Las Cruces building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Las Cruces, New Mexico.
Verified 2026-07-02 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 700 N. Main St., Suite 1100, P.O. Box 20000, Las Cruces, NM 88001
- Phone
- 575-528-3222
- Office hours
- Monday, Tuesday, Thursday, Friday 7:30 AM - 5:00 PM; Wednesday 8:00 AM - 2:00 PM (afternoon closed for admin/training); online access 24 hours
- Website
- Official site
Published scheduling rules
- All permit applications in Las Cruces are submitted online through the Citizen Portal (Accela Citizen Access at aca-prod.accela.com/lascruces). The Permitting Counter at 700 N. Main St., Suite 1100 is open to the public 8 a.m. to 5 p.m. Monday-Friday for in-person help, applications, status checks, inspection requests, and payments. (General)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
After excavation for footings is complete and required reinforcing steel is in place, per the state Building Permit Guide for Residential Construction
- 2
Concrete Slab / Under-Floor
After all in-slab or under-floor equipment, conduit, and piping are in place, before concrete is placed or floor sheathing installed
- 3
Frame
After roof, framing, fire blocking and bracing are in place and rough electrical, plumbing, and heating are complete
- 4
Weather-Resistive Barrier
After installation of the weather-resistive barrier, before it is covered
- 5
Final
After finish grading, building complete and ready for occupancy; final electrical, plumbing, and mechanical inspections must be conducted first
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Before concrete pour
- 2
Frame
After framing and rough MEP complete
- 3
Final
All work complete per approved plans
Applies to: Fire Sprinkler & Fire Alarm Systems Permit
- 1
Sprinkler / Alarm Rough-In
Piping, hangers, and wiring/devices installed and visible for inspection before concealment; system layout verified against the approved hydraulic calculation and plans
- 2
Fire Pump Test
Required only when a fire pump is part of the system (diesel or electric); pump performance verified against design specifications
- 3
Final Acceptance Test
Full system flow test (sprinkler) and functional test (alarm devices, panel, notification appliances), witnessed by Fire Prevention prior to occupancy
Applies to: Residential Addition / Alteration / Remodel Permit
- 1
Frame
After framing, fire blocking and bracing in place and rough MEP complete
- 2
Weather-Resistive Barrier
After installation of weather-resistive barrier, before covered (exterior work)
- 3
Final
All work complete per approved plans; final electrical, plumbing, mechanical inspections conducted first
Applies to: Residential Plumbing Permit
- 1
Underground / Slab
Before concrete pour — pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
Final plumbing inspection must be conducted prior to final general construction inspection
Applies to: Change of Occupancy Permit (Change of Use / Certificate of Occupancy)
- 1
Change-of-Occupancy Compliance Inspection
Applies only to the 'with inspection' fee tier; verifies the new use complies with applicable building and fire/life-safety code requirements
- 2
Final Inspection (multi-trade)
Required before Certificate of Occupancy issuance; for Same Day CO, all applicable trade inspections must be completed and logged by 12 pm
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
Wiring and conduit installed before walls closed, where applicable
- 2
Final
EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; final electrical inspection must be conducted prior to final general construction inspection if bundled with a larger project
Applies to: Residential Electrical Permit
- 1
Rough-In
Wiring and conduit installed before walls closed
- 2
Final
Final electrical inspection must be conducted prior to final general construction inspection
Applies to: Residential Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and equipment installed before walls closed
- 2
Final
Final mechanical inspection must be conducted prior to final general construction inspection
Applies to: Sign Permit
- 1
Footing / Foundation
Required only for pole and monument (freestanding) signs; verifies footing depth and reinforcement before concrete is placed
- 2
Final
Verifies the completed sign matches the approved permit plans; a separate electrical final inspection is required for illuminated signs
Applies to: Solar Photovoltaic (PV) Permit
- 1
Building / Structural
Panel mounting and racking attachment verified
- 2
Electrical
Electrical connections and interconnection point verified
Final inspection only: Roofing Permit (Reroof)
Sources & verification
Verified against official sources. Last reviewed 2026-07-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Cruces building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Las Cruces building permits
Get alerts for Las Cruces
We'll email you when Las Cruces's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.