Solar Photovoltaic (PV) Permit in Unincorporated Doña Ana County, New Mexico
Required for installation of rooftop or ground-mount solar photovoltaic systems in unincorporated Doña Ana County. Unlike many jurisdictions in this database, Doña Ana County issues its OWN electrical permits directly — it is not routed to the New Mexico Construction Industries Division (CID) — and publishes a distinct flat electrical fee specifically for 'Photovoltaic (Solar PV)' work. The structural/mounting portion is billed as a building permit under the County Code's general 'Other construction' valuation scale (Chapter 179, Article VI), since solar is not separately addressed in that fee article.
Verified 2026-07-20 · Source
When you need this permit
- Building permit required for the structural/mounting portion, valued under Doña Ana County Code § 179-16C's general valuation scale for 'construction not otherwise specifically addressed' in the fee article
- Separate Electrical Permit required for the interconnection work, obtained AFTER the building permit is issued, by a New Mexico-licensed electrical contractor — issued directly by Doña Ana County itself, not the State CID
- 25% of assessed permit fees due at building-permit application submittal when construction drawing/site plan review is required; remaining 75% collected prior to permit issuance, per County Code § 179-16D
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Racking, roof-penetration, and electrical interconnection compliance verified by the County
See the full Unincorporated Doña Ana County inspection guide — scheduling & re-inspection fees →
Tips
- Doña Ana County is unusual in this database: it issues its OWN electrical permits (not routed to the State CID) and publishes a distinct flat $45.00 'Photovoltaic (Solar PV)' fee on its own Electrical Permit Form/Fee Schedule — cheaper and simpler to look up than the valuation-based tables used by most neighboring counties for the electrical side.
- The electrical permit must be applied for AFTER the building permit is issued, per the County's own process — don't submit both simultaneously expecting parallel processing.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Doña Ana County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Doña Ana County
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Unincorporated Doña Ana County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Doña Ana County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →