How to schedule
Inspections are requested through the building department below.
- Address
- CID Las Cruces Office: 505 S. Main St., Ste. 103, Las Cruces, NM 88001 (also published as 'Ste. 103, Loretto Town Center'). City of Deming Planning and Zoning: 1275 E. Pine St., Deming, NM 88030
- Phone
- CID Las Cruces: (575) 524-6320; City of Deming Planning and Zoning: (575) 546-8848
- Office hours
- City of Deming Planning and Zoning: Monday-Thursday 8:00 AM-4:45 PM; Friday 8:00 AM-11:45 AM
- Website
- Official site
Published scheduling rules
- Skipping an inspection due to your own action costs $150 the first time and $400 for each missed inspection after that, per Deming Municipal Code 11-1-3.F — schedule inspections carefully. (Residential Building Permit (New Construction))
- For CID inspection requests generally, contact the CID Las Cruces office at (575) 524-6320; for general CID permit questions, email CID.PERMITHELP@state.nm.us. (General)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation Inspection
Made after excavation for footings is complete and required reinforcing steel is in place, before concrete placement
- 2
Concrete Slab / Under-Floor Inspection
Made after all in-slab or under-floor building service equipment, conduit, and piping are in place, but before concrete is placed or floor sheathing installed
- 3
Frame Inspection
Made after roof, framing, fire blocking, and bracing are in place and rough electrical, plumbing, and heating are complete and approved
- 4
Final Inspection
Made after finish grading and building completion; final electrical, plumbing, and mechanical inspections must be conducted first. CID issues the Certificate of Occupancy after approving the final inspection
Applies to: Plumbing Permit
- 1
Underground / Slab Plumbing
Before concrete pour — verify pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
All fixtures connected, no leaks, proper venting verified
Applies to: Change of Occupancy / Certificate of Occupancy Permit
- 1
Occupancy Compliance Inspection
Verifies the space meets the applicable egress, fire-safety, structural, and accessibility requirements for the new occupancy classification under IEBC Chapter 10 / Table 1011.5
- 2
Final Inspection / Certificate of Occupancy Issuance
CID issues the new Certificate of Occupancy once all required inspections are approved, per N.M. Admin. Code 14.5.3.13
Applies to: Electrical Permit
- 1
Rough-In Inspection
Wiring and conduit installed before walls closed
- 2
Final Inspection
All devices installed, panel labeled, system energized
Applies to: EV Charger / EVSE Permit (Electrical Permit)
- 1
Rough-In Inspection
Wiring and conduit installed before walls closed (if applicable)
- 2
Final Inspection
Charger circuit/outlet installed, breaker sized correctly, energized
Applies to: Fire Sprinkler & Fire Alarm System Permit
- 1
Contractor Pre-Test
Installing contractor fully pre-tests the fire protection system(s) in accordance with NFPA standards until all systems pass, before requesting a Final Acceptance Test
- 2
Final Acceptance Test
A State Fire Inspector is dispatched to conduct the Final Acceptance Test at a scheduled date/time; approved/stamped plans, manufacturer specifications, testing documentation, and a representative for each system must be on-site
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Equipment
Ductwork and mechanical equipment rough-in before walls closed
- 2
Final
Equipment operational, combustion air verified, venting correct
Applies to: Residential Addition / Alteration Permit
- 1
Frame Inspection
After framing, fire blocking, and bracing complete; rough electrical, plumbing, and heating approved
- 2
Final Inspection
After completion; final electrical, plumbing, and mechanical inspections conducted first
Applies to: Roofing Permit (Reroof)
- 1
Decking Inspection
Required upon removal of the existing roof, before new roofing material is applied
- 2
Final Inspection
Upon completion of the roofing project or application of the roof coating system
Applies to: Solar Photovoltaic (PV) Permit
- 1
Electrical Rough-In / Structural (if applicable)
Conduit runs, mounting/racking attachment, and structural reinforcement (if required) verified before energizing
- 2
Final Electrical Inspection
All electrical connections, grounding, and interconnection point verified per the approved one-line diagram
Final inspection only: Demolition Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Deming building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Deming building permits
Get alerts for Deming
We'll email you when Deming's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.