Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Doña Ana County, New Mexico.

Verified 2026-07-05 · Source

How to schedule

Inspections are requested through the building department below.

Address
845 N. Motel Blvd., Room 150, Las Cruces, NM 88007
Phone
(575) 647-7350; Fax (575) 525-6131; TDD (575) 525-5951
Office hours
County administrative offices open at 8:00 AM (confirmed via the county's own delayed-opening notice stating a 2-hour delay resumes 'normal operations' at 10 a.m., i.e. normal opening is 8:00 AM); the Building Services Division's own site does not publish a distinct closing time or Building-Services-specific hours separate from general county office hours, and no further closing-time citation could be independently confirmed after checking the department's own pages, the county homepage, and the general department directory.

Inspection sequence

Applies to: Single Family Dwelling Permit

  1. 1

    Plumbing Rough-In / Foundation

    1st phase: all drain and water lines installed before the slab is placed; foundation inspection complete with compaction and footings verified

  2. 2

    Plumbing Top Out / HVAC Rough-In / Electrical Rough-In / Sheathing

    2nd phase: all vents extended through roof with water/gas piping installed (plumbing); ductwork with insulation, gas vents through roof, gas piping and dryer vent (HVAC); panel and all wire boxes for receptacles/switches/cable/phone/lighting (electrical); sheathing inspection once exterior sheathing is installed. All 2nd-phase inspections must be approved before scheduling Frame and Lath.

  3. 3

    Frame / Lath

    Framing and lath inspections, performed after all 1st- and 2nd-phase inspections are approved

  4. 4

    Insulation

    3rd phase: insulation inspection, or an insulation certificate from a licensed installer may be submitted instead

  5. 5

    Plumbing Final / HVAC Final / Electrical Final

    4th phase: all fixtures/water heater/gas piping tested and drains working (plumbing); all heating/cooling equipment installed with registers in place (HVAC); meter installed with all receptacles/switches/lighting working (electrical). All 4th-phase inspections must be approved before scheduling the Building Final.

  6. 6

    Building Final Inspection

    Final structural/building inspection, scheduled only after all trade finals are approved

Applies to: Plumbing / Mechanical Permit

  1. 1

    Plumbing Rough-In / Top Out

    1st phase: all drain and water lines installed before slab placement; 2nd phase: all vents extended through roof, water and gas piping installed

  2. 2

    HVAC Rough-In

    All ductwork with insulation, gas vents through roof, gas piping, and dryer vent — 2nd phase

  3. 3

    Plumbing Final / HVAC Final

    All fixtures, water heater, gas piping system tested and drains in working condition (plumbing); all heating and cooling equipment installed with registers in place (HVAC). Inspection phone: (575) 647-7350.

Applies to: Certificate of Occupancy (Change of Use/Occupancy)

  1. 1

    Building Final Inspection (new construction)

    For new construction, the CO is issued upon the Building Final Inspection already documented as the final step of this file's residential-building-permit entry (order 6) — no separate CO-specific inspection exists in that scenario.

  2. 2

    As-Built / Occupancy Classification Verification (change of use on existing building)

    For a change of use on an existing building with no new construction, no distinct published inspection checklist was found; a site visit by the Building Official to confirm the building meets the applicable code requirements for the new occupancy classification is standard IBC § 111 practice, but Doña Ana County does not itemize this on any published document — confirm the process with Building Services, (575) 647-7350.

Applies to: Electrical Permit

  1. 1

    Electrical Rough-In

    Panel, all wire boxes for receptacles, switches, cable, phone, and lighting — part of the 2nd-phase inspections on new construction

  2. 2

    Electrical Final

    Meter installed with all receptacles, switches, and lighting in working condition. Inspection phone: (575) 647-7350.

Applies to: EV Charger / EVSE Permit

  1. 1

    Electrical Rough-In

    Wiring/conduit for the EV charger circuit installed before wall cover, if applicable

  2. 2

    Electrical Final

    EVSE equipment connected and operational, breaker sizing and grounding verified. Inspection phone: (575) 647-7350.

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Fire Prevention Plan Review

    Construction documents for automatic fire-extinguishing and fire alarm systems are reviewed by the County Fire Code Official (Fire Prevention Division) prior to permit issuance, per the adopted IFC's administrative provisions and DAC Code § 195-3(A)(8).

  2. 2

    Final Fire Inspection

    A final inspection by the Fire Prevention Division confirming the installed system matches the approved plans is required before the system may be placed in service, consistent with the adopted IFC's general permit/inspection framework. Doña Ana County does not publish a distinct itemized inspection checklist for fire-sprinkler/alarm permits specifically (unlike the phased building/electrical/plumbing inspection checklists documented elsewhere in this file) — confirm the specific inspection sequence with the Fire Prevention Division, (575) 647-7925.

Applies to: Reroof & Reroof/Overlay Permit

  1. 1

    Sheathing (if re-sheathing performed)

    Required only where the roof deck is re-sheathed as part of the reroof scope

  2. 2

    Final

    Final roofing inspection after installation is complete. Inspection phone: (575) 647-7350.

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Racking, roof-penetration, and electrical interconnection compliance verified by the County

Final inspection only: Sign Permit

Unincorporated Doña Ana County building permits

Get alerts for Unincorporated Doña Ana County

We'll email you when Unincorporated Doña Ana County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.