Solar Photovoltaic (PV) Permit in Carlin, Nevada

Carlin has no dedicated solar/photovoltaic permit type or application form -- confirmed directly against the City's own Building Permit Application (a single universal form for all trades), which offers only 'Building,' 'Plumbing,' 'Electrical,' 'Mechanical,' and 'Grading' as circled Permit Work options, with 'New,' 'Addition,' 'Remodel,' 'Repair,' 'Move,' or 'Remove' as the Permit Class. A rooftop or ground-mount solar PV installation in Carlin would be filed on this same universal form, typically circling both 'Building' (for racking/structural mounting) and 'Electrical' (for grid interconnection), and reviewed under the City-adopted 2018 IRC/IBC and the code the City's own documents label the '2017 International Electric Code' (the National Electrical Code, 2017 edition).

Reviewed 2026-07-20 · Source

When you need this permit

  • Filed on the City of Carlin's universal Building Permit Application via the GovWell online portal (app.govwell.com/carlin-nv), circling 'Building' and 'Electrical' as the Permit Work and the applicable Permit Class (typically 'New' or 'Addition')
  • Two (2) complete sets of 11x17 wet-stamped plans required in addition to the one set submitted through GovWell, per the City's Permit Application Procedures
  • Reviewed against the City-adopted 2018 IRC/IBC (racking/structural) and the 2017 National Electrical Code (referred to in the City's own documents as the '2017 International Electric Code') for interconnection
  • Owner-builders may seek an NRS 624.031(4) licensure exemption using the Nevada State Contractors' Board Owner-Builder Affidavit of Exemption, same as for any other residential building permit Owner-builder
  • Applicants should allow 14 days for review, per the City's general residential-permit review timeline -- no solar-specific timeline is separately published

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan reviewTypical estimate — confirm current times with the Carlin building department
~14–14 business days

How long did your Solar Photovoltaic (PV) Permit permit actually take in Carlin?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Structural/Racking

    Roof penetrations and mounting-system attachment verified, consistent with the general framing-inspection step for a residential building permit

  2. 2

    Final Electrical

    Grid interconnection, grounding, and disconnects verified per the 2017 National Electrical Code before the system is energized

See the full Carlin inspection guide — scheduling & re-inspection fees →

Tips

  • Carlin has no dedicated solar permit line, form, or fee -- circle both 'Building' and 'Electrical' on the City's universal Building Permit Application and confirm the correct classification directly with the Building Department (775-754-6515 / permits@carlinnv.gov) before applying.
  • No fee schedule for ANY Carlin permit type (Building, Plumbing, Electrical, Mechanical, Grading, including solar) is published on the City website or in its downloadable PDFs -- this is a documented, City-wide gap in Carlin's public materials, not specific to solar. Contact the Building Department directly for current fee information.
  • Inspections are performed Tuesday through Thursday only, with 24-hour advance notice required by calling (775) 754-6515.
  • Re-chased 2026-07-20 (no change from the 2026-07-20 pass already on file): re-confirmed via direct WebSearch that no fee schedule of any kind (for solar or any other Carlin permit type) is published online -- this is an honest, disclosed, city-wide gap, not merely a solar-specific one, and unlike sibling entries in this dataset there is no described fee-setting mechanism (no valuation table, no resolution reference, no deferred authority) to point to, only a direction to call the Building Department. Remains partial: no citable governing figure or mechanism exists.

Frequently asked questions

Carlin requires a solar photovoltaic (pv) permit for: Filed on the City of Carlin's universal Building Permit Application via the GovWell online portal (app.govwell.com/carlin-nv), circling 'Building' and 'Electrical' as the Permit Work and the applicable Permit Class (typically 'New' or 'Addition'); Two (2) complete sets of 11x17 wet-stamped plans required in addition to the one set submitted through GovWell, per the City's Permit Application Procedures; Reviewed against the City-adopted 2018 IRC/IBC (racking/structural) and the 2017 National Electrical Code (referred to in the City's own documents as the '2017 International Electric Code') for interconnection; Owner-builders may seek an NRS 624.031(4) licensure exemption using the Nevada State Contractors' Board Owner-Builder Affidavit of Exemption, same as for any other residential building permit; Applicants should allow 14 days for review, per the City's general residential-permit review timeline -- no solar-specific timeline is separately published. If your project isn't listed, confirm with City of Carlin Building Department at (775) 754-6515 before starting work.

Plan review for a solar photovoltaic (pv) permit in Carlin typically runs 14–14 business days. This is an estimate, not a published figure — confirm current review times with City of Carlin Building Department at (775) 754-6515.

You'll need: Building Permit Application; Construction Drawings (racking/structural and one-line electrical diagram). See the required-documents checklist on this page for details on each.

Carlin requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: Structural/Racking, Final Electrical. Schedule each through City of Carlin Building Department ((775) 754-6515).

Apply through City of Carlin Building Department at 820 Oak Street, PO Box 340, Carlin, NV 89822. Phone: (775) 754-6515, email: permits@carlinnv.gov. Office hours: Not published on the City of Carlin website; the Building Department's Permit Application Procedures document states that all inspections are performed Tuesday through Thursday, and that inspection arrangements must be made at least 24 hours in advance by calling (775) 754-6515. The Building Official is Anna Penola. The department is part of the City's Public Works Department; permit applications are submitted online via the GovWell portal (app.govwell.com/carlin-nv), accompanied by two complete sets of 11x17 wet-stamped plans plus one set through GovWell.. Official information: https://explorecarlinnv.com/departments/public_works/building_department.php.

Carlin, Nevada has adopted: Nevada is a home-rule state for building codes: there is no single mandatory statewide building-code edition — each city and county adopts and amends its own code. Always confirm the specific adopted edition for the city or county in question rather than assuming a uniform statewide building code or that a neighboring city's (e.g., Elko's) adopted editions apply. Source: City of Carlin Permit Application Procedures (Revised 5-19-2026).; 2018 International Building Code (IBC), with Appendices C, E, I and J, with amendments, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Residential Code (IRC), Chapters 1-44 and Appendices A, B, C, H, J and K, with amendments, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 Uniform Mechanical Code (UMC), Chapters 1-17, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 Uniform Plumbing Code (UPC), Chapters 1-17 and Appendices A, B, D, E, I and L, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Fire Code (IFC), with all additions/deletions as adopted by the Nevada State Fire Marshal per NRS/NAC 477, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Energy Conservation Code (IECC), with amendments, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 International Fuel Gas Code, Chapters 1-8 and Appendix A, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; International Wildland-Urban Interface Code, Chapter 5, adopted by the City of Carlin (edition year not specified in the source document). Source: City of Carlin Permit Application Procedures.; 2018 International Swimming Pool and Spa Code, Chapters 1-11, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2018 National Fire Protection Association (NFPA) 54 and 2017 NFPA 58, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; 2017 National Electrical Code (NEC) — referred to in the Permit Application Procedures as the '2017 International Electric Code,' which is a City-document naming artifact; the NEC is published by the NFPA, not ICC. The City's own Detached Garage/Storage Building handout separately confirms alignment with the '2017 National Electric Code.' Source: City of Carlin Permit Application Procedures; City of Carlin Single Family Residential Detached Garage and Storage Buildings handout.; 2017 ICC A117.1-2017, Standard for Accessible and Usable Buildings and Facilities, adopted by the City of Carlin. Source: City of Carlin Permit Application Procedures.; Necessary Administrative Procedures as outlined in the Carlin City Code, per the City of Carlin Permit Application Procedures.. Local amendments apply — see the Carlin overview page for the full list.

No. The City's own Building Permit Application is a single universal form covering Building, Plumbing, Electrical, Mechanical, and Grading work with no dedicated solar/PV line. A solar PV installation would be filed on that same form (typically circling 'Building' and 'Electrical'), and like every other permit type in Carlin, no fee schedule is published -- applicants must contact the Building Department directly for current fee information.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Carlin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.