Demolition Permit — Boulder City, Nevada · Requirements sheet
Verified 2026-07-03 · Source: https://www.bcnv.org/DocumentCenter/View/10814/Demolition-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Boulder City, Nevada
Required for demolition or relocation of any building or structure (or portion thereof) in Boulder City. Governed by 2026 Administrative Code Section 110.2(O) and, for properties in the Historic District, Title 11, Chapter 27 of the Boulder City Code.
Verified 2026-07-03 · Source
When you need this permit
- Demolition permit required prior to the demolition or relocation of any building or structure or portion thereof (2026 Administrative Code Section 110.2(O))
- Site plan must show the structure(s) to be demolished, square footages, and setbacks to remaining structures and property lines
- All utility locations and points of termination must be indicated on the site plan
- A dust pollution management plan with an approved sealant of the lot is required (water is not an approved sealant)
- Report of Hazardous Materials Assessment required as backup documentation
- Structural calculations required if interior load-bearing walls are being removed or modified
- For properties in the Historic District: digital color exterior photographs (all sides) required, plus completion of the Demolition Permit Checklist for Properties in the Historic District; the Community Development Department must delay approval up to 45 days per Title 11, Chapter 27, Section 11-27-6 to make a historical record, allow Historic Preservation Committee review, and inform the owner of rehabilitation incentives
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Final
Site cleared and demolition verified complete
See the full Boulder City inspection guide — scheduling & re-inspection fees →
Tips
- The plan review timeframe for a first review of a Demolition permit is 1-2 weeks. Source: City of Boulder City Demolition Permit Submittal Checklist (02/16/2021 V1).
- For properties in the Historic District, the City may delay approval of the demolition permit up to 45 days under Title 11, Chapter 27, Section 11-27-6 of the Boulder City Code.
- Dust pollution management requires an approved sealant on the lot — water alone is explicitly not an approved sealant.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Boulder City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Boulder City
Demolition Permit in other cities
Compare demolition permit fees across Nevada →
Look up this fee in a different city →