell.. Official information: https://explorecarlinnv.com/departments/public_works/building_department.php.

Carlin, Nevada has adopted: Nevada is a home-rule state for building codes: there is no single mandatory statewide building-code edition — each city and county adopts and amends its own code. Always confirm the specific adopted edition for the city or county in question rather than assuming a uniform statewide building code or that a neighboring city's (e.g., Elko's) adopted editions apply. Source: City of Carlin Permit Application Procedures (Revised 5-19-2026).; 2018 International Building Code (IBC), with Appendices C, E, I and J, with amendments, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Residential Code (IRC), Chapters 1-44 and Appendices A, B, C, H, J and K, with amendments, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 Uniform Mechanical Code (UMC), Chapters 1-17, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 Uniform Plumbing Code (UPC), Chapters 1-17 and Appendices A, B, D, E, I and L, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Fire Code (IFC), with all additions/deletions as adopted by the Nevada State Fire Marshal per NRS/NAC 477, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Energy Conservation Code (IECC), with amendments, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Fuel Gas Code, Chapters 1-8 and Appendix A, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; International Wildland-Urban Interface Code, Chapter 5, adopted by the City of Carlin (edition year not specified in the source document). Source: City of Carlin Permit Application Procedures.; 2018 International Swimming Pool and Spa Code, Chapters 1-11, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 National Fire Protection Association (NFPA) 54 and 2017 NFPA 58, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2017 National Electrical Code (NEC) — referred to in the Permit Application Procedures as the '2017 International Electric Code,' which is a City-document naming artifact; the NEC is published by the NFPA, not ICC. The City's own Detached Garage/Storage Building handout separately confirms alignment with the '2017 National Electric Code.' Source: City of Carlin Permit Application Procedures; City of Carlin Single Family Residential Detached Garage and Storage Buildings handout.; 2017 ICC A117.1-2017, Standard for Accessible and Usable Buildings and Facilities, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; Necessary Administrative Procedures as outlined in the Carlin City Code, per the City of Carlin Permit Application Procedures.. Local amendments apply — see the Carlin overview page for the full list.

Nevada State Law requires all commercial-use plans to be designed by a Nevada State Registered Architect, Registered Engineer, or Licensed Contractor. Source: City of Carlin Permit Application Procedures.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Carlin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Carlin.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.