Unincorporated Emery County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Emery County, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
75 East Main St, Room 106, PO Box 417, Castle Dale, UT 84513
Phone
(435) 381-3555
Office hours
Mon–Fri 8:30 AM – 5:00 PM, except county holidays

Published scheduling rules

  • Inspections are scheduled by calling Katrina at Sunrise Engineering, 1-800-560-6151 — the county contracts inspection services to Sunrise Engineering. A minimum of 24 business hours' notice is required for all inspections. (Residential Building Permit)
  • Inspections are scheduled through Sunrise Engineering (1-800-560-6151, ask for Katrina), which the county contracts for inspection services — a minimum of 24 business hours' notice is required. (Commercial Building Permit)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Temp Pedestal / Power to Panel / Gas Line

    Pre-construction utility inspections as applicable

  2. 2

    Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing)

    Before concrete pour and before rough work is covered

  3. 3

    Rough (Building, Electrical, Mechanical, Plumbing, Insulation, Weather Barrier, Shear Nailing, Shower Pan, Stucco Lathe, Bond Beam, Block Building)

    After framing and rough-in MEP, before drywall/wall cover — specific rough inspections depend on construction type

  4. 4

    Final (Building, Electrical, Mechanical, Plumbing, Grading)

    All work complete; occupancy is prohibited until after final inspection and Certificate of Occupancy is issued

Applies to: Commercial Building Permit

  1. 1

    Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing)

    Before concrete pour and before rough work is covered.

  2. 2

    Rough (Building, Electrical, Mechanical, Plumbing, Weather Barrier, Bond Beam, Block Building)

    After framing and rough-in MEP, before drywall/wall cover.

  3. 3

    Final (Building, Electrical, Mechanical, Plumbing, Grading)

    All work complete; occupancy is prohibited until after final inspection and Certificate of Occupancy is issued.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough (Building, Electrical, Mechanical, Plumbing)

    As applicable to the tenant-improvement scope, before wall closure.

  2. 2

    Final

    All work complete; occupancy prohibited until after final inspection and Certificate of Occupancy.

Applies to: Solar PV Installation Permit

  1. 1

    Electrical Inspection

    Inspection of the PV system's electrical work — panel/interconnection, inverter, and wiring — part of the standard building-permit inspection sequence administered by Emery County Building & Zoning.

  2. 2

    Final

    For roof-mounted arrays, confirms structural attachment and completed work before the system is placed in service.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Emery County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Emery County building permits

Get alerts for Unincorporated Emery County

We'll email you when Unincorporated Emery County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.