Re-Roofing Permit in Roswell, New Mexico

Required for all new roof installations, re-roofs, and applications of roof coating systems on residential and commercial buildings in Roswell, per 14.5.2.8(E) NMAC. Excludes manufactured/mobile homes, which are permitted through the state office. Reviewed by the City of Roswell Building & Inspections Division.

Verified 2026-07-02 · Source

When you need this permit

  • All new roof installations and re-roofs require a building permit and inspections
  • All applications of roof coating systems require a building permit and inspections
  • Does not include manufactured/mobile homes — permits for those are available through the state office
  • Must describe existing roof type and re-roofing installation in detail on the application
  • Installation detail submitted must not be deviated from without approval from the building inspector
  • Permit must be posted on the job site

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Re-Roofing Permit FeeRe-Roofing Permit Application (DocumentCenter/View/5821) and City of Roswell Building Fee Schedule (DocumentCenter/View/26127)
Valuation-based per the City of Roswell Building Fee Schedule (applicant enters Re-roofing Contract Cost on the application; the application does not print a flat re-roof-specific fee, and cross-checking the fee schedule confirms Roswell uses the same valuation-tiered Building Permit Fee table for re-roofs as for other building permits)

Review timeline

Plan reviewTypical estimate — confirm current times with the Roswell building department
~1–3 business days

How long did your Re-Roofing Permit permit actually take in Roswell?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Decking Inspection

    Required at minimum upon removal of the existing roof, per 14.5.2.8(E)(3) NMAC

  2. 2

    Final

    Required for the roof system or roof coating system application upon completion; call the building inspector directly at (575) 637-6293 to schedule

See the full Roswell inspection guide — scheduling & re-inspection fees →

Tips

  • Roof coatings require a permit in Roswell just like full re-roofs — do not assume a coating-only job is exempt.
  • Manufactured/mobile home re-roofs are NOT covered by this city permit — apply through the state (NM CID) instead.
  • You must call the building inspector directly at (575) 637-6293 to schedule the required final inspection.

Frequently asked questions

Yes. Per 14.5.2.8(E) NMAC, all new roof installations, re-roofs, and roof coating applications require a building permit and inspections in Roswell, except for manufactured/mobile homes, which are permitted through the state office.

In Roswell, the published Re-Roofing Permit Fee is: Valuation-based per the City of Roswell Building Fee Schedule (applicant enters Re-roofing Contract Cost on the application; the application does not print a flat re-roof-specific fee, and cross-checking the fee schedule confirms Roswell uses the same valuation-tiered Building Permit Fee table for re-roofs as for other building permits). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a re-roofing permit in Roswell typically runs 1–3 business days. This is an estimate, not a published figure — confirm current review times with City of Roswell Community Development — Building & Inspections Division at (575) 637-6280.

You'll need: Re-Roofing Permit Application. See the required-documents checklist on this page for details on each.

Roswell requires 2 inspection(s) for a re-roofing permit, in order: Decking Inspection, Final. Schedule each through City of Roswell Community Development — Building & Inspections Division ((575) 637-6280).

Apply through City of Roswell Community Development — Building & Inspections Division at 400 W. 2nd St., Roswell, NM 88201 (mailing: PO Box 1838, Roswell, NM 88202-1838). Phone: (575) 637-6280, email: permits@roswell-nm.gov. Official information: https://www.roswell-nm.gov/1279/Building-Inspections.

Roswell, New Mexico has adopted: 2021 International Building Code, adopted as the New Mexico Commercial Building Code (NMCBC); 2021 International Residential Code, adopted as the New Mexico Residential Building Code (NMRBC); 2021 International Existing Building Code, adopted as the New Mexico Existing Building Code (NMEBC); 2021 International Fire Code (IFC); 2020 National Electrical Code, adopted as the New Mexico Electrical Code (NMEC); 2021 International Energy Conservation Code, adopted as the New Mexico Energy Conservation Code (NMECC); 2017 ANSI A117.1 (Accessibility); 2021 Uniform Mechanical Code, adopted as the New Mexico Mechanical Code (NMMC); 2021 Uniform Plumbing Code, adopted as the New Mexico Plumbing Code (NMPC). Local amendments apply — see the Roswell overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Roswell building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.