Henderson building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Henderson, Nevada.
Verified 2026-06-30 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 240 S Water Street, Henderson, NV 89015 (PO Box 95050, Henderson, NV 89009-5050)
- Phone
- 702-267-3620
- Office hours
- Mon–Thu 7:30 AM – 5:30 PM (closed Fridays and holidays); permit technicians Mon–Thu 7:30 AM – 5:30 PM
- Website
- Official site
Published scheduling rules
- All submittals received after 4:30 PM or on Fri–Sun and holidays are processed as if received the next business day. (Residential Addition / Remodel Permit)
Inspection sequence
Applies to: Residential Building Permit — New Construction (Custom Single-Family)
- 1
Foundation / Footing
Before concrete pour — verify forms, rebar, anchor bolts, and frost depth compliance
- 2
Underground Rough-In (MEP)
Underground plumbing, electrical conduit, and gas piping before slab or backfill
- 3
Framing
After framing, sheathing, and all rough-in trades complete — before insulation or wall cover
- 4
Insulation
Insulation installed and energy code compliance items checked before drywall
- 5
Final
All work complete — verify compliance with approved plans, Certificate of Occupancy issued
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings and foundation before concrete pour
- 2
Framing
Structural framing, egress windows, and fire separation
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-ins before walls closed
- 4
Final
All work complete, smoke/CO detectors, address posted
Applies to: Commercial Tenant Improvement Permit
- 1
Rough Framing / Structural
Non-structural walls, framing, blocking before cover
- 2
MEP Rough-In
Electrical, plumbing, and mechanical rough-ins — coordinate with trade permit inspections
- 3
Above-Ceiling / Above T-Bar
Before ceiling tiles or drywall go up — verify fire-rated assemblies, MEP above ceiling
- 4
Final / Certificate of Occupancy
All work complete; CO issued for change of occupancy or new tenant
Applies to: Swimming Pool / Spa Permit
- 1
Pre-Gunite / Steel
Rebar, bond beam, and rough plumbing before shotcrete/gunite application
- 2
Plumbing / Electrical Rough-In
Equipment pad, conduit, plumbing lines, and bonding before deck pour
- 3
Deck / Barrier
Pool deck, coping, and safety barrier installation
- 4
Final
Completed pool with all equipment operational, barriers in place, electrical bonding verified
Applies to: Fire Sprinkler System Permit
- 1
Underground / Rough-In Sprinkler Piping
Pipe sizing, hangers, and standpipe connections verified before concealment
- 2
Hydrostatic Pressure Test
System tested at 200 psi (or 50 psi above working pressure, whichever is greater) for 2 hours per NFPA 13
- 3
Final — Flow and Alarm Test
Sprinkler heads, flow switch, and fire alarm interconnection verified operational
Applies to: Residential Addition / Remodel Permit
- 1
Rough Framing / Structural
After framing and rough-in trades — before insulation or wall cover
- 2
Insulation (if applicable)
Insulation installed before drywall — required for additions with new conditioned space
- 3
Final
All work complete per approved plans
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical / Conduit
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final — Structural / Mounting
Panel racking, roof attachment, penetration sealing verified
- 3
Final — Electrical
Inverter installation, interconnection, and labeling verified
Applies to: Block / Screen Wall Permit
- 1
Footing / Rebar
Before concrete pour — verify footing depth and rebar placement
- 2
Final
Completed wall — verify height, alignment, and cap installation
Applies to: Electrical Permit
- 1
Rough-In Electrical
Conduit, wiring, and box placement before walls closed
- 2
Final
All devices installed, panel labeled, GFCI/AFCI protection verified, service energized
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
Circuit, conduit, and disconnect placement verified before energizing
- 2
Final Electrical
EV receptacle/charger installation, GFCI/load management, and labeling verified
Applies to: Fire Alarm System Permit
- 1
Rough-In Wiring
Device locations, conduit, and wiring verified before wall closure
- 2
Final — Functional System Test
Full test of initiating and indicating devices, notification appliances, and central-station monitoring connection
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and mechanical equipment rough-in before walls closed
- 2
Final
Equipment operational, combustion air verified, venting and clearances correct
Applies to: Plumbing Permit
- 1
Underground / Rough-In
After pipes installed, before walls closed or slab poured — pressure test required
- 2
Final
All fixtures connected, no leaks, proper venting verified
Applies to: Sign Permit
- 1
Electrical Rough-In (illuminated signs only)
Circuit and disconnect placement verified before the sign is energized
- 2
Final Sign Inspection
Installed sign matches approved plans — location, area, height, structural attachment, address display, and illumination compliance verified
Final inspection only: Change of Occupancy / Certificate of Occupancy Permit, Demolition Permit, Residential Reroof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Henderson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Henderson building permits
Get alerts for Henderson
We'll email you when Henderson's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.