The City of Fallon has no dedicated EV charger permit, application, or fee schedule. Installation of an electric vehicle charging station (Level 1/2 EVSE) is electrical work and falls under the City's standard Electrical Permit process (2023 NEC as adopted by Ordinance No. 788), using the Permit Application's 'Minor Electrical & Plumbing' section (new electric circuit) or, for a panel/service upgrade, the amperage-change field — the same mechanism documented in the electrical-permit entry. No EV-specific line item was found in the Municode-hosted ordinance text or on the City website. Re-chased exhaustively 2026-07-20: directly downloaded and text-extracted the City's Building Permit Application PDF (no fee table present, only a 'Minor Electrical & Plumbing' checkbox section), and re-checked the Business Licenses & Building Permits page and a fresh web search for any City of Fallon fee-schedule resolution PDF -- none found. This confirms the same gap independently, not merely an unrechased carryover.

Reviewed 2026-07-20 · Source

When you need this permit

  • A construction permit from the city engineer is required for the electrical work associated with an EV charger installation (City Code § 17.08.010)
  • Governed by the 2023 NEC (including Article 625, Electric Vehicle Power Transfer System) as adopted by City of Fallon Ordinance No. 788 (City Code § 17.04.020(J))
  • Use the Permit Application's 'Minor Electrical & Plumbing' section — check 'new electric circuits' for a dedicated EVSE circuit, or specify the new amperage if a service/panel upgrade is required to support the charger
  • Construction must be performed by a contractor licensed in the State of Nevada, except for qualifying Home Owner/Builders Owner-builderContractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Fee (applies to EV charger circuit/service work; no distinct EV line)City of Fallon Code of Ordinances § 17.08.080; confirm current amount with the Building Department at (775) 423-5107
Not published — set by City Council resolution; no dedicated electrical or EV-charger fee table found on the City website or in the Municode-hosted ordinance text

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / Electric Vehicle Charging Station Permit permit actually take in Fallon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building Department Inspections

    The city engineer performs a sufficient number of inspections to assure project safety (City Code § 17.08.070(B)); coordinate rough-in/final electrical inspection scheduling directly with the Building Department at (775) 423-5107

See the full Fallon inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate 'EV charger permit' in Fallon — apply for a standard Electrical Permit and select 'new electric circuits' (or the applicable amperage change) on the Minor Electrical & Plumbing section of the Permit Application.
  • The City's adopted 2023 NEC includes Article 625 (Electric Vehicle Power Transfer System), which governs EVSE installation requirements even though no City-specific EV fee or checklist has been published.

Frequently asked questions

Yes — an EV charger circuit is electrical work and requires the City's standard Electrical Permit (governed by the 2023 NEC, including Article 625). There is no separate EV-specific permit, application, or fee; it is processed through the same 'Minor Electrical & Plumbing' pathway as any other new circuit or service-change work.

In Fallon, the published Electrical Permit Fee (applies to EV charger circuit/service work; no distinct EV line) is: Not published — set by City Council resolution; no dedicated electrical or EV-charger fee table found on the City website or in the Municode-hosted ordinance text. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Fallon does not publish a plan-review timeline for this permit. Contact City of Fallon Building Department (Engineering and Public Works) at (775) 423-9862 / (775) 423-5107 for current turnaround.

You'll need: City of Fallon Building Department Permit Application. See the required-documents checklist on this page for details on each.

Fallon requires 1 inspection(s) for an ev charger / electric vehicle charging station permit, in order: Building Department Inspections. Schedule each through City of Fallon Building Department (Engineering and Public Works) ((775) 423-9862 / (775) 423-5107).

Apply through City of Fallon Building Department (Engineering and Public Works) at 55 West Williams Avenue, Fallon, Nevada 89406. Phone: (775) 423-9862 / (775) 423-5107, email: buildingpermits@fallonnevada.gov. Office hours: City Building Department, 55 W. Williams Avenue, Fallon, NV 89406 (fax (775) 423-8874). The Building Department is organizationally part of the City's Engineering and Public Works Department, which is responsible for 'Airport Oversight, Building Inspections, Building Permit Issuance.' Applications may be submitted in person, or (for roofing/siding-type minor work per the permit form) scanned and emailed to the office; the City Engineer reviews and issues construction permits per City Code Chapter 17.08.. Official information: https://www.fallonnevada.gov/business/business-licenses-building-permits/.

Fallon, Nevada has adopted: The City of Fallon self-administers its own building permitting program within city limits — it is NOT routed to Churchill County. The City Building Department (55 W. Williams Avenue) issues permits and performs inspections directly; Churchill County's separate Building Department (270 S. Maine Street, Suite A, Fallon, NV) has its own, distinct jurisdiction limited to unincorporated Churchill County. Source: City of Fallon Code of Ordinances Chapter 17.04 and 17.08 (city engineer/building department issues permits); City of Fallon Departments page (Engineering and Public Works: 'Airport Oversight, Building Inspections, Building Permit Issuance'); Churchill County Building Department page (separate department/address for unincorporated county).; Nevada has no single mandatory statewide building code edition for all jurisdictions (unlike Montana) — Nevada is a home-rule state for building codes, with the principal statewide requirement being an energy-code floor under NRS 701.220 (local governments must adopt a code at least as stringent as the most recent published IECC edition, currently the 2024 IECC per the Nevada Governor's Office of Energy). Each city/county separately adopts its own building code editions and amendments. City of Fallon's actual adopted editions are documented below from its own Code of Ordinances — not assumed from any statewide default.; 2024 International Building Code (IBC), with Appendices C, E, H, and I, adopted by the City of Fallon with local additions/deletions (Section 113 deleted; Section 312.1 amended; Section 1612.3 amended to insert 'Churchill County and Incorporated Areas' and 'April 5, 2021' effective flood-hazard date). Source: City of Fallon Code of Ordinances § 17.04.020(A); 2024 International Residential Code (IRC), with Appendices AB, BF, CA, CB, CD, and CE, adopted by the City of Fallon (Section R112 deleted). Source: City of Fallon Code of Ordinances § 17.04.020(B); 2024 International Existing Building Code (IEBC), with Appendices A and B, adopted by the City of Fallon (Section 112 deleted). Source: City of Fallon Code of Ordinances § 17.04.020(C); 2024 International Fuel Gas Code (IFGC), with Appendices A, B, and C, adopted by the City of Fallon (Section 112 deleted). Source: City of Fallon Code of Ordinances § 17.04.020(D); 2024 International Mechanical Code (IMC), adopted by the City of Fallon (Sections 112 and 113 deleted). Source: City of Fallon Code of Ordinances § 17.04.020(E); 2024 International Swimming Pool and Spa Code (ISPSC), adopted by the City of Fallon (Section 112 deleted). Source: City of Fallon Code of Ordinances § 17.04.020(F); 2024 Uniform Plumbing Code (UPC), with Appendices A, B, and D, adopted by the City of Fallon (Table 104.5 replaced with the City's own Table B) — Nevada jurisdictions may adopt either the UPC or the IPC; Fallon adopted the UPC. Source: City of Fallon Code of Ordinances § 17.04.020(G); 2024 Uniform Mechanical Code (UMC), with Appendices A, B, and C, adopted by the City of Fallon (Table 104.5 replaced with the City's own Table C) — adopted alongside (in addition to) the IMC. Source: City of Fallon Code of Ordinances § 17.04.020(H); 2024 International Energy Conservation Code (IECC), adopted by the City of Fallon (Section 109 deleted) — satisfies the NRS 701.220 statewide energy-code floor. Source: City of Fallon Code of Ordinances § 17.04.020(I); NRS 701.220; 2023 National Electrical Code (NEC), adopted by the City of Fallon. Source: City of Fallon Code of Ordinances § 17.04.020(J); 2024 Northern Nevada Amendments (NNA), published by the Northern Nevada Chapter of the International Code Council on February 20, 2025, adopted by the City of Fallon, amending IBC Table 1608.2.1 (ground snow load table) to replace 'Lyon County' with 'City of Fallon and Lyon County.' Source: City of Fallon Code of Ordinances § 17.04.020(K); All codes adopted 'by reference,' together with the noted supplements, amendments, and additions/deletions, per Ordinance No. 747 (adopted March 4, 2014) as most recently amended by Ordinance No. 788 (adopted December 2, 2025). 'Jurisdiction' and similar terms in the adopted codes mean the City of Fallon. Source: City of Fallon Code of Ordinances §§ 17.04.010, 17.04.020, 17.04.030. Local amendments apply — see the Fallon overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fallon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.