EV Charger / EVSE Permit in Henderson, Nevada

Henderson has a dedicated, itemized 'EV receptacle' fee on its Development Services Center (DSC) Fee Schedule -- a standalone flat fee separate from the general electrical permit line items, distinct from (and lower than) a full solar PV permit. This entry covers a standalone EV charger/receptacle installation that is NOT part of a PV (solar) system; when an EV charger is installed together with rooftop solar, it is typically bundled into the solar-pv-permit instead (see the sibling solar-pv-permit entry in this dataset, which lists the same $223 EV receptacle line item for that combined scenario).

Verified 2026-07-20 · Source

When you need this permit

  • Standalone electrical permit application via Henderson's DSC Online portal for EV charger/receptacle installation not combined with a PV system
  • Nevada State Contractor's license required for the installing electrician/contractor Contractor
  • Systems must comply with the 2023 NEC with Southern Nevada Building Officials (SNBO) amendments (effective January 2, 2026)
  • If the EV charger is installed as part of a new or expanded solar PV system, it is billed under the solar-pv-permit's electrical scope instead of as a standalone EV receptacle

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

EV receptacle (not part of a PV system) -- eachHenderson DSC Fee Schedule Table B -- Miscellaneous Building Items, effective 10/01/2025; also cross-listed on Table C -- Building MPE Items in the sibling electrical-permit entry of this dataset -- corroborated by an independent secondary source referencing the same $223 Henderson EV charger permit fee
$223

Review timeline

Plan reviewTypical estimate — confirm current times with the Henderson building department
~1–10 business days

How long did your EV Charger / EVSE Permit permit actually take in Henderson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Circuit, conduit, and disconnect placement verified before energizing

  2. 2

    Final Electrical

    EV receptacle/charger installation, GFCI/load management, and labeling verified

See the full Henderson inspection guide — scheduling & re-inspection fees →

Tips

  • Henderson's EV receptacle fee is a flat $223 per receptacle -- one of the few jurisdictions in this dataset with a truly dedicated, line-itemized EV charger permit fee rather than a general electrical catch-all.
  • If your EV charger is being installed alongside new or expanded rooftop solar, it will likely be bundled into the solar-pv-permit rather than billed as a separate standalone EV receptacle -- check with DSC Online to confirm which permit type applies to your project.
  • The Henderson DSC Fee Schedule (effective 10/01/2025) lists this fee on Table B (Miscellaneous Building Items) though it is also referenced from Table C (Building MPE Items) in the general electrical permit documentation -- the $223 figure is consistent across both citations.

Frequently asked questions

Henderson requires an ev charger / evse permit for: Standalone electrical permit application via Henderson's DSC Online portal for EV charger/receptacle installation not combined with a PV system; Nevada State Contractor's license required for the installing electrician/contractor; Systems must comply with the 2023 NEC with Southern Nevada Building Officials (SNBO) amendments (effective January 2, 2026); If the EV charger is installed as part of a new or expanded solar PV system, it is billed under the solar-pv-permit's electrical scope instead of as a standalone EV receptacle. If your project isn't listed, confirm with City of Henderson Building and Fire Safety Department — Development Services Center at 702-267-3620 before starting work.

Yes. Henderson charges a flat $223 'EV receptacle' fee (Table B -- Miscellaneous Building Items, effective 10/01/2025) for a standalone EV charger installation not combined with a solar PV system. If the charger is installed alongside solar, it is typically bundled into the solar PV permit instead.

Plan review for an ev charger / evse permit in Henderson typically runs 1–10 business days. This is an estimate, not a published figure — confirm current review times with City of Henderson Building and Fire Safety Department — Development Services Center at 702-267-3620.

You'll need: Building / Electrical Permit Application; Single-Line Electrical Diagram. See the required-documents checklist on this page for details on each.

Henderson requires 2 inspection(s) for an ev charger / evse permit, in order: Rough Electrical, Final Electrical. Schedule each through City of Henderson Building and Fire Safety Department — Development Services Center (702-267-3620).

Apply through City of Henderson Building and Fire Safety Department — Development Services Center at 240 S Water Street, Henderson, NV 89015 (PO Box 95050, Henderson, NV 89009-5050). Phone: 702-267-3620, email: COHPermits@cityofhenderson.com. Office hours: Mon–Thu 7:30 AM – 5:30 PM (closed Fridays and holidays); permit technicians Mon–Thu 7:30 AM – 5:30 PM. Official information: https://www.cityofhenderson.com/government/departments/building-and-fire-safety.

Henderson, Nevada has adopted: 2024 International Building Code (IBC) with Southern Nevada amendments — effective January 2, 2026; 2024 International Residential Code (IRC) with Southern Nevada amendments — effective January 2, 2026; 2024 International Existing Building Code (IEBC) — effective January 2, 2026; 2024 International Energy Conservation Code (IECC) with Southern Nevada amendments — effective January 2, 2026; Climate Zone 3B applies below 4,000 ft elevation; 2024 Uniform Plumbing Code (UPC) with Southern Nevada amendments — effective January 2, 2026 (NOTE: UPC, not IPC); 2024 Uniform Mechanical Code (UMC) with Southern Nevada amendments — effective January 2, 2026 (NOTE: UMC, not IMC); 2023 National Electrical Code (NEC) with Southern Nevada amendments — effective January 2, 2026; 2024 International Fire Code (IFC) — effective January 2, 2026; 2024 International Swimming Pool and Spa Code (ISPSC) with Southern Nevada amendments — effective January 2, 2026; 2024 International Wildland-Urban Interface Code (IWUIC) — effective January 2, 2026. Local amendments apply — see the Henderson overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Henderson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.