Electrical Permit in Henderson, Nevada

Required for standalone electrical work in Henderson, including panel upgrades, new circuits, service changes, EV charger installations, and appliance hookups. Governed by the 2023 NEC with Southern Nevada local amendments (effective January 2, 2026). Fees per Table C — Building MPE Items.

Verified 2026-06-30 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Service regardless of amperage (including first meter socket)$190Henderson DSC Fee Schedule Table C — Building MPE Items, effective 10/01/2025
Each individual meter socket / sub-panel / distribution board$175Table C
Each appliance (no limit to HP, KW, or KVA rating)$155Table C — applies to HVAC appliances, water heaters, dryers, ranges, etc.
Each general lighting outlet, receptacle outlet, or switch (multi-outlet assembly per 5 ft or portion)$152Table C
EV receptacle (not part of a PV system)$223Table B — Miscellaneous Building Items; EV receptacle fee
Each temporary power pole or service$206Table C
Signal, alarm, television outlet, control panel, antenna, or telephone switchboard (over 50 volts)$178Table C
Underwater light (each)$190Table C
Other electrical inspections (per hour)$286Table C
Stand-alone electrical plan check (hourly)$429Table C

Review timeline

~110 business days

Typical estimate — confirm current times with the Henderson building department

Inspection process

  1. 1

    Rough-In Electrical

    Conduit, wiring, and box placement before walls closed

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified, service energized

Tips

Frequently asked questions

How much does a panel upgrade cost to permit in Henderson?
A service entrance/panel upgrade is $190 per the Henderson DSC Fee Schedule Table C (effective 10/01/2025). Additional meter sockets or sub-panels are $175 each.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Henderson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Henderson

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.