Required for electrical installation, alteration, or repair work in Boulder City, governed by the 2017 National Electrical Code (NEC) with Southern Nevada Building Code Amendments.

Verified 2026-07-03 · Source

From$40.00Permit Issuance — see all 9 fees below

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Permit Issuance$40.002026 Administrative Code, Table C
Receptacle, switch and lighting outlet (each)$1.002026 Administrative Code, Table C
Appliance Outlets, Residential or Commercial (each)$5.002026 Administrative Code, Table C
Service (same-for-same), 600V or less and not over 200 amperes, includes Temporary Power (each)$40.002026 Administrative Code, Table C
Service (same-for-same), 600V or less and over 200 up to 1,000 amperes (each)$60.002026 Administrative Code, Table C
Service (same-for-same), over 600V and/or over 1,000 amperes (each)$85.002026 Administrative Code, Table C
Electrical permit bundled with a building permit18.00% of the base building permit fee (Table A)2026 Administrative Code, Section 110.2(I)(1)
Service Change (Up to 200 AMP) — per common permit fee flyer$80.002020 Fee Schedule, 'Common Permit Fees' box
Temporary Power$290.002020 Fee Schedule, 'Common Permit Fees' box (includes $40 issuance plus $250 utility connection fee per Table H)

Review timeline

714 business days

Boulder City’s published plan-review target

Inspection process

  1. 1

    Rough-In

    Wiring and box placement before wall closure

  2. 2

    Final

    Devices installed and panel labeled per 2017 NEC

Tips

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boulder City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Boulder City

Electrical Permit in other cities

Compare electrical permit fees across Nevada

Related guides

Project checklist — coming soon

Describe your project once and get every permit, document, and fee it triggers in Boulder City — in one checklist. Leave your email and we'll tell you when it's ready.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.