Covers temporary accessory structures (e.g., sheds) up to 200 sq ft and 12 feet in height, placed within side and rear yard setbacks, potentially over public utility easements. Governed by West Wendover City Code 8-5A-6(C). Not available for front or exterior side yard setbacks; structures must not include permanent surface treatments.

Verified 2026-07-03 · Source

When you need this permit

  • Structure limited to R-3 occupancy only, maximum 12 feet height, maximum 200 square feet, single story
  • Not permitted within front or exterior side yard setbacks
  • No permanent surface treatments (concrete pads, asphalt paving, affixed decking) allowed under this permit
  • May require review of current or future use of public utility/access easements associated with the property; the City may or may not allow placement over an active/inactive easement
  • Site plan (scale no less than 1/8" = 1'), structure design/specifications (installation/erection instructions or cut sheets for prefabricated structures, or detailed construction drawings if built on-site), and engineered drawings/calculations for anchoring or spot footings (stamped by a Nevada licensed Structural Engineer) required
  • Permit may be revoked at any time by the City for non-compliance or to protect public utility access/operation
  • All permit fees due and payable at time of Provisional Building Permit issuance

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Structure size 100 sq ft or lessCity of West Wendover Provisional Building Permit Application, July 21, 2020
$160.46
Structure size 101 to 150 sq ftCity of West Wendover Provisional Building Permit Application, July 21, 2020
$206.66
Structure size 151 to 200 sq ftCity of West Wendover Provisional Building Permit Application, July 21, 2020
$252.06

Review timeline

Plan review
Not published — contact the department

How long did your Provisional Building Permit (Temporary/Accessory Structures) permit actually take in West Wendover?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building Official Inspection

    The Building Official or representative inspects all work prior to concealment; 24-hour advance notice required

See the full West Wendover inspection guide — scheduling & re-inspection fees →

Tips

  • This permit is explicitly for TEMPORARY structures only — no permanent surface treatments (concrete pads, asphalt, affixed decking) are allowed.
  • The City may revoke a Provisional Building Permit at any time for non-compliance or to protect public utility easement access — this is a real risk for structures placed over an easement.
  • Requires sign-off from both the Director of Community Development and the Director of Public Works on the application form itself.

Frequently asked questions

West Wendover requires a provisional building permit (temporary/accessory structures) for: Structure limited to R-3 occupancy only, maximum 12 feet height, maximum 200 square feet, single story; Not permitted within front or exterior side yard setbacks; No permanent surface treatments (concrete pads, asphalt paving, affixed decking) allowed under this permit; May require review of current or future use of public utility/access easements associated with the property; the City may or may not allow placement over an active/inactive easement; Site plan (scale no less than 1/8" = 1'), structure design/specifications (installation/erection instructions or cut sheets for prefabricated structures, or detailed construction drawings if built on-site), and engineered drawings/calculations for anchoring or spot footings (stamped by a Nevada licensed Structural Engineer) required; Permit may be revoked at any time by the City for non-compliance or to protect public utility access/operation; All permit fees due and payable at time of Provisional Building Permit issuance. If your project isn't listed, confirm with City of West Wendover Community Development Department at (775) 664-3081 before starting work.

In West Wendover, the published Structure size 100 sq ft or less is: $160.46. Additional published fees: Structure size 101 to 150 sq ft — $206.66; Structure size 151 to 200 sq ft — $252.06. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

West Wendover does not publish a plan-review timeline for this permit. Contact City of West Wendover Community Development Department at (775) 664-3081 for current turnaround.

You'll need: Provisional Building Permit Application; Site Plan Drawing; Structure Design and Specifications. Depending on your project, West Wendover may also ask for: Engineered Anchoring/Footing Calculations. See the required-documents checklist on this page for details on each.

West Wendover requires 1 inspection(s) for a provisional building permit (temporary/accessory structures), in order: Building Official Inspection. Schedule each through City of West Wendover Community Development Department ((775) 664-3081).

Apply through City of West Wendover Community Development Department at 1111 N. Gene L. Jones Way, P.O. Box 2825, West Wendover, NV 89883. Phone: (775) 664-3081. Office hours: West Wendover City Hall, 1111 N. Gene L. Jones Way, West Wendover, Nevada 89883. Building permit applications are submitted in person to the Community Development (Planning Desk) at City Hall; completed documentation must be provided in person with original signatures prior to or at the time of payment. Main Community Development phone: (775) 664-3081; Fax: (775) 664-3720. Building Official (Fire Chief) inspections contact: Jeff Knudtson, 935 Wendover Boulevard (Fire Station), (775) 664-2274. No public email address for the Community Development Department is published on the department page (contact links route through a webform); confirm current staff email directly with the department.. Official information: https://www.westwendovercity.com/government/city-departments/community-development.

West Wendover, Nevada has adopted: West Wendover is its own city building-code authority (not governed by Elko County) under West Wendover City Code Title 7, Chapter 1, which provides that building codes are updated/amended from time to time and each amendment must be formally approved by City Council resolution per Section 7-1-2(A). Source: City of West Wendover Resolution No. 2020-17 (adopting Exhibit 1 building codes) and Building Permit Application (July 2020).; 2018 International Building Code (IBC), together with Appendix Chapters C, E, I, and J. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1 (adopted September 1, 2020).; 2018 International Residential Code (IRC), together with Appendix Chapters A, B, C, G, H, J, K, and M. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Fire Code (IFC), together with all appendices. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Existing Building Code (IEBC). Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Energy Conservation Code (IECC), Commercial and Residential Provisions chapters 1 through 5. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 Uniform Plumbing Code (UPC), together with Appendix Chapters A, B, C, D, E, G, I, J, K and L. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 Uniform Mechanical Code (UMC), together with Appendix Chapters A, B and C, applicable only when the International Mechanical Code (IMC) is silent. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Mechanical Code (IMC), together with Appendix Chapters A and B. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Fuel Gas Code (IFGC), together with Appendix Chapters A, B, C and D. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Swimming Pool and Spa Code (ISPSC), chapters 2 through 11. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 International Wildland-Urban Interface Code, chapter 5. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2018 Northern Nevada Amendments by the Northern Nevada Chapter of the International Code Council, together with Appendix A (copies available at www.nnicc.org). Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; 2017 National Electrical Code (NEC). Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.; National Fire Protection Association (NFPA) standards, editions as adopted by the State of Nevada. Source: City of West Wendover Resolution No. 2020-17, Exhibit 1.. Local amendments apply — see the West Wendover overview page for the full list.

It is a permit for small temporary accessory structures (max 200 sq ft, max 12 ft tall, R-3 occupancy only) placed within side/rear yard setbacks, potentially over public utility easements. Fees range from $160.46 (100 sq ft or less) to $252.06 (151-200 sq ft). Source: City of West Wendover Provisional Building Permit Application, July 21, 2020.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Wendover building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.