Skip to main content
PermitBase

Henderson building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Henderson, Nevada.

Verified 2026-06-30 · Source

How to schedule

Inspections are requested through the building department below.

Address
240 S Water Street, Henderson, NV 89015 (PO Box 95050, Henderson, NV 89009-5050)
Phone
702-267-3620
Office hours
Mon–Thu 7:30 AM – 5:30 PM (closed Fridays and holidays); permit technicians Mon–Thu 7:30 AM – 5:30 PM

Published scheduling rules

  • All submittals received after 4:30 PM or on Fri–Sun and holidays are processed as if received the next business day. (Residential Addition / Remodel Permit)

Inspection sequence

Applies to: Residential Building Permit — New Construction (Custom Single-Family)

  1. 1

    Foundation / Footing

    Before concrete pour — verify forms, rebar, anchor bolts, and frost depth compliance

  2. 2

    Underground Rough-In (MEP)

    Underground plumbing, electrical conduit, and gas piping before slab or backfill

  3. 3

    Framing

    After framing, sheathing, and all rough-in trades complete — before insulation or wall cover

  4. 4

    Insulation

    Insulation installed and energy code compliance items checked before drywall

  5. 5

    Final

    All work complete — verify compliance with approved plans, Certificate of Occupancy issued

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour

  2. 2

    Framing

    Structural framing, egress windows, and fire separation

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors, address posted

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Rough Framing / Structural

    Non-structural walls, framing, blocking before cover

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-ins — coordinate with trade permit inspections

  3. 3

    Above-Ceiling / Above T-Bar

    Before ceiling tiles or drywall go up — verify fire-rated assemblies, MEP above ceiling

  4. 4

    Final / Certificate of Occupancy

    All work complete; CO issued for change of occupancy or new tenant

Applies to: Swimming Pool / Spa Permit

  1. 1

    Pre-Gunite / Steel

    Rebar, bond beam, and rough plumbing before shotcrete/gunite application

  2. 2

    Plumbing / Electrical Rough-In

    Equipment pad, conduit, plumbing lines, and bonding before deck pour

  3. 3

    Deck / Barrier

    Pool deck, coping, and safety barrier installation

  4. 4

    Final

    Completed pool with all equipment operational, barriers in place, electrical bonding verified

Applies to: Fire Sprinkler System Permit

  1. 1

    Underground / Rough-In Sprinkler Piping

    Pipe sizing, hangers, and standpipe connections verified before concealment

  2. 2

    Hydrostatic Pressure Test

    System tested at 200 psi (or 50 psi above working pressure, whichever is greater) for 2 hours per NFPA 13

  3. 3

    Final — Flow and Alarm Test

    Sprinkler heads, flow switch, and fire alarm interconnection verified operational

Applies to: Residential Addition / Remodel Permit

  1. 1

    Rough Framing / Structural

    After framing and rough-in trades — before insulation or wall cover

  2. 2

    Insulation (if applicable)

    Insulation installed before drywall — required for additions with new conditioned space

  3. 3

    Final

    All work complete per approved plans

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical / Conduit

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final — Structural / Mounting

    Panel racking, roof attachment, penetration sealing verified

  3. 3

    Final — Electrical

    Inverter installation, interconnection, and labeling verified

Applies to: Block / Screen Wall Permit

  1. 1

    Footing / Rebar

    Before concrete pour — verify footing depth and rebar placement

  2. 2

    Final

    Completed wall — verify height, alignment, and cap installation

Applies to: Electrical Permit

  1. 1

    Rough-In Electrical

    Conduit, wiring, and box placement before walls closed

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified, service energized

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Circuit, conduit, and disconnect placement verified before energizing

  2. 2

    Final Electrical

    EV receptacle/charger installation, GFCI/load management, and labeling verified

Applies to: Fire Alarm System Permit

  1. 1

    Rough-In Wiring

    Device locations, conduit, and wiring verified before wall closure

  2. 2

    Final — Functional System Test

    Full test of initiating and indicating devices, notification appliances, and central-station monitoring connection

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed

  2. 2

    Final

    Equipment operational, combustion air verified, venting and clearances correct

Applies to: Plumbing Permit

  1. 1

    Underground / Rough-In

    After pipes installed, before walls closed or slab poured — pressure test required

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Sign Permit

  1. 1

    Electrical Rough-In (illuminated signs only)

    Circuit and disconnect placement verified before the sign is energized

  2. 2

    Final Sign Inspection

    Installed sign matches approved plans — location, area, height, structural attachment, address display, and illumination compliance verified

Henderson building permits

Get alerts for Henderson

We'll email you when Henderson's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.