Solar Photovoltaic (PV) Permit in Fallon, Nevada
VerifiedRequired for installation of rooftop or ground-mounted solar photovoltaic systems within Fallon city limits. Falls under the City's general construction-permit requirement, governed by the 2024 IRC/IBC (structural/mounting) and the 2023 NEC (Article 705 interconnection requirements) as adopted by the City of Fallon.
Verified 2026-07-03 · Source
When you need this permit
- A construction permit from the city engineer is required for solar PV installation as electrical/structural work under City Code § 17.08.010 ('erection of a building... plumbing mechanical, electrical... and other work covered in the codes adopted')
- Structural/mounting design must comply with the 2024 IBC/IRC as adopted by City of Fallon Ordinance No. 788, including the 2024 Northern Nevada Amendments ground-snow-load table (IBC Table 1608.2.1, 'City of Fallon and Lyon County')
- Electrical interconnection must comply with the 2023 NEC (including Article 705 interconnected/utility-interactive system requirements) as adopted by City Code § 17.04.020(J)
- No dedicated solar-specific plan-requirements document (of the kind some larger Nevada/Montana cities publish) was found published by the City of Fallon; applicants should submit under the standard Building Permit Application and confirm submittal specifics (one-line diagram, structural calculations, module/inverter listings) directly with the Building Department
Required documents
- Required
City of Fallon Building Department Permit Application
Standard permit application; submit as a Building/Electrical permit at 55 W. Williams Avenue. No solar-specific application or checklist was found published by the City
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building/Electrical Permit Fee (solar PV) | Not published — set by City Council resolution; no dedicated solar fee table found on the City website or in the Municode-hosted ordinance text | City of Fallon Code of Ordinances § 17.08.080; confirm current amount with the Building Department at (775) 423-5107 |
Review timeline
Not published
Fallon does not publish a plan-review timeline — contact the building department for current turnaround.
Inspection process
- 1
Building Department Inspections
The city engineer performs a sufficient number of inspections to assure project safety (City Code § 17.08.070(B)); coordinate rough electrical/final inspection scheduling directly with the Building Department at (775) 423-5107
Tips
- No City of Fallon-specific solar PV submittal-requirements document (site plan/one-line diagram/labeling diagram checklist) was found published online — call the Building Department at (775) 423-5107 before submitting to confirm exactly what plan set they expect.
- Structural mounting calculations must still account for Fallon's adopted 2024 Northern Nevada Amendments ground-snow-load entry (IBC Table 1608.2.1) — confirm the current design value with the Building Department.
Frequently asked questions
- Does Fallon have a dedicated solar permit application?
- No dedicated solar-specific application or requirements checklist was found published by the City of Fallon as of this review. Solar PV work is permitted under the City's standard Building Permit Application and reviewed against the adopted 2024 IBC/IRC (structural) and 2023 NEC (electrical interconnection, NEC Article 705).
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
- City of Fallon Building Department (Engineering and Public Works) — official building department
- Chapter 17.04 - Construction Codes | City of Fallon Code of Ordinances (Municode)
- Chapter 17.08 - Construction Permits | City of Fallon Code of Ordinances (Municode)
- Building Permit Application (PDF) | City of Fallon
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fallon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Fallon
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Nevada →
Project checklist — coming soon
Describe your project once and get every permit, document, and fee it triggers in Fallon — in one checklist. Leave your email and we'll tell you when it's ready.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.