Codes adopted

2024 International Building Code (IBC), including Appendices C and J — North Logan Municipal Code § 9-401 adopts 'the building codes, adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(a), the 2024 IBC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here. Because NLMC § 9-401 is a blanket cross-reference to the state's adopted edition rather than a hardcoded year, North Logan's local ordinance tracks the statute automatically — no city ordinance amendment was needed for this transition. North Logan's own Building Codes & Design Criteria page links directly to the State Adopted Codes list rather than publishing a separate local list, and states 'there are no local amendments for North Logan' (live-checked 2026-07-16, unchanged).2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition. Adopted per NLMC § 9-401's blanket adoption of state-adopted building codes.Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in NLMC Title 9, added here per statute.2024 International Plumbing Code (IPC) — NLMC § 9-600/§ 9-701 adopts 'the Uniform Plumbing Code, currently adopted by State of Utah'; per Utah Code § 15A-2-103(1)(d), the 2024 IPC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here (blanket cross-reference tracks the statute automatically).2024 International Mechanical Code (IMC) — NLMC § 9-705 adopts the mechanical code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(e), the 2024 IMC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.2024 International Fuel Gas Code (IFGC) — NLMC § 9-702 adopts the fuel gas code 'as adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(f), the 2024 IFGC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.2024 International Energy Conservation Code (IECC), single unsplit statewide edition — NLMC § 9-707 adopts the energy conservation code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(h), the 2024 IECC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.2023 National Electrical Code (NEC) — REMAINS CURRENT; NLMC § 9-500/§ 9-501 adopts 'the electrical code, adopted by the State of Utah'; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 statewide transition.2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it (covered generally by NLMC § 9-401's blanket building-code adoption).Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it.NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. North Logan's Building Codes & Design Criteria page (northlogancity.gov/building) was live-checked 2026-07-16: it still links generically to the state's 'State Adopted Codes' list rather than itemizing edition years itself, and still states 'there are no local amendments for North Logan' — no page-vs-statute lag was found because the page (like NLMC Title 9's own text) defers entirely to the state's current list rather than asserting specific years.

Permit types & fees

Residential Building Permit

Verified

Required for new single-family residential construction and any structure over 200 sq ft in North Logan. Must be preceded by a Zoning Clearance (Step 1) before the Building Permit (Step 2) can be requested. Fee is valuation-based under the 1997 Uniform Building Code Table No. 3-A, adjusted annually by CPI, per North Logan Municipal Code § 9-205 and the city's Master Fee Schedule.

Verified 2026-07-08 · Source

Requirements

  • New single-family residential construction, or any structure over 200 sq. ft.
  • Zoning Clearance (Step 1) must be obtained first via the CivicReview portal before a Building Permit application can be submitted — applies to primary structures, accessory structures, agricultural structures, signs, fences, pools, or retaining walls over 3 feet in height
  • Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203
  • Soils Hazard Mitigation Plan required if the site's NRCS soils rating is 'very limited,' per NLMC § 9-206
  • Concrete inspection required for curb, gutter, and sidewalk work, with at least 24-hour advance notice

Required documents

  • RequiredZoning Clearance ApplicationSubmitted online via the CivicReview portal (app.civicreview.com); required before a Building Permit can be requested, per North Logan's official Building Department page.
  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com after Zoning Clearance approval; applicant uploads the zoning clearance approval letter along with applicable building plans, per North Logan's official Building Department page.
  • Required2 Sets of Plans and SpecificationsRequired with the written building permit application per North Logan Municipal Code § 9-203; one set is retained by the Building Inspector.
  • OptionalOwner/Builder Certification FormUtah Department of Commerce, Division of Occupational and Professional Licensing form, required when the owner acts as their own contractor; available as a downloadable PDF on North Logan's Building Department page.

Fee schedule

Fee typeAmountNotes
Building Permit FeeAs established in the 1997 Uniform Building Code (Table No. 3-A), adjusted annually by the CPINorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026), citing North Logan Municipal Code § 9-205: 'The Treasurer shall collect a fee for the Building Permit from the applicant in an amount in accordance with Table No. 3-A of the Uniform Building Code.' A down payment is due at application: Single Family Home $50; permits where the total fee is likely to be less than $100.00, $0 down payment.
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026).
Road Impact Fee (Single Family Detached)$2,432 per housing unitNorth Logan Master Fee Schedule, 'Building Permit Fees' section — Road Impact Fee table, Residential (per housing unit), citing the North Logan Impact Fee Analysis report dated June 25, 2024.
Water Impact Fee (3/4-inch meter, standard residential)$4,841 per meterNorth Logan Master Fee Schedule, 'Building Permit Fees' section — Water Impact Fee table by meter size.
Residential Sewer Impact Fee (Single Family Residential)$6,697 (North Service Area) or $4,039 (South Service Area)North Logan Master Fee Schedule, 'Building Permit Fees' section — Residential Sewer Impact Fee table, varies by service area.
Parks & Trails Impact Fee (Residential)$5,315 per household/housing unitNorth Logan Master Fee Schedule, 'Building Permit Fees' section.
Logan City Imposed Wastewater Treatment Impact Fee (LCIWTIF) — Single Family Unit$2,433.00 per unit (1 ERU multiplier)North Logan Master Fee Schedule, 'Building Permit Fees' section, per Resolution 25-02 (2/19/2025); collected by North Logan and remitted per agreement with Logan City for wastewater treatment capacity.
Water Meter FeeDirect market cost of meter and supplies, plus $60.00 installation feeNorth Logan Master Fee Schedule, 'Building Permit Fees' section; cost verified by the Public Works Department.

Combined Electrical, Mechanical, Plumbing Permit

Verified

Required for standalone electrical, mechanical, or plumbing work in North Logan not part of a new residential building permit. Exempt from the Zoning Clearance requirement and can be applied for directly. Fee is calculated as a percentage of what the corresponding Building Permit Fee would be. EV charger/EVSE installation is electrical work and falls under this combined Electrical, Mechanical, Plumbing Permit; North Logan's Master Fee Schedule does not publish a separate EV-charger fee line item.

Verified 2026-07-20 · Source

Requirements

  • Electrical, mechanical, or plumbing work performed independently of new construction
  • Exempt from Zoning Clearance (Step 1) — apply directly for the permit
  • Subject to the adopted 2023 NEC (electrical), 2024 IMC (mechanical), and 2024 IPC (plumbing) per North Logan Municipal Code Title 9

Required documents

  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com; no Zoning Clearance approval letter required for these exempt permit types.

Fee schedule

Fee typeAmountNotes
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026). The underlying Building Permit Fee is calculated per the 1997 Uniform Building Code Table No. 3-A valuation table, adjusted annually by CPI, per North Logan Municipal Code § 9-205.

Encroachment Permit

Verified

Required for work within the public right-of-way in North Logan, including street excavation, road cuts, boring, and utility trenching. Fees are structured around inspection and surety/cash bond deposits tied to the type and age of the disturbed surface.

Verified 2026-07-08 · Source

Requirements

  • Required for any work within the public right-of-way
  • Applies to street excavation, asphalt/concrete penetration, boring, and utility trenching
  • Cash fee or surety bond required, refunded/released after 24 months if the excavation surface is accepted by a city official

Required documents

  • RequiredEncroachment Permit Application (CivicReview)Submitted online via the CivicReview portal (app.civicreview.com), per North Logan's official Building Department page, 'Additional Permits' section.

Fee schedule

Fee typeAmountNotes
Narrow Trench (<6" wide) Boring Permit Fee$0.60 per linear footNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section, Street Excavation Permits or Encroachment Permits table.
Road Cut — No Disturbance of Asphalt / Road >3 years$1,000.00 non-refundable fee plus $500.00 deposit; if disturbed area exceeds 300 sq ft, $3.50 per sq ft of asphalt disturbedNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
New Road Cut Permit Fee (<3 years)$5,000.00 non-refundable fee plus $500.00 deposit; if disturbed area exceeds 300 sq ft, $16.50 per sq ft of asphalt disturbedNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
Asphalt or Concrete Surface Penetration$25.00 non-refundable inspection fee plus cash fee or surety bond of $200.00 or $3.00 per sq ft, whichever is greaterNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
Pothole Fee$250 per pothole, non-refundable feeNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.
Sidewalk, Street, Driveway, and Building Material on Street PermitsNo fee, but applicant must pay any costs incurred by the cityNorth Logan Master Fee Schedule, 'Other Construction Related Permits' section.

Commercial Building Permit

Verified

Required for new commercial building construction in North Logan. Governed by the same two-step Zoning Clearance (Step 1) + Building Permit (Step 2) process and the same 1997 Uniform Building Code Table No. 3-A valuation-based fee (NLMC § 9-205) as residential construction, but subject to a distinct commercial down payment tier and commercial-specific road, water, sewer, and wastewater-treatment impact fees per the North Logan Master Fee Schedule.

Verified 2026-07-19 · Source

Requirements

  • New commercial building construction, or any structure over 200 sq. ft.
  • Zoning Clearance (Step 1) must be obtained first via the CivicReview portal before a Building Permit application can be submitted — North Logan's official Building Department page describes this requirement as applying to 'the construction or modification of any permanent structure' with no residential/commercial carve-out
  • Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203
  • Down payment of $1,100 due at application for 'New building other than single family home,' per the North Logan Master Fee Schedule's Building Permit Fees down-payment table
  • Soils Hazard Mitigation Plan required if the site's NRCS soils rating is 'very limited,' per NLMC § 9-206
  • Concrete inspection required for curb, gutter, and sidewalk work, with at least 24-hour advance notice

Required documents

  • RequiredZoning Clearance ApplicationSubmitted online via the CivicReview portal (app.civicreview.com); required before a Building Permit can be requested, per North Logan's official Building Department page (live-checked 2026-07-19).
  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com after Zoning Clearance approval; applicant uploads the zoning clearance approval letter along with applicable building plans, per North Logan's official Building Department page.
  • Required2 Sets of Plans and SpecificationsRequired with the written building permit application per North Logan Municipal Code § 9-203; one set is retained by the Building Inspector. NLMC Title 9 does not itemize additional commercial-specific plan documents (e.g., a separate site plan or SWPPP requirement) beyond this general application requirement.

Fee schedule

Fee typeAmountNotes
Building Permit FeeAs established in the 1997 Uniform Building Code (Table No. 3-A), adjusted annually by the CPINorth Logan Master Fee Schedule, 'Building Permit Fees' section (fetched via print-preview 2026-07-19): 'Building Permit Fee*** As established in the 1997 Uniform Building Code adjusted annually by the CPI,' citing North Logan Municipal Code § 9-205. This is the same underlying valuation fee table used for residential construction; NLMC Title 9 does not publish a separate commercial fee table.
Down Payment — New Building Other Than Single Family Home$1,100North Logan Master Fee Schedule, 'Building Permit Fees' section, down-payment table (fetched 2026-07-19): 'New building other than single family home $1,100.' Due when the applicant first applies for the building permit; forfeited to the city if the application is withdrawn after plan review or not completed, per the same section.
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (fetched 2026-07-19): 'Combined Electrical, Mechanical, Plumbing Permit Fee — 27.5% of the Building Permit Fee.'
Zoning Clearance Fee$125.00North Logan Master Fee Schedule, 'Development Fees' section, 'Misc. Development Fees' table (fetched 2026-07-19): 'Zoning Clearance fee $125.00.' Applies to the Step 1 Zoning Clearance required before the Step 2 Building Permit can be requested.
Road Impact Fee — Commercial/Industrial (per 1,000 sq. ft.)Small Office Building $3,427; Medical or Dental Office Building $7,777; Apparel Store $13,887; Light Industrial $1,517; Warehousing $877; Manufacturing $1,487North Logan Master Fee Schedule, 'Building Permit Fees' section, Road Impact Fee table, Commercial/Industrial (per 1,000 square feet) (fetched 2026-07-19). Verbatim note in the same table: 'For building types other than those listed above, fee will be calculated by utilizing the Institute of Transportation Engineers (ITE) Manual and the North Logan Impact Fee Analysis report dated June 25, 2024.'
Water Impact Fee (by meter size)3/4-inch $4,841; 1-inch $8,084; 1.5-inch $16,120; 2-inch $25,801; 3-inch $72,611; 4-inch $161,342North Logan Master Fee Schedule, 'Building Permit Fees' section, Water Impact Fee table by meter size (fetched 2026-07-19) — the same table applies to commercial connections, which typically use larger meter sizes than the standard residential 3/4-inch meter.
Non-Residential Sewer Impact Fee (by pipe size)North Service Area: 4-inch $6,697, 6-inch $15,068, 8-inch $26,788, 12-inch $60,274. South Service Area: 4-inch $4,039, 6-inch $9,088, 8-inch $16,157, 12-inch $36,353North Logan Master Fee Schedule, 'Building Permit Fees' section, 'Non-Residential Sewer Impact Fee' table by pipe size and service area (fetched 2026-07-19). 'For pipes other than those listed above, fee will be calculated by the "Capacity Ratio to 4" Sewer Pipe".'
Logan City Imposed Wastewater Treatment Impact Fee (LCIWTIF) — Non-Standard Impact Fee (Commercial/Industrial)2-inch Displacement Compound Meter (3.2 ERU multiplier): $7,786.00 minimum fee; 4-inch Compound Meter (10 ERU multiplier): $24,327.00 minimum fee; otherwise (actual GPD / 245 GPD) x $2,433.00North Logan Master Fee Schedule, 'Building Permit Fees' section, LCIWTIF table (fetched 2026-07-19): 'NON-STANDARD IMPACT FEE** ... ** LCIWTIF Definition: Non-Standard Impact Fee: Defined as commercial and industrial facilities, and public facilities.' Per Resolution 25-02 (2/19/2025), same resolution cited for the residential LCIWTIF fee in this file.

Commercial Tenant Improvement / Tenant Finish Permit

Required for interior remodel, tenant improvement, and tenant finish work in existing commercial buildings in North Logan, per NLMC § 9-201's general requirement that any alteration to a building or structure requires a building permit. North Logan does not publish a tenant-improvement-specific fee table separate from its general Building Permit Fee down-payment tiers, and its official materials do not explicitly state whether interior tenant improvement work triggers the Step 1 Zoning Clearance required for new/modified permanent structures.

Reviewed 2026-07-19 · Source

Requirements

  • Alteration to an existing commercial building or structure — NLMC § 9-201 requires a permit for any construction or alteration of a building or structure (except a fence)
  • Written application accompanied by 2 sets of plans and specifications stating the specific nature of the alteration, per NLMC § 9-203
  • Down payment of $1,100 due at application if the remodel affects more than 3,000 sq. ft. of a building other than a single-family home AND requires structural changes; otherwise the $50 'all other permits' down payment tier applies, per the Master Fee Schedule's down-payment table
  • Whether a Zoning Clearance (Step 1) is separately required is NOT explicitly stated for interior tenant improvement work — North Logan's Building Department page scopes Zoning Clearance to 'the construction or modification of any permanent structure,' with examples limited to primary/accessory/agricultural structures, signs, fences, pools, and retaining walls over 3 feet; interior finish work that does not modify the structure's exterior, footprint, or height is not listed as requiring or being exempt from Zoning Clearance

Required documents

  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com, per North Logan's official Building Department page.
  • Required2 Sets of Plans and SpecificationsRequired with the written building permit application per North Logan Municipal Code § 9-203, describing the specific nature of the tenant improvement or remodel.
  • OptionalZoning Clearance ApplicationRequired if the scope of work modifies a permanent structure (see requirements note above on the unresolved applicability to interior-only tenant improvement work); confirm with the Building Department, (435) 752-1310, before submitting a Building Permit application without it.

Fee schedule

Fee typeAmountNotes
Building Permit FeeAs established in the 1997 Uniform Building Code (Table No. 3-A), adjusted annually by the CPINorth Logan Master Fee Schedule, 'Building Permit Fees' section (fetched 2026-07-19), citing NLMC § 9-205. North Logan does not publish a separate tenant-improvement or commercial-remodel-specific fee table — the same valuation-based Table No. 3-A fee applies.
Down Payment — Remodel Other Than Single Family Home (>3,000 sq. ft. + structural changes)$1,100North Logan Master Fee Schedule, 'Building Permit Fees' section, down-payment table (fetched 2026-07-19): 'Remodel to other than single family home affecting more than 3,000 sq. ft. and requiring structural changes $1,100.'
Down Payment — All Other Permits (below the 3,000 sq. ft./structural-change threshold)$50North Logan Master Fee Schedule, 'Building Permit Fees' section, down-payment table (fetched 2026-07-19): 'All other permits $50.' Applies to smaller tenant improvement/remodel scopes that don't meet the $1,100 tier's size and structural-change criteria.
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (fetched 2026-07-19) — applies if the tenant improvement scope includes electrical, mechanical, or plumbing trade work.

Photovoltaic (PV) System Permit

Verified

Required for installation of a residential or commercial photovoltaic (solar) system in North Logan. Unlike a standard standalone electrical permit, PV installations follow their own documented submittal process — a dedicated Permit Application, plans emailed directly to the Building Department, and a PV System Plan Check Worksheet used to verify NEC code compliance. The underlying permit fee itself is the same valuation-based Building Permit Fee plus the 27.5% Combined Electrical/Mechanical/Plumbing Permit Fee documented in this file's electrical-mechanical-plumbing-permit entry — North Logan does not publish a separate dollar-amount solar fee tier — but the application path, required worksheet, and a $50 non-refundable deposit are solar-specific and distinct from other trade permits.

Verified 2026-07-20 · Source

Requirements

  • Permit Application identifying the primary contractor and any subcontractors, including contractor license numbers
  • Plans submitted electronically in PDF format, emailed to plans@northlogancity.org (per the city's dedicated PV permit process page, archived 2024-02-28; a stamped copy is returned by email once approved)
  • Structural plans required if the installation involves modification of a building or construction of any supporting structure for the PV system
  • PV System Plan Check Worksheet completed and submitted with the plans — covers site diagram, one-line diagram, array configuration, equipment/system grounding, disconnect and point-of-connection details, inverter listing/utility-interactivity status, PV module listing and Pmax voltage/current, ground-fault and DC arc-fault protection (NEC 690.7/690.8/690.11), and for roof-mounted arrays, structural calculations and roof-attachment details, or for ground-mounted arrays, foundation/footing and mounting-structure details
  • $50.00 non-refundable deposit due at submittal of the permit application and documents, applied toward the final calculated fees

Required documents

  • RequiredPermit ApplicationIdentifies the primary contractor and subcontractors with license numbers; downloadable from the city's Building Department page.
  • RequiredPV System Plan Check WorksheetNorth Logan's official worksheet for verifying NEC code compliance of the proposed PV system — covers supplied diagrams, inverter information, PV module information, array information (ground-fault/arc-fault protection, max array voltage, short-circuit current), and roof- or ground-mounting structural details. Listed as a current Building Department resource on northlogancity.gov (live-checked 2026-07-19); PDF text extracted from a 2016-dated version of the worksheet via Wayback Machine archive.
  • OptionalStructural PlansRequired if the installation modifies a building or involves construction of a supporting structure for the PV system.

Fee schedule

Fee typeAmountNotes
PV System Application Deposit$50.00 (non-refundable, applied toward final fees)North Logan City 'Permit Process for Photovoltaic (PV) Systems' page: 'A $50.00 deposit will be required when the permit application and documents are submitted. This deposit is nonrefundable, but will be applied toward the fees calculated during permit finalization.' Sourced from a Wayback Machine archive dated 2024-02-28 (web.archive.org/web/20240228111527/https://northlogancity.org/permit-process-for-photovoltaic-pv-sytems/); the live page at this URL returns HTTP 404 as of 2026-07-19 re-check on the city's current React-based website, but the city's live Building Department page (northlogancity.gov/building, checked 2026-07-19) still lists a 'PV System Plan Check Worksheet' as a current Forms & Resources item, corroborating that PV permitting remains an active, distinct process. Re-chased 2026-07-20: independently corroborated via the CURRENT LIVE North Logan Master Fee Schedule (northlogan.municipalcodeonline.com/book?type=fees#name=Building_Permit_Fees, most recently amended by Res. 25-02 on 2/19/2025, rendered and read directly since it is a JS-rendered page a prior pass could not access) -- the schedule's 'Building Permit Fee' down-payment table lists 'All other permits: $50' (and 'Single family home: $50'), matching this figure exactly under the general down-payment category a solar/PV retrofit permit would fall into. This is now a live, current, independently-corroborating source for the $50 figure, not solely an archived one.
Building Permit Fee + Combined Electrical, Mechanical, Plumbing Permit FeeBuilding Permit Fee per 1997 UBC Table No. 3-A (adjusted annually by CPI) plus 27.5% of that fee for the combined electrical/mechanical/plumbing scopePer the archived PV permit process page: 'The fees will include a building permit fee and impact fees. The amount of these fees will be calculated as part of the permit finalization process' — payment is due when the finalized permit is picked up, accepted only by check or cash. No PV-specific dollar-figure fee table is separately published; the underlying valuation-based Building Permit Fee (NLMC § 9-205) and 27.5% Combined Electrical/Mechanical/Plumbing Permit Fee (North Logan Master Fee Schedule) are the applicable fees. Re-chased 2026-07-20: re-fetched the live current Master Fee Schedule directly (rendered via browser since the site is a JS-rendered civiclinq-style book) and confirmed verbatim: 'Building Permit Fee*** As established in the 1997 Uniform Building Code adjusted annually by the CPI' and 'Combined Electrical, Mechanical, Plumbing Permit Fee: 27.5% of the Building Permit Fee' (both under the still-current 'Building Permit Fees' section, most recently amended 2/19/2025). Also ran a full-text search of the entire fee schedule for 'solar' -- zero results -- and read the adjacent 'Other Construction Related Permits' section in full (sidewalk/driveway/excavation/right-of-way permits only) -- confirming no dedicated PV/solar fee line exists anywhere in the current schedule. The general valuation-based mechanism is therefore confirmed as the governing fee structure, not an unverified inference.

Sign Permit

Verified

Required in North Logan City to erect, construct, or alter any sign, per the same Zoning Clearance-then-Building Permit process used for other structures. North Logan's official Master Fee Schedule publishes a distinct 'Signs And Sign Permit Fees' category separate from the valuation-based Building Permit Fee: a flat $75.00 Sign Permit fee, plus a Sign Construction Inspection Fee that follows the Building Permit Fee schedule.

Verified 2026-07-20 · Source

Requirements

  • A Zoning Clearance (Step 1) must be obtained first via the CivicReview portal before a Sign Permit/Building Permit application can be submitted — North Logan Municipal Code lists signs among the structure types requiring Zoning Clearance, alongside primary structures, accessory structures, agricultural structures, fences, pools, and retaining walls over 3 feet in height
  • Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203 (the same general building-permit submittal requirement applied citywide)

Required documents

  • RequiredZoning Clearance Application (CivicReview portal)Required first-step approval before a sign permit application can be submitted, per North Logan Municipal Code.
  • RequiredPlans and Specifications (2 sets)Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203.

Fee schedule

Fee typeAmountNotes
Sign Permit$75.00 plus any costs incurred by the city that exceed this amountNorth Logan City Master Fee Schedule, 'Signs And Sign Permit Fees' section: 'Sign Permit $75.00 plus any costs incurred by the city that exceed this amount.'
Sign Construction Inspection FeeSame as Building Permit Fee (valuation-based, per 1997 UBC Table No. 3-A, adjusted annually by CPI)North Logan City Master Fee Schedule: 'Sign Construction Inspection Fee — Construction Inspection Fee shall follow the Building Permit Fee, as stated above.'

Fire Sprinkler / Fire Alarm System Plan Review and Permit

Verified

Fire protection and fire code enforcement for North Logan is provided by the Logan City Fire Department (LCFD), not North Logan's own Building Department — a direct fetch of northlogancity.gov/fire confirms 'The Logan City Fire Department (LCFD) provides fire protection and emergency medical services to the cities of Logan, North Logan, Providence, and River Heights,' with North Logan covered from Station 120 (built 1993). LCFD's Fire Prevention Bureau requires automatic fire alarm and automatic fire sprinkler system plans to go through a mandatory third-party plan review (an approved private firm, not LCFD directly) before LCFD grants final approval, IN ADDITION to LCFD's own plan-review/inspection fees. A second re-chase on 2026-07-20 located the actual governing fee document: it is not Logan City's Building Permit Fees Resolution No. 20-09 (checked in full previously, no fire line item) but a separate, dedicated City of Logan Resolution No. 23-14, 'A Resolution Adopting Fire Prevention Inspection Fees,' adopted by the Logan Municipal Council on 10/4/2023 and found via a full CDX sweep of loganutah.gov's council-packet archive (a URL never surfaced by the site's own navigation or search). Its attached Fire Department Fee Schedule sets, for 'New Construction/Tenant Improvements with fire sprinklers and fire alarms': 1 general plan review $75.00, 1 fire alarm plan review $75.00, 1 fire sprinkler plan review $75.00, 1 fire alarm rough-install inspection $75.00, 1 fire sprinkler rough-install inspection $75.00, 1 final inspection (24-hour test, 2 visits) $150.00 — subtotal $525.00, added directly to the building permit fee (rising to $675.00 if a kitchen-hood suppression system plan review/final is also required). This LCFD-set fee is separate from and in addition to the mandatory third-party peer-review firm's own charge (still not city-published, since that firm sets its own private rate). Cross-checked North Logan's own municipal code Master Fee Schedule (northlogan.municipalcodeonline.com/book/print?type=fees, fetched in full) and confirmed it has no fire alarm/sprinkler/plan-review line items of its own (only fire-inspection add-ons tied to business licenses), consistent with North Logan deferring fire permitting entirely to LCFD and LCFD's Resolution 23-14 governing. No resolution superseding 23-14 for these specific line items was found in the council-packet archive through 2026.

Verified 2026-07-20 · Source

Requirements

  • New installation or modification of an automatic fire alarm system or automatic fire sprinkler system on a property in North Logan (served by Logan City Fire Department)
  • Plan submittal secured through Logan Fire Department Fire Prevention Bureau before any work on the system begins, per LCFD's Automatic Fire Alarm/Sprinkler Systems Information Packets (September 2023)
  • Plans for systems requiring third-party review must first go to an LCFD-approved private review firm (e.g., Bureau Veritas, RMC-F LLC, CBPE, SAFEbuilt, Jensen Hughes, West Coast Code Consultants, Protection Consultants Inc.) before LCFD will grant final approval
  • Fire sprinkler hydrostatic, flush, and thrust block testing must be witnessed by an LCFD fire official prior to final inspection being scheduled

Required documents

  • RequiredAutomatic Fire Alarm Systems Information Packet (September 2023)LCFD Fire Prevention Bureau packet outlining IFC/IBC/NFPA and local-amendment requirements for automatic fire alarm system plan submittals; contact Fire Marshal Craig Humphreys, (435) 716-9515.
  • RequiredAutomatic Fire Sprinkler Systems Information Packet (September 2023)LCFD Fire Prevention Bureau packet outlining IFC/IBC/NFPA and local-amendment requirements for automatic fire sprinkler system plan submittals; contact Fire Marshal Craig Humphreys, (435) 716-9515.
  • RequiredThird Party Fire Plan Review — Approved Firm ListLCFD's published list of approved third-party review companies for fire alarm and sprinkler plans; applicants select and pay one of these firms directly for the required review before LCFD grants final approval.

Fee schedule

Fee typeAmountNotes
General Plan Review (fire alarm/sprinkler project)$75.00City of Logan Resolution No. 23-14, 'Fire Prevention Inspection Fees' (adopted by the Logan Municipal Council 10/4/2023), Fire Department Fee Schedule — applies to properties served by Logan City Fire Department, including North Logan.
Fire Alarm Plan Review$75.00City of Logan Resolution No. 23-14, Fire Department Fee Schedule, 'New Construction/Tenant Improvements with fire sprinklers and fire alarms' line item.
Fire Sprinkler Plan Review$75.00City of Logan Resolution No. 23-14, Fire Department Fee Schedule, same line item.
Fire Alarm Rough-Install Inspection$75.00City of Logan Resolution No. 23-14, Fire Department Fee Schedule.
Fire Sprinkler Rough-Install Inspection$75.00City of Logan Resolution No. 23-14, Fire Department Fee Schedule.
Final Inspection (24-hour test, 2 visits)$150.00City of Logan Resolution No. 23-14, Fire Department Fee Schedule.
Combined Fire Alarm + Sprinkler Total (added to building permit)$525.00 (rises to $675.00 if a kitchen-hood suppression system plan review ($75) and final ($75) are also required)City of Logan Resolution No. 23-14, Fire Department Fee Schedule subtotal for new construction/TI with both fire sprinklers and fire alarms. This LCFD-set fee is separate from and in addition to the mandatory third-party peer-review firm's own charge, which remains privately set and not city-published.

EV Charger / EVSE Permit

Verified

North Logan does not publish a distinct EV-charger fee line item. Per the North Logan City Master Fee Schedule, installing an EV charger (EVSE) is electrical work billed under the city's combined Electrical, Mechanical, Plumbing Permit — 27.5% of what the corresponding Building Permit Fee would be.

Verified 2026-07-20 · Source

Requirements

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New dedicated circuit and/or panel/service capacity to serve the charger
  • Compliance with the 2023 NEC, adopted statewide by Utah Code § 15A-2-103(1)(g), and North Logan Municipal Code Title 9
  • Exempt from the Zoning Clearance requirement — can be applied for directly

Required documents

  • RequiredBuilding Permit Application (CityInspect)Submitted online via nlogan.cityinspect.com; no Zoning Clearance approval letter required for this exempt permit type.

Fee schedule

Fee typeAmountNotes
Combined Electrical, Mechanical, Plumbing Permit Fee27.5% of the Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026). The underlying Building Permit Fee is calculated per the 1997 Uniform Building Code Table No. 3-A valuation table, adjusted annually by CPI, per North Logan Municipal Code § 9-205. EV charger installs are billed under this combined electrical fee — North Logan does not publish a separate EV-specific rate.

Change of Use Permit (Business License Relocation / New Occupancy Review)

Verified

North Logan does not publish a single, distinctly-named 'Change of Use Permit.' A direct fetch of the city's own Business License Department page (northlogancity.gov/business-license) and North Logan Municipal Code (NLMC) Title 8, Regulation Of Business, confirms the functional mechanism instead: NLMC § 8-111 requires 'a separate license must be obtained for each separate place of business,' and each license 'authorize[s] the licensee to engage only in the business licensed thereby at the location or in the manner designated' — meaning a business relocating to a different building/tenant space, or changing its use, must file a new Business License Application (Form B-3) at the new location/use rather than transfer the old one (licenses are non-transferable per NLMC § 8-109 and § 8-413). Form B-3's 'Building Code Compliance Information' section (building use, square footage, fire sprinkler status, number of exits/stories, whether construction/remodeling is occurring) functions as North Logan's use/occupancy screening in place of a separate zoning-compliance certificate. Certain business types require an additional Conditional Use Permit from the Planning Commission per NLMC § 8-505 (child care over 8 children, licensed group child care, beauty/barber shops with more than 3 practitioners, instruction groups exceeding 4 students/class, and all short-term rentals per NLMC § 12C-517), a distinct $350.00 fee per the Master Fee Schedule's Misc. Development Fees section. Where the change of use requires construction to accommodate the new occupancy, that construction is billed under this file's commercial-building-permit or commercial-tenant-improvement-permit entries (including the Zoning Clearance question left open in the latter) — those fees are not duplicated here. No certificate-of-occupancy or change-of-use ordinance provision was found anywhere in NLMC Title 9 (Building And Construction) — a full-text check of that title for 'occupancy'/'occupant' returned only one unrelated match (§ 9-503, utility disconnection notice to a building's 'owner or occupant'). NLMC Title 12 (Land Use) was replaced in its entirety by Ordinance 25-11 and is still being codified online as of this research (2026-07-22), so a distinct Title 12C zoning/use-change provision cannot be ruled out, but is not independently confirmed.

Verified 2026-07-22 · Source

Requirements

  • A business relocating to a different building or tenant space in North Logan, or changing its use/occupancy, must file a new Business License Application (Form B-3) for that specific location — per NLMC § 8-111, a separate license is required for each separate place of business, and per NLMC § 8-109/§ 8-413 an existing license cannot be assigned or transferred to a new location or use
  • Form B-3's Building Code Compliance Information section must be completed, disclosing building use, square footage, fire sprinkler status, number of exits/stories, age of building, and whether construction or remodeling is being done
  • A Conditional Use Permit from the Planning Commission is required for specific business types regardless of location change, per NLMC § 8-505: child care for more than 8 children, licensed group child care, beauty/barber shops with more than 3 practitioners, instruction to groups exceeding 4 students per class, and all short-term rental units (per NLMC § 12C-517)
  • If the new use requires construction or remodeling (Form B-3 item 11), the applicant must separately obtain the applicable Building Permit or Commercial Tenant Improvement permit documented elsewhere in this file

Required documents

  • RequiredBusiness License Application (Form B-3)North Logan City Corporation's standard business license application; used for both new applications and renewals, with no separate 'change of location' variant — a relocating or use-changing business checks 'New Application' for the new location, per northlogancity.gov/business-license.
  • OptionalConditional Use Permit ApplicationSubmitted online via North Logan's Land Use Applications portal (Community Development Department); required only for the specific business types listed in NLMC § 8-505, independent of whether the business is new, relocating, or changing use.
  • OptionalSelf-Inspection WorksheetRequired specifically for Home Business License applicants per northlogancity.gov/business-license's 'Home Business License' listing, covering Fire Department safety requirements.

Fee schedule

Fee typeAmountNotes
Commercial Business License — Initial (Class 1, up to 90,000 sq. ft.)$150.00 base (includes up to a one-hour Fire Inspection)North Logan Master Fee Schedule, 'Business License Fees' section (current as of 5/5/2026): 'Commercial Class 1: <or= 90,000 sq.ft. — Initial License $150.00 base* (includes up to One-Hour Fire Inspection).' Applies to a new or relocating/use-changing business at a new location, since NLMC § 8-111 treats each location as requiring its own license.
Commercial Business License — Initial (Class 2, over 90,000 sq. ft. and/or large manufacturer)$200.00 base (includes up to a three-hour Fire Inspection)North Logan Master Fee Schedule, 'Business License Fees' section: 'Commercial Class 2: > 90,000 sq.ft. and/or Large manufacturer — Initial License $200.00 base* (includes up to Three-Hour Fire Inspection).'
Home Occupation License — Initial (Class 1 / Class 2)Class 1 (no or very limited client access): $75.00 base; Class 2 (more regular client access): $135.00 base (includes up to a one-hour Fire Inspection)North Logan Master Fee Schedule, 'Business License Fees' section. A 'Home Exempt' tier (no public access) requires no license and no fee.
Conditional Use Permit$350.00North Logan Master Fee Schedule, 'Development Fees' section, 'Misc. Development Fees' table (fetched 2026-07-22): 'Conditional Use Permit $350.00.' Required only for the specific business types listed in NLMC § 8-505.
Zoning Clearance$125.00North Logan Master Fee Schedule, 'Development Fees' section, 'Misc. Development Fees' table. Scoped by North Logan's own Land Use Applications page to 'the construction or modification of any permanent structure or permanent improvement' — applicable only where a change of use is accompanied by such construction/modification, not to an interior-only occupancy change with no structural work.
Added Fee for Fire Inspection (beyond the bundled amount)$75.00 per additional half hourNorth Logan Master Fee Schedule, 'Business License Fees' section, 'Additional Fees': 'Added Fee for Fire Inspection: Add $75.00 per half hour.'
Hazardous Materials Fee$20.00North Logan Master Fee Schedule, 'Business License Fees' section, 'Additional Fees': 'Hazard Materials Fee: Add $20.00.' Applies if Form B-3's hazardous-materials checkboxes are triggered by the new use.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-07)View current record →All versions →

Permalink: /utah/cache-county/north-logan/as-of/2026-07-16/

Snapshot date: 2026-07-16

Commit: 9d25784

Reproducible from PermitBase’s version-controlled dataset, commit 9d25784.