Demolition Permit in Deming, New Mexico
VerifiedRequired for demolition of structures in Deming. The Multi Purpose State Building Application includes a 'Demolition' scope-of-work checkbox, and the general building permit required under Deming Municipal Code 11-1-3.A applies to 'any construction or alteration project,' which the City's own fee ordinance and CID's scope-of-work checkbox both treat as covering demolition.
Verified 2026-07-03 · Source
When you need this permit
- Complete the Multi Purpose State Building Application, checking the 'Demolition' scope-of-work box
- Pay the City of Deming's general permit fee under Municipal Code 11-1-3.A (minimum $10.00, scaling with valuation) in addition to any CID fee
- Coordinate utility disconnection and any asbestos-related requirements directly with utility providers and the applicable state environmental authority before demolition
Required documents
- Required
Multi Purpose State Building Application
Submitted to CID with the 'Demolition' scope-of-work box checked
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| City of Deming — General Permit Fee (valuation-based) | $10.00 minimum up to $5,000 valuation, plus $2.00 per additional $1,000 (or portion) above $5,000 | Deming Municipal Code 11-1-3.A — general permits are required for 'any construction or alteration project,' the same fee schedule cited for demolition scope on the state form |
| State CID Building Permit Fee (valuation-based) | Calculated by CID based on project valuation/scope; contact CID Las Cruces (575-524-6320) for the fee before mailing an application | NM RLD Construction Industries Forms and Applications: Fees page |
Review timeline
3–3 business days
Deming’s published plan-review target
Inspection process
- 1
Final Inspection
Site verified clear of remaining structure/foundation elements per the approved permit scope
Tips
- Deming's own Municipal Code does not carry a separate demolition-specific ordinance (unlike some larger New Mexico cities) — demolition is handled as a scope of work on the same statewide CID Multi Purpose State Building Application, subject to the same City general permit fee as any other construction/alteration project.
Frequently asked questions
- Do I need a permit to demolish a building in Deming?
- Yes. Use the Multi Purpose State Building Application with the 'Demolition' scope-of-work box checked, submitted to CID's Las Cruces office, plus the City of Deming's general permit fee under Municipal Code 11-1-3.A.
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
- New Mexico Construction Industries Division (CID), Las Cruces Office — building, electrical, mechanical, and plumbing permit issuance, plan review, and inspections for the City of Deming; City of Deming Planning and Zoning Department / City Engineer (Floodplain Administrator) — local general-permit fee collection, zoning compliance, and floodplain development permit prerequisite — official building department
- General Building Application 2022 (State CID form hosted by City of Deming) (PDF)
- 11-1-3: Building Permit Fees | Deming, NM Code of Ordinances (amlegal.com)
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Deming building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Deming
Demolition Permit in other cities
Compare demolition permit fees across New Mexico →
Project checklist — coming soon
Describe your project once and get every permit, document, and fee it triggers in Deming — in one checklist. Leave your email and we'll tell you when it's ready.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.