Boulder City does not brand a standalone 'Tenant Improvement permit' — tenant improvements and other alterations to existing commercial space are processed under the City's 'Commercial – Remodel' building permit, which is nonetheless a genuinely distinct submittal track: it has its own published checklist (which itself uses the term 'tenant improvement' for this work), a much shorter published first-review timeframe of 1–2 weeks versus 3–4 weeks for new construction, and fewer prerequisites (no drainage or traffic study requirement). Fees are identical in structure to any building permit: valuation-based Table A plus 65% plan review and $40 issuance. The incoming business will separately need a Certificate of Business Occupancy through the business-license process before operating.

Verified 2026-08-01 · Source

When you need this permit

  • Appropriate zoning must already be in place for the proposed use, and a permanent address including suite numbers (if applicable) must be assigned, before the application can be accepted (Commercial – Remodel checklist, Part 2 Prerequisites — note the drainage-study and traffic-study prerequisites of the new-construction track do not appear on the remodel checklist)
  • All documents must be digitally stamped/signed and emailed to buildingpermits@bcnv.org (20MB per email limit; subject-line keywords such as 'Initial Submittal – [address]' speed processing) (checklist Part 4)
  • A non-refundable plan review deposit equal to the full plan review fee must be paid before staff review any plans/documents; a blank or incomplete checklist makes the submittal incomplete and it will not be reviewed (checklist Part 1; Administrative Code Section 110.2(E))
  • Plans must indicate all tenant space within the building and identify adjacent occupancies and uses on the site plan, plus occupancy separations, fire assemblies and exiting on the floor plan (checklist Part 5)
  • Work must comply with the City's adopted codes as listed on the checklist (2018 IBC/UMC/UPC/IECC/IFC editions and 2017 NEC, with Southern Nevada Building Code Amendments) and Title 11 zoning; the 2018 International Existing Building Code governs work on existing buildings per Administrative Code Section 101.5.2
  • If the tenant improvement changes the space's building-code occupancy classification, a Certificate of Occupancy under Section 113.1 is required through this permit, and the change of occupancy can trigger accessibility-upgrade obligations under Section 107.10.2
  • Properties in the Boulder City Historic District may require Historic Preservation Committee review, which can delay the permit (checklist Part 6)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, Table A)Identical Table A schedule as all Boulder City building permits — the City publishes no TI-specific or commercial-remodel-specific fee line. Valuation is total value of work including labor and materials, set finally by the Building Official (Sections 110.2(D), 111.1). 2026 Building and Safety Division Administrative Code.
$27.00 minimum at $1–$500 valuation; e.g. $45.00 + $9.00/$1,000 in the common $2,001–$25,000 TI range; $639.50 + $3.50/$1,000 above $100,000
Plan Review FeeSection 110.2(F); collected as a non-refundable deposit at submittal (Section 110.2(E)); expedited review is 2x (Section 110.2(G)).
65% of the building permit fee
Permit Issuance FeeAll permits (Section 110.2(A)).
$40.00
Electrical / Plumbing / Mechanical Permit Fees (when associated with the building permit)Section 110.2(I)(1); no separate trade plan-review fee when submitted as one package with the building plans (Section 110.2(J)).
Electrical 18.00%, plumbing 16.50%, mechanical 15.00% of the building permit fee
Certificate of Business Occupancy (for the incoming business, separate process)Table H, Plan Review and Inspection Fees section — obtained through the Business License process, not through this building permit; see the certificate-of-business-occupancy-permit entry.
$60.00 each certificate

Review timeline

Plan reviewBoulder City’s published plan-review target
7–14 business days

How long did your Commercial Tenant Improvement (Commercial – Remodel Permit) permit actually take in Boulder City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Inspections per the permit's Inspection Record

    The Building Official makes the inspections set forth on the Inspection Record assigned to each permit (Section 112.3), scheduled by the permit holder; work may not proceed past an inspection point or be covered/concealed without approval (Section 112.6)

  2. 2

    Final Inspection

    Made after all work required by the building permit is completed (Section 112.3.3)

  3. 3

    Certificate of Business Occupancy inspections (separate, post-construction)

    Before the business operates in the finished space, Building and Safety and Fire Department inspections through the Business License process lead to the $60 Certificate of Business Occupancy (Sections 112.7, 113.2); these are made only after all other agency inspections are complete and the Table H fee is paid

See the full Boulder City inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separately named 'Tenant Improvement permit' in Boulder City — apply using the Commercial – Remodel checklist, which explicitly treats tenant improvements (its kitchen-plan item begins 'If tenant improvement includes a full service kitchen…'). A third commercial track, Commercial – Foundation Only, also exists for phased projects.
  • The remodel track's published first review (1–2 weeks) is roughly half to a third of the new-construction window (3–4 weeks) — but only if the submittal is complete; incomplete packages and blank checklists are not reviewed at all.
  • Budget for the sequence: TI building permit (Table A + 65% plan review + $40 issuance) during construction, then the $60 Certificate of Business Occupancy via the Business License portal before the tenant can operate. A new tenant occupying an existing space with NO construction work skips this permit entirely and only needs the business-license/Certificate-of-Business-Occupancy flow — see the certificate-of-business-occupancy-permit entry.
  • If the TI changes the space's occupancy classification (e.g. mercantile to assembly), the permit also carries a Section 113.1 Certificate of Occupancy and can trigger accessibility upgrades under Section 107.10.2 — flag this early with plan reviewers.
  • For roof-mounted mechanical equipment added during a TI, the checklist requires elevation drawings showing screening and confirming the unit does not exceed the parapet height.

Frequently asked questions

Boulder City requires a commercial tenant improvement (commercial – remodel permit) for: Appropriate zoning must already be in place for the proposed use, and a permanent address including suite numbers (if applicable) must be assigned, before the application can be accepted (Commercial – Remodel checklist, Part 2 Prerequisites — note the drainage-study and traffic-study prerequisites of the new-construction track do not appear on the remodel checklist); All documents must be digitally stamped/signed and emailed to buildingpermits@bcnv.org (20MB per email limit; subject-line keywords such as 'Initial Submittal – [address]' speed processing) (checklist Part 4); A non-refundable plan review deposit equal to the full plan review fee must be paid before staff review any plans/documents; a blank or incomplete checklist makes the submittal incomplete and it will not be reviewed (checklist Part 1; Administrative Code Section 110.2(E)); Plans must indicate all tenant space within the building and identify adjacent occupancies and uses on the site plan, plus occupancy separations, fire assemblies and exiting on the floor plan (checklist Part 5); Work must comply with the City's adopted codes as listed on the checklist (2018 IBC/UMC/UPC/IECC/IFC editions and 2017 NEC, with Southern Nevada Building Code Amendments) and Title 11 zoning; the 2018 International Existing Building Code governs work on existing buildings per Administrative Code Section 101.5.2; If the tenant improvement changes the space's building-code occupancy classification, a Certificate of Occupancy under Section 113.1 is required through this permit, and the change of occupancy can trigger accessibility-upgrade obligations under Section 107.10.2; Properties in the Boulder City Historic District may require Historic Preservation Committee review, which can delay the permit (checklist Part 6). If your project isn't listed, confirm with City of Boulder City Community Development Department, Building and Safety Division at (702) 293-9282 before starting work.

In Boulder City, the published Building Permit Fee (valuation-based, Table A) is: $27.00 minimum at $1–$500 valuation; e.g. $45.00 + $9.00/$1,000 in the common $2,001–$25,000 TI range; $639.50 + $3.50/$1,000 above $100,000. Additional published fees: Plan Review Fee — 65% of the building permit fee; Permit Issuance Fee — $40.00; Electrical / Plumbing / Mechanical Permit Fees (when associated with the building permit) — Electrical 18.00%, plumbing 16.50%, mechanical 15.00% of the building permit fee; Certificate of Business Occupancy (for the incoming business, separate process) — $60.00 each certificate. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Boulder City's published plan-review target for a commercial tenant improvement (commercial – remodel permit) is 7–14 business days.

You'll need: Completed Building Permit Application; Plan Set. Depending on your project, Boulder City may also ask for: Energy Compliance Report; Completed Electrical Load Calculation Worksheet; Kitchen Plan Details; Fire Sprinkler and Alarm Plans. See the required-documents checklist on this page for details on each.

Boulder City requires 3 inspection(s) for a commercial tenant improvement (commercial – remodel permit), in order: Inspections per the permit's Inspection Record, Final Inspection, Certificate of Business Occupancy inspections (separate, post-construction). Schedule each through City of Boulder City Community Development Department, Building and Safety Division ((702) 293-9282).

Apply through City of Boulder City Community Development Department, Building and Safety Division at 401 California Avenue, Boulder City, NV 89005. Phone: (702) 293-9282, email: buildingpermits@bcnv.org. Office hours: Monday through Thursday, 7:00 a.m. to 6:00 p.m. (excluding holidays); applications submitted after office hours are processed the next available work day. Inspection scheduling hotline: (702) 293-9327 or buildinginspections@bcnv.org; inspection requests must be received by 3:30 p.m. for next-business-day scheduling (no Friday/weekend/holiday inspections).. Official information: https://www.bcnv.org/163/Building-Permits.

Functionally yes, nominally no. The City processes TI work under its 'Commercial – Remodel' building permit, but that track is distinct from new construction: its own published checklist (which uses the term 'tenant improvement'), a shorter published first-review timeframe of 1–2 weeks, and no drainage/traffic-study prerequisites. Fees follow the same valuation-based Table A schedule as every other building permit — there is no separate TI fee line. Source: Commercial – Remodel Permit Submittal Checklist; 2026 Administrative Code Section 110.2 and Table A.

No. A building permit (this entry) is needed only when construction work is performed. A tenant simply moving into an existing space with no alterations goes through the Business License process, which triggers Building and Fire inspections and a $60 Certificate of Business Occupancy — no building permit involved. Source: 2026 Administrative Code Sections 112.7 and 113.2; Boulder City Business Licensing page.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Boulder City.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.