Inspection sequence, scheduling, and re-inspection fees for building permits in Roswell, New Mexico.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
400 W. 2nd St., Roswell, NM 88201 (mailing: PO Box 1838, Roswell, NM 88202-1838)
Phone
(575) 637-6280
Office hours

Published scheduling rules

  • You must call the building inspector directly at (575) 637-6293 to schedule the required final inspection. (Re-Roofing Permit)
  • CID's general inspection scheduling line is (505) 222-9813 or 1-877-243-0979, or email cid.inspection@rld.nm.gov; the CID permit help hotline is (505) 222-9837 or cid.permithelp@rld.nm.gov. (Electrical Permit (State-Administered))
  • A foundation, structural, and final inspection by the Building Inspector is required before any sign requiring a Building Permit can be issued a Certificate of Occupancy (C-of-O); scheduling inspections is the responsibility of the contractor or sign owner (Article 60, Section 4.H) (Sign Permit)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Foundation / Density-Compaction

    Density/compaction tests required prior to pouring foundation per 14.5.2.10(A)(1)(f) NMAC

  2. 2

    Roof Decking (for re-roofs)

    Required at minimum upon removal of existing roof, per 14.5.2.8(E)(3) NMAC

  3. 3

    Final

    Final inspection of the roof system or roof coating application upon completion of a roofing project; general final inspection for all other building permits before Certificate of Occupancy

Applies to: Sign Permit

  1. 1

    Foundation

    Required for any sign requiring a Building Permit, per Article 60 Section 4.H

  2. 2

    Structural

    Required for any sign requiring a Building Permit, per Article 60 Section 4.H

  3. 3

    Final

    Required before a Certificate of Occupancy (C-of-O) can be issued for the sign; scheduling is the responsibility of the contractor or sign owner, per Article 60 Section 4.H

Applies to: Change of Occupancy / Certificate of Occupancy Permit

  1. 1

    Final Inspection

    Required by the Building Division before a Certificate of Occupancy is issued

  2. 2

    Fire Marshal Review (commercial changes of occupancy)

    The Fire Prevention Division's Fire Marshal reviews new business/construction plans for fire code compliance, which extends to occupancy-classification changes with different fire-protection thresholds

Applies to: Fire Sprinkler / Fire Alarm System Permit

  1. 1

    Fire Code / New Construction Plan Review

    The Fire Marshal reviews new business construction plans for fire code compliance and coordinates with the Planning and Zoning Department; the specific rough-in/final inspection sequence for sprinkler and alarm installations is not separately published

  2. 2

    Annual Fire Inspection

    The Fire Prevention Division's inspector conducts annual inspections on every business in Roswell to verify continued fire code and life-safety compliance, including sprinkler and alarm systems

Applies to: Re-Roofing Permit

  1. 1

    Decking Inspection

    Required at minimum upon removal of the existing roof, per 14.5.2.8(E)(3) NMAC

  2. 2

    Final

    Required for the roof system or roof coating system application upon completion; call the building inspector directly at (575) 637-6293 to schedule

Applies to: Solar PV Permit (City Building Permit + State CID Electrical)

  1. 1

    Structural / Roof-Mount (City)

    Verifies racking/mounting attachment and roof penetrations against approved plans

  2. 2

    Electrical Rough-In / Final (NM CID)

    Scheduled directly with CID, not the City — CID's general inspection scheduling line is (505) 222-9813 or 1-877-243-0979, or cid.inspection@rld.nm.gov

Roswell building permits

Get alerts for Roswell

We'll email you when Roswell's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.