Skip to main content
PermitBase

Commercial Building Permit (No Dedicated Commercial Track — Universal Joint Application) in Ely, Nevada

The City of Ely has no separately named commercial building permit process: commercial construction is processed on the same joint City of Ely/White Pine County Building Permit Application used for all construction, with 'Commercial' checked as the Proposed Use (the form's options are Residential, Commercial, Industrial, Mining, Other). Reviewed against the 2018 International Building Code as adopted by Ely Municipal Code 9-1-1 (Ord. 746, 8-18-2022), applying the City's published design criteria (frost depth 36 inches, seismic zone D or C, 115 mph three-second gust wind speed; snow load determined case-by-case after application submission). The Building Official completes the form's back-page administrative block — Size of Bldg. Sq. Ft., Total Valuation of Work, Type of Construction, Occupancy Group, Maximum Occupancy, Land Use Zone — and routes Special Approvals to the Regional Planning Commission (RPC), Fire, Health, and Will Serve review lines as applicable. Fees are valuation-based per Ely Municipal Code 9-1-5 (conforming to the 1997 Uniform Administrative Code fee table) and the county's public statement that 'the cost of permits is based on the valuation of construction'; no dollar-figure fee table is published by either the City or the County.

Reviewed 2026-08-01 · Source

When you need this permit

  • Building permit required when any owner or authorized agent intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, per the City of Ely How Do I/FAQ page
  • Application submitted on the joint City of Ely/White Pine County Building Permit Application with 'Commercial' checked as Proposed Use and the applicable Class of Work (New Building, Addition, Relocate/Move, Repair, Alteration, Demolition, Mobile Home, Other)
  • Reviewed against the 2018 International Building Code (IBC) as adopted by Ely Municipal Code 9-1-1, plus the 2018 UMC/UPC/IFC/IECC and 2011 NEC editions identified on the City's Building Department and Building Codes webpage
  • Plans must address the City's published design criteria: frost depth 36 inches, seismic zone D or C, 115 mph three-second gust wind speed, 1,500 lb. soil bearing capacity; snow load is determined case-by-case after application submission per the City's Building Department webpage
  • Two complete sets of building plans required, showing floor plans, elevations, wall and roof construction, dimensions, window sizes, doors, heating, plumbing, and electrical, in sufficient detail for a proper plan check, per the White Pine County Building Permit Procedures document (jointly administered department)
  • Plans may be required to be drawn by licensed/qualified people under NRS Chapters 623 and 625 (Nevada architect/engineer licensing statutes), per the White Pine County Building Permit Procedures document; 'book-bought' plans are not accepted
  • Plot plan required showing plot dimensions, building sizes and locations, distances from roads, ditches and canals, distances between structures, easements, and utility poles, per the White Pine County Building Permit Procedures document
  • All contractor names with both State License Number and City License Number for Building, Plumbing, Electrical, and Mechanical contractors must be listed on the application
  • Elevation certificate may be required if the building site is in a flood zone other than Zone X; the application form itself asks 'Is this property in a flood zone?'
  • Special Approvals routed on the application's back page as applicable: Regional Planning Commission (RPC), Fire, Health, and Will Serve — each marked Approved, Denied, or Not Required by the department
  • Application conformance to all applicable zoning-title regulations required; any permit issued in conflict with zoning is null and void, per Ely Municipal Code 12-16-2(D)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeEly Municipal Code 9-1-5 (Ord. 746, 8-18-2022) requires all permit fees to conform to the 1997 Uniform Administrative Code fee table, which is not published online by the City or County; the County's only public statement is 'the cost of permits is based on the valuation of construction.' The application records Total Valuation of Work and a Building Permit $ line.
Not published — valuation-based
Plan Check FeeCharged on all permits requiring plan review per the City's Building Permit Package; Ely Municipal Code 9-1-5(C) requires plan review fees to be paid to each entity performing plan review. Itemized as a separate 'Plan Check' line on the application's fee block.
Not published
Fuel SurchargeItemized line on the application's fee block; amount not published.
Not published
RPC / Fire / Health / Will Serve review feesSeparate Special Approvals review lines on the application; charged where the respective review applies. Dollar amounts not published.
Not published
Penalty (work started before permit)Any work done prior to issuance of permit is subject to double permit fees, per the City of Ely Building Permit Package; the application fee block carries a dedicated 'Penalty' line.
Double permit fees

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit (No Dedicated Commercial Track — Universal Joint Application) permit actually take in Ely?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing & Foundation

    Footings and foundation verified before concrete pour/backfill; first item on the application's printed 'Required Inspections' list

  2. 2

    Under-floor Utilities

    Under-floor/under-slab plumbing and utility rough-in verified before concealment

  3. 3

    Framing, Rough Plumbing, Rough Electrical & Rough Mechanical

    The application's printed inspection list states these four can be scheduled together, before walls are closed

  4. 4

    Stucco - Wire Stapling

    Stucco wire/lath fastening verified before applying finish coats, where applicable

  5. 5

    Insulation

    Insulation verified before drywall installation

  6. 6

    Dry Wall

    Drywall fastening verified before finishing

  7. 7

    Final

    All work complete and verified per approved plans and adopted codes before occupancy; Occupancy Group and Maximum Occupancy are recorded on the permit itself

See the full Ely inspection guide — scheduling & re-inspection fees →

Tips

  • Ely has no dedicated commercial permitting track: 'Commercial' is simply one of five Proposed Use checkboxes (Residential, Commercial, Industrial, Mining, Other) on the universal joint City of Ely/White Pine County Building Permit Application — the same form, checklist, and fee block used for residential work.
  • Tenant improvement is NOT a distinct permit type in Ely. No TI application, TI checklist, TI fee line, or TI timeline is published by the City or County anywhere; a commercial tenant improvement is processed as this general building permit with 'Commercial' as Proposed Use and 'Alteration' (or 'Repair') as Class of Work. If the tenancy's use or occupancy classification changes, the FAQ trigger language ('change the occupancy of a building or structure') applies and the new Occupancy Group is recorded on the permit.
  • No dollar-figure fee schedule exists publicly for commercial work (or any permit type): Ely Municipal Code 9-1-5 pegs fees to the unpublished 1997 Uniform Administrative Code table, and White Pine County (joint department) states only that cost is based on construction valuation. Budget for building permit + plan check + fuel surcharge + any RPC/Fire/Health/Will Serve review fees, and get a quote from the Building Department at (775) 289-6500 before committing.
  • Plan review fees must be paid to each entity performing plan review (Ely Municipal Code 9-1-5(C)) — on a commercial job with RPC, Fire, and Health reviews, expect multiple review fees, not one.
  • Commercial plans face the NRS 623/625 screen: the joint department's procedures document states plans can be required to be drawn by licensed/qualified people and that 'book-bought' plans are not accepted — for commercial occupancies, plan preparation by a Nevada-licensed architect or engineer is the safe assumption; confirm with the Building Official.
  • The permit becomes null and void if work is not commenced within 180 days, or if work is suspended or abandoned for 180 days after commencement; all inspections must be scheduled 48 hours in advance per the application (the older Building Permit Package states 24 hours — confirm current lead time).
  • Snow load is not a fixed published value — the City's Building Department webpage states it is determined case-by-case after the application is submitted.
  • White Pine County (the county side of this joint department) has enacted a Temporary Moratorium on the Acceptance, Processing, and Approval of Land Use Applications for Data Center Development (Resolution 2026-18), per the County's Building page as of 2026-08-01 — data-center or large-load commercial projects should confirm with the department whether it affects their site, including within Ely city limits.

Frequently asked questions

Ely requires a commercial building permit (no dedicated commercial track — universal joint application) for: Building permit required when any owner or authorized agent intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, per the City of Ely How Do I/FAQ page; Application submitted on the joint City of Ely/White Pine County Building Permit Application with 'Commercial' checked as Proposed Use and the applicable Class of Work (New Building, Addition, Relocate/Move, Repair, Alteration, Demolition, Mobile Home, Other); Reviewed against the 2018 International Building Code (IBC) as adopted by Ely Municipal Code 9-1-1, plus the 2018 UMC/UPC/IFC/IECC and 2011 NEC editions identified on the City's Building Department and Building Codes webpage; Plans must address the City's published design criteria: frost depth 36 inches, seismic zone D or C, 115 mph three-second gust wind speed, 1,500 lb. soil bearing capacity; snow load is determined case-by-case after application submission per the City's Building Department webpage; Two complete sets of building plans required, showing floor plans, elevations, wall and roof construction, dimensions, window sizes, doors, heating, plumbing, and electrical, in sufficient detail for a proper plan check, per the White Pine County Building Permit Procedures document (jointly administered department); Plans may be required to be drawn by licensed/qualified people under NRS Chapters 623 and 625 (Nevada architect/engineer licensing statutes), per the White Pine County Building Permit Procedures document; 'book-bought' plans are not accepted; Plot plan required showing plot dimensions, building sizes and locations, distances from roads, ditches and canals, distances between structures, easements, and utility poles, per the White Pine County Building Permit Procedures document; All contractor names with both State License Number and City License Number for Building, Plumbing, Electrical, and Mechanical contractors must be listed on the application; Elevation certificate may be required if the building site is in a flood zone other than Zone X; the application form itself asks 'Is this property in a flood zone?'; Special Approvals routed on the application's back page as applicable: Regional Planning Commission (RPC), Fire, Health, and Will Serve — each marked Approved, Denied, or Not Required by the department; Application conformance to all applicable zoning-title regulations required; any permit issued in conflict with zoning is null and void, per Ely Municipal Code 12-16-2(D). If your project isn't listed, confirm with City of Ely Building Department at (775) 289-6500 / (775) 289-2430 before starting work.

No dollar amounts are published. Ely Municipal Code 9-1-5 requires fees to conform to the 1997 Uniform Administrative Code fee table (not published online), and White Pine County states only that permit cost is based on the valuation of construction. Plan review fees are additional and payable to each reviewing entity. Contact the Building Department at (775) 289-6500 or (775) 289-2430 for a quote. Source: Ely Municipal Code 9-1-5; White Pine County Building page.

Ely does not publish a plan-review timeline for this permit. Contact City of Ely Building Department at (775) 289-6500 / (775) 289-2430 for current turnaround.

You'll need: Building Permit Application (City of Ely/White Pine County joint form); Building Plans (2 complete sets); Plot Plan; Utility Letters of Intent to Serve and Clearance; All-Weather Road / Emergency Access Approval Letter. Depending on your project, Ely may also ask for: White Pine Regional Planning Commission Approvals; Elevation Certificate. See the required-documents checklist on this page for details on each.

Ely requires 7 inspection(s) for a commercial building permit (no dedicated commercial track — universal joint application), in order: Footing & Foundation, Under-floor Utilities, Framing, Rough Plumbing, Rough Electrical & Rough Mechanical, Stucco - Wire Stapling, Insulation, Dry Wall, Final. Schedule each through City of Ely Building Department ((775) 289-6500 / (775) 289-2430).

Apply through City of Ely Building Department at 501 Mill Street, P.O. Box 299, Ely, NV 89301. Phone: (775) 289-6500 / (775) 289-2430, email: buildingofficial@cityofelynv.gov. Office hours: Monday-Friday 8:00 AM-5:00 PM. City of Ely Building Department, 501 Mill Street, Ely, NV 89301 (mailing: P.O. Box 299, Ely, NV 89301). Fax (775) 289-1463. Building Official: Christopher Flannery (buildingofficial@cityofelynv.gov). The Building and Planning Department is jointly operated with White Pine County (Building & Planning Dept. Manager Jennifer Drew-Lesher, jdrew@whitepinecountynv.gov) and uses a shared City of Ely/White Pine County Building Permit Application form. Source: City of Ely Building Department & Building Codes page; Building Permit Application (joint form).. Official information: https://www.cityofelynv.gov/building-department-and-building-codes-city-of-ely/.

No. Commercial construction uses the same joint City of Ely/White Pine County Building Permit Application as residential work, with 'Commercial' checked under Proposed Use. The Building Department records Occupancy Group, Maximum Occupancy, Type of Construction, and Total Valuation of Work on the form's administrative page, and routes RPC, Fire, Health, and Will Serve reviews as applicable. Source: joint Building Permit Application; City of Ely How Do I/FAQ page.

No. Neither the City of Ely nor White Pine County publishes any tenant-improvement-specific application, fee, or process. A TI is processed as a standard building permit with 'Commercial' as Proposed Use and 'Alteration' as Class of Work; a change in the space's occupancy classification also triggers the permit requirement under the City's FAQ language. Source: joint Building Permit Application; City of Ely How Do I/FAQ page.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Ely.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.