This is PermitBase’s published record for North Logan as of 2026-07-07. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

North Logan building permits

Verified

North Logan, Utah — as published 2026-07-07.

Verified 2026-07-08 · Source

Codes adopted

2021 International Building Code (IBC) — North Logan Municipal Code § 9-401 adopts 'the building codes, adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(a), the 2021 IBC is the current statewide-adopted edition (effective through June 30, 2026). North Logan's own Building Codes & Design Criteria page links directly to the State Adopted Codes list rather than publishing a separate local list, and states 'there are no local amendments for North Logan.'2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b), adopted per NLMC § 9-401's blanket adoption of state-adopted building codes; continues in force after July 1, 2026.2021 International Plumbing Code (IPC) — NLMC § 9-600/§ 9-701 adopts 'the Uniform Plumbing Code, currently adopted by State of Utah'; per Utah Code § 15A-2-103(1)(d), the 2021 IPC is the current statewide edition.2021 International Mechanical Code (IMC) — NLMC § 9-705 adopts the mechanical code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(e), the 2021 IMC is the current statewide edition.2021 International Fuel Gas Code (IFGC) — NLMC § 9-702 adopts the fuel gas code 'as adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(f), the 2021 IFGC is the current statewide edition.2021 International Energy Conservation Code (IECC) — NLMC § 9-707 adopts the energy conservation code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(h), the 2021 IECC is the current statewide edition.2023 National Electrical Code (NEC) — NLMC § 9-500/§ 9-501 adopts 'the electrical code, adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(g), the 2023 NEC is the current statewide edition.

Permit types & fees

Residential Building Permit

Verified

Required for new single-family residential construction and any structure over 200 sq ft in North Logan. Must be preceded by a Zoning Clearance (Step 1) before the Building Permit (Step 2) can be requested. Fee is valuation-based under the 1997 Uniform Building Code Table No. 3-A, adjusted annually by CPI, per North Logan Municipal Code § 9-205 and the city's Master Fee Schedule.

Verified 2026-07-08 · Source

Requirements

  • New single-family residential construction, or any structure over 200 sq. ft.
  • Zoning Clearance (Step 1) must be obtained first via the CivicReview portal before a Building Permit application can be submitted — applies to primary structures, accessory structures, agricultural structures, signs, fences, pools, or retaining walls over 3 feet in height
  • Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203
  • Soils Hazard Mitigation Plan required if the site's NRCS soils rating is 'very limited,' per NLMC § 9-206
  • Concrete inspection required for curb, gutter, and sidewalk work, with at least 24-hour advance notice

Required documents

  • RequiredZoning Clearance ApplicationSubmitted online via the CivicReview portal (app.civicreview.com); required before a Building Permit can be requested, per North Logan's official Building Department page.
  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com after Zoning Clearance approval; applicant uploads the zoning clearance approval letter along with applicable building plans, per North Logan's official Building Department page.
  • Required2 Sets of Plans and SpecificationsRequired with the written building permit application per North Logan Municipal Code § 9-203; one set is retained by the Building Inspector.
  • OptionalOwner/Builder Certification FormUtah Department of Commerce, Division of Occupational and Professional Licensing form, required when the owner acts as their own contractor; available as a downloadable PDF on North Logan's Building Department page.

Fee schedule

Fee typeAmountNotes
Building Permit FeeAs established in the 1997 Uniform Building Code (Table No. 3-A), adjusted annually by the CPINorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026), citing North Logan Municipal Code § 9-205: 'The Treasurer shall collect a fee for the Building Permit from the applicant in an amount in accordance with Table No. 3-A of the Uniform Building Code.' A down payment is due at application: Single Family Home $50; permits where the total fee is likely to be less than $100.00, $0 down payment.
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026).
Road Impact Fee (Single Family Detached)$2,432 per housing unitNorth Logan Master Fee Schedule, 'Building Permit Fees' section — Road Impact Fee table, Residential (per housing unit), citing the North Logan Impact Fee Analysis report dated June 25, 2024.
Water Impact Fee (3/4-inch meter, standard residential)$4,841 per meterNorth Logan Master Fee Schedule, 'Building Permit Fees' section — Water Impact Fee table by meter size.
Residential Sewer Impact Fee (Single Family Residential)$6,697 (North Service Area) or $4,039 (South Service Area)North Logan Master Fee Schedule, 'Building Permit Fees' section — Residential Sewer Impact Fee table, varies by service area.
Parks & Trails Impact Fee (Residential)$5,315 per household/housing unitNorth Logan Master Fee Schedule, 'Building Permit Fees' section.
Logan City Imposed Wastewater Treatment Impact Fee (LCIWTIF) — Single Family Unit$2,433.00 per unit (1 ERU multiplier)North Logan Master Fee Schedule, 'Building Permit Fees' section, per Resolution 25-02 (2/19/2025); collected by North Logan and remitted per agreement with Logan City for wastewater treatment capacity.
Water Meter FeeDirect market cost of meter and supplies, plus $60.00 installation feeNorth Logan Master Fee Schedule, 'Building Permit Fees' section; cost verified by the Public Works Department.

Combined Electrical, Mechanical, Plumbing Permit

Verified

Required for standalone electrical, mechanical, or plumbing work in North Logan not part of a new residential building permit. Exempt from the Zoning Clearance requirement and can be applied for directly. Fee is calculated as a percentage of what the corresponding Building Permit Fee would be.

Verified 2026-07-08 · Source

Requirements

  • Electrical, mechanical, or plumbing work performed independently of new construction
  • Exempt from Zoning Clearance (Step 1) — apply directly for the permit
  • Subject to the adopted 2023 NEC (electrical), 2021 IMC (mechanical), and 2021 IPC (plumbing) per North Logan Municipal Code Title 9

Required documents

  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com; no Zoning Clearance approval letter required for these exempt permit types.

Fee schedule

Fee typeAmountNotes
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026). The underlying Building Permit Fee is calculated per the 1997 Uniform Building Code Table No. 3-A valuation table, adjusted annually by CPI, per North Logan Municipal Code § 9-205.

Encroachment Permit

Verified

Required for work within the public right-of-way in North Logan, including street excavation, road cuts, boring, and utility trenching. Fees are structured around inspection and surety/cash bond deposits tied to the type and age of the disturbed surface.

Verified 2026-07-08 · Source

Requirements

  • Required for any work within the public right-of-way
  • Applies to street excavation, asphalt/concrete penetration, boring, and utility trenching
  • Cash fee or surety bond required, refunded/released after 24 months if the excavation surface is accepted by a city official

Required documents

  • RequiredEncroachment Permit Application (CivicReview)Submitted online via the CivicReview portal (app.civicreview.com), per North Logan's official Building Department page, 'Additional Permits' section.

Fee schedule

Fee typeAmountNotes
Narrow Trench (<6" wide) Boring Permit Fee$0.60 per linear footNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section, Street Excavation Permits or Encroachment Permits table.
Road Cut — No Disturbance of Asphalt / Road >3 years$1,000.00 non-refundable fee plus $500.00 deposit; if disturbed area exceeds 300 sq ft, $3.50 per sq ft of asphalt disturbedNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
New Road Cut Permit Fee (<3 years)$5,000.00 non-refundable fee plus $500.00 deposit; if disturbed area exceeds 300 sq ft, $16.50 per sq ft of asphalt disturbedNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
Asphalt or Concrete Surface Penetration$25.00 non-refundable inspection fee plus cash fee or surety bond of $200.00 or $3.00 per sq ft, whichever is greaterNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
Pothole Fee$250 per pothole, non-refundable feeNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
Sidewalk, Street, Driveway, and Building Material on Street PermitsNo fee, but applicant must pay any costs incurred by the cityNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Later version (2026-07-16) →View current record →All versions →