Skip to main content
PermitBase

Las Cruces building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Las Cruces, New Mexico.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
700 N. Main St., Suite 1100, P.O. Box 20000, Las Cruces, NM 88001
Phone
575-528-3222
Office hours
Monday, Tuesday, Thursday, Friday 7:30 AM - 5:00 PM; Wednesday 8:00 AM - 2:00 PM (afternoon closed for admin/training); online access 24 hours

Published scheduling rules

  • All permit applications in Las Cruces are submitted online through the Citizen Portal (Accela Citizen Access at aca-prod.accela.com/lascruces). The Permitting Counter at 700 N. Main St., Suite 1100 is open to the public 8 a.m. to 5 p.m. Monday-Friday for in-person help, applications, status checks, inspection requests, and payments. (General)

Inspection sequence

Applies to: Commercial Building Permit (New Construction, Addition, Shell)

  1. 1

    Foundation / Footing

    After excavation and reinforcing steel placement, before concrete is placed. Inspections are requested through the Citizen Portal (Accela) after permit issuance — same-day requests are not permitted; inspections may be requested up to 5 working days out. The City publishes its inspection request categories (Building, Electrical, Mechanical, Plumbing, Walls, Fences) but not a formal commercial-sequence checklist, so this sequence reflects standard IBC practice under the City's categories.

  2. 2

    Underground / Slab

    In-slab or under-floor plumbing, electrical conduit, and mechanical work before concrete placement

  3. 3

    Frame / Cover-Up

    Structural framing, fire blocking, and rough electrical, plumbing, and mechanical complete, before concealment (the City's fee schedule lists a Cover-up Fee for work concealed without inspection)

  4. 4

    Trade Finals (Electrical, Plumbing, Mechanical, Fire)

    Final inspections on each sub-contractor trade permit and fire systems acceptance testing, before the general final

  5. 5

    Building Final / Certificate of Occupancy

    All work complete per approved plans; for a Same Day Certificate of Occupancy ($150.00), all inspections must be completed and logged by 12 pm and the CO is issued by 5 pm

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    After excavation for footings is complete and required reinforcing steel is in place, per the state Building Permit Guide for Residential Construction

  2. 2

    Concrete Slab / Under-Floor

    After all in-slab or under-floor equipment, conduit, and piping are in place, before concrete is placed or floor sheathing installed

  3. 3

    Frame

    After roof, framing, fire blocking and bracing are in place and rough electrical, plumbing, and heating are complete

  4. 4

    Weather-Resistive Barrier

    After installation of the weather-resistive barrier, before it is covered

  5. 5

    Final

    After finish grading, building complete and ready for occupancy; final electrical, plumbing, and mechanical inspections must be conducted first

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Frame

    After framing and rough MEP complete

  3. 3

    Final

    All work complete per approved plans

Applies to: Commercial Tenant Improvement / Alteration Permit

  1. 1

    Rough / Cover-Up (Frame and Trade Rough-Ins)

    Framing and rough electrical, plumbing, and mechanical in the work area before concealment — the City's fee schedule lists a Cover-up Fee for work concealed without inspection. Inspections are requested through the Citizen Portal after permit issuance (no same-day requests; up to 5 working days out). The City publishes inspection request categories (Building, Electrical, Mechanical, Plumbing) rather than a formal TI-sequence checklist, so this sequence reflects standard practice under those categories.

  2. 2

    Trade Finals (Electrical, Plumbing, Mechanical, Fire)

    Final inspections on each associated trade sub-permit, plus fire sprinkler/alarm acceptance testing where systems were modified

  3. 3

    Building Final / Certificate of Occupancy

    All work complete per approved plans; Same Day Certificate of Occupancy available for $150.00 if all inspections are completed and logged by 12 pm (CO issued by 5 pm)

Applies to: Fire Sprinkler & Fire Alarm Systems Permit

  1. 1

    Sprinkler / Alarm Rough-In

    Piping, hangers, and wiring/devices installed and visible for inspection before concealment; system layout verified against the approved hydraulic calculation and plans

  2. 2

    Fire Pump Test

    Required only when a fire pump is part of the system (diesel or electric); pump performance verified against design specifications

  3. 3

    Final Acceptance Test

    Full system flow test (sprinkler) and functional test (alarm devices, panel, notification appliances), witnessed by Fire Prevention prior to occupancy

Applies to: Residential Addition / Alteration / Remodel Permit

  1. 1

    Frame

    After framing, fire blocking and bracing in place and rough MEP complete

  2. 2

    Weather-Resistive Barrier

    After installation of weather-resistive barrier, before covered (exterior work)

  3. 3

    Final

    All work complete per approved plans; final electrical, plumbing, mechanical inspections conducted first

Applies to: Residential Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    Final plumbing inspection must be conducted prior to final general construction inspection

Applies to: Change of Occupancy Permit (Change of Use / Certificate of Occupancy)

  1. 1

    Change-of-Occupancy Compliance Inspection

    Applies only to the 'with inspection' fee tier; verifies the new use complies with applicable building and fire/life-safety code requirements

  2. 2

    Final Inspection (multi-trade)

    Required before Certificate of Occupancy issuance; for Same Day CO, all applicable trade inspections must be completed and logged by 12 pm

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed, where applicable

  2. 2

    Final

    EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; final electrical inspection must be conducted prior to final general construction inspection if bundled with a larger project

Applies to: Residential Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed

  2. 2

    Final

    Final electrical inspection must be conducted prior to final general construction inspection

Applies to: Residential Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and equipment installed before walls closed

  2. 2

    Final

    Final mechanical inspection must be conducted prior to final general construction inspection

Applies to: Sign Permit

  1. 1

    Footing / Foundation

    Required only for pole and monument (freestanding) signs; verifies footing depth and reinforcement before concrete is placed

  2. 2

    Final

    Verifies the completed sign matches the approved permit plans; a separate electrical final inspection is required for illuminated signs

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Building / Structural

    Panel mounting and racking attachment verified

  2. 2

    Electrical

    Electrical connections and interconnection point verified

Final inspection only: Roofing Permit (Reroof)

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Cruces building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Las Cruces building permits

Get alerts for Las Cruces

We'll email you when Las Cruces's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.