EV Charger / EVSE Permit (Billed as Power Apparatus Unit Fee) in Elko, Nevada

Required for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Elko, governed by the 2023 NEC as adopted by the City. The City's Electrical Fee Schedule has no dedicated EV-charger or EVSE line item — a charger is billed under the general 'Power Apparatus' unit fee category (Electrical Fee Schedule, Table 5.1, item 5), which the schedule expressly defines to cover 'motors, generators, transformers, rectifiers, synchronous converters, capacitors, industrial heating, air conditioners and heat pumps, cooking or baking equipment and other apparatus,' rated by horsepower (HP), kilowatt (kW), kilovolt-ampere (kVA), or kVAR — the same rating basis (kW) used for EVSE nameplate output — plus the standard $40.00 Processing Fee, subject to the $87.00 per-permit minimum.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for installation of an EV charger circuit; apply through the City's E-Permits portal using the universal Building Permit Application Form (check the 'Elec' box)
  • Governed by the 2023 NEC as adopted by the City of Elko, including Article 625 (Electric Vehicle Power Transfer Systems)
  • Electrical Load Calculation form required for service sizing if the charger install affects the panel/service
  • $87.00 minimum charge per permit/application applies (Processing Fee $40.00 + minimum Permit Fee $47.00), same as for any other electrical permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Processing Fee (in addition to system/unit fees)City of Elko Electrical Permit Fees, Table 5 & 5.1; minimum total charge per permit is $87.00
$40.00
Power Apparatus — up to and including 1 kW/HP/kVACity of Elko Electrical Fee Schedule, Table 5.1, item 5 (Power Apparatus); no EV-charger-specific line exists, so a charger is classed here by its rated kW output
$4.25
Power Apparatus — over 1 and not over 10 kW/HP/kVACovers most Level 2 residential EVSE units (typically 7.2-11.5 kW nameplate rating)
$11.00
Power Apparatus — over 10 and not over 50 kW/HP/kVAWould cover higher-output Level 2 or lower-tier DC fast chargers
$22.00
Services 600 volts or less, not over 200 amperesApplies in addition/instead if a new/upgraded electrical service is required to support the charger
$27.25 each

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit (Billed as Power Apparatus Unit Fee) permit actually take in Elko?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Charger circuit wiring and box placement verified before walls are closed, if applicable

  2. 2

    Final

    EVSE installed and connections verified per 2023 NEC Article 625

See the full Elko inspection guide — scheduling & re-inspection fees →

Tips

  • The City of Elko has no dedicated EV-charger fee line — a charger circuit is billed under the general 'Power Apparatus' unit fee category (Table 5.1, item 5), rated by the charger's kW/HP/kVA nameplate output, the same category used for motors, transformers, and heat pumps.
  • Most residential Level 2 EVSE (7.2-11.5 kW) falls in the 'over 1 and not over 10' tier ($11.00); confirm your specific unit's rated output against the tier boundaries.
  • The $87.00 per-permit minimum (Processing Fee $40.00 + minimum Permit Fee $47.00) applies to an EV charger permit as to any other standalone electrical permit.

Frequently asked questions

Elko requires an ev charger / evse permit (billed as power apparatus unit fee) for: Electrical permit required for installation of an EV charger circuit; apply through the City's E-Permits portal using the universal Building Permit Application Form (check the 'Elec' box); Governed by the 2023 NEC as adopted by the City of Elko, including Article 625 (Electric Vehicle Power Transfer Systems); Electrical Load Calculation form required for service sizing if the charger install affects the panel/service; $87.00 minimum charge per permit/application applies (Processing Fee $40.00 + minimum Permit Fee $47.00), same as for any other electrical permit. If your project isn't listed, confirm with City of Elko Building Department at (775) 777-7220 before starting work.

The City of Elko has no dedicated EV-charger fee. The $40.00 Electrical Permit Processing Fee applies, plus a Power Apparatus unit fee based on the charger's rated kW/HP/kVA output ($4.25 up to 1 kW, $11.00 for over 1 up to 10 kW — the tier covering most residential Level 2 EVSE), subject to an $87.00 per-permit minimum total charge, per the City of Elko Electrical Fee Schedule.

Elko does not publish a plan-review timeline for this permit. Contact City of Elko Building Department at (775) 777-7220 for current turnaround.

You'll need: Building Permit Application Form (Elec). Depending on your project, Elko may also ask for: Electrical Load Calculation. See the required-documents checklist on this page for details on each.

Elko requires 2 inspection(s) for an ev charger / evse permit (billed as power apparatus unit fee), in order: Rough-In, Final. Schedule each through City of Elko Building Department ((775) 777-7220).

Apply through City of Elko Building Department at 1753 College Avenue, Elko, NV 89801. Phone: (775) 777-7220, email: Permits@elkocitynv.gov. Office hours: Elko City Hall, 1751 College Avenue, Elko, Nevada 89801; Building Department at 1753 College Avenue. The Building Department accepts electronic submittals only (E-Permits portal). Main city phone: 775-777-7100; Building Department direct: (775) 777-7220.. Official information: https://www.elkocity.com/departments/building_department/index.php.

Elko, Nevada has adopted: Nevada is a home-rule state for building codes: there is no single mandatory statewide building-code edition — each city and county adopts and amends its own code. The only genuine statewide floor is the energy code: Nevada's Energy Assurance/building energy standards reference the IECC, and NRS 701.220 directs the State to adopt and update energy efficiency standards for new construction (Nevada has moved through 2018/2021/2024 IECC cycles at the state level over time). Always confirm the specific adopted edition for the city or county in question rather than assuming a uniform statewide building code. Source: Nevada Legislature NRS Chapter 701 (State Office of Energy) and Nevada Public Utilities/Energy Office building-energy program pages.; City of Elko adopted the 2024 International Building Code (IBC), with Appendices H, J and Q and certain city modifications, effective per City Council adoption on December 9, 2025. Source: City of Elko Building Codes/Design Standards page.; 2024 International Residential Code (IRC), adopted by the City of Elko with the exception of Chapters 11 through 43, except that Chapter 42 (Electrical) is retained. Source: City of Elko Building Codes/Design Standards page.; 2024 International Existing Building Code (IEBC), adopted by the City of Elko with City of Elko Building Code Amendments. Source: City of Elko Building Codes/Design Standards page.; 2024 International Fire Code (IFC), adopted by the City of Elko. Source: City of Elko Building Codes/Design Standards page.; 2024 International Energy Conservation Code (IECC), adopted by the City of Elko. Source: City of Elko Building Codes/Design Standards page.; 2024 Uniform Mechanical Code (UMC) — Nevada jurisdictions commonly use the Uniform Mechanical Code (IAPMO) rather than the International Mechanical Code; City of Elko adopted the 2024 UMC. Source: City of Elko Building Codes/Design Standards page.; 2024 Uniform Plumbing Code (UPC) — adopted by the City of Elko (Nevada jurisdictions commonly use the UPC, not the International Plumbing Code). Source: City of Elko Building Codes/Design Standards page.; 2023 National Electrical Code (NEC), with necessary provisions, adopted by the City of Elko. Source: City of Elko Building Codes/Design Standards page.; ICC code books (IBC, IRC, IEBC, IFC, IECC) available at www.iccsafe.org; UPC and UMC code books available at the International Association of Plumbing and Mechanical Officials (IAPMO) website, www.iapmo.org; NEC available at the National Fire Protection Association website, www.nfpa.org. Source: City of Elko Building Codes/Design Standards page.. Local amendments apply — see the Elko overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Elko building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.