EV Charger / EVSE Permit (No Dedicated Type — Fee Schedule Unpublished) — Ely, Nevada · Requirements sheet
Reviewed 2026-07-20 · Source: https://www.cityofelynv.gov/building-department-and-building-codes-city-of-ely/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (No Dedicated Type — Fee Schedule Unpublished) in Ely, Nevada
Installation of a Level 2 (or higher) electric vehicle charger/EVSE within Ely city limits is not a separately named permit type — like solar PV, it is covered by the City's general building-permit trigger language ('to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system'), per the City's own How Do I/FAQ page, and is reviewed under the 2011 NEC (Article 625, Electric Vehicle Power Transfer System) as identified on the City's Building Department & Building Codes webpage. No EV-charger-specific application, checklist, or fee line is published by the City of Ely; no dollar-amount fee schedule is published for any permit type at all — Ely Municipal Code 9-1-5 ties fees to the 1997 Uniform Administrative Code fee table, which is not published online. Because Ely's building permits are jointly administered with White Pine County, the County side shows the same gap: the County's own Building page, Building Permit Procedures & Applications page, Building Code Design Criteria Information page, downloadable 'Customer Building Permit Procedures' PDF, and Building FAQ publish no dollar-figure fee schedule or numeric review timeline; the County's only public statement is 'The cost of permits is based on the valuation of construction' with a phone number to call. The gap is thus confirmed independently on both the City and County sides of the joint department.
Reviewed 2026-07-20 · Source
When you need this permit
- Electrical permit required for installation of an EV charger circuit, per the City's How Do I/FAQ page language ('to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system')
- Governed by the 2011 NEC as identified on the City's Building Department and Building Codes webpage, including Article 625
- Application submitted on the joint City of Ely/White Pine County Building Permit Application, listing the Electrical Contractor's name/address and both State License Number and City License Number
- All inspections must be scheduled 48 hours in advance per the joint Building Permit Application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Charger circuit wiring and breaker sizing verified before concealment, if applicable
- 2
Final
EVSE installed, GFCI/disconnect and connections verified against the 2011 NEC
See the full Ely inspection guide — scheduling & re-inspection fees →
Tips
- The City of Ely has no dedicated EV-charger permit, checklist, or fee schedule — a charger circuit is processed as a standard electrical permit under the general trigger language covering installation of 'any electrical... system,' the same mechanism used for solar PV in this jurisdiction.
- No dollar-amount fee schedule for any permit type (including electrical) is published by the City. Ely Municipal Code 9-1-5 ties fees to the unpublished 1997 Uniform Administrative Code fee table; confirm current fee amounts directly with the Building Department at (775) 289-6500 or (775) 289-2430.
- Any work performed prior to permit issuance is subject to double permit fees, per the City of Ely Building Permit Package.
- Ely's electrical code edition (2011 NEC) predates NEC 625's more recent bidirectional and load-management provisions introduced in later cycles, so equipment and design assumptions based on a current NEC may not match what is enforced here. Confirm with the Building Department which specific EVSE requirements apply.
- 'cost is based on valuation of construction' is the only public statement from either side.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ely building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Ely's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Ely yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Ely lands. Privacy.
Other permits in Ely
EV Charger / EVSE Permit (No Dedicated Type — Fee Schedule Unpublished) in other cities
Compare ev charger / evse permit (no dedicated type — fee schedule unpublished) fees across Nevada →
Look up this fee in a different city →
Related guides
Now live
Build your Ely project checklist
Describe your project once and get every permit, document, and fee it triggers in Ely — in one checklist. Free, for any city and any number of projects.
Get started →