Unincorporated Emery County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Emery County, Utah.
Verified 2026-07-08 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 75 East Main St, Room 106, PO Box 417, Castle Dale, UT 84513
- Phone
- (435) 381-3555
- Office hours
- Mon–Fri 8:30 AM – 5:00 PM, except county holidays
- Website
- Official site
Published scheduling rules
- Inspections are scheduled by calling Katrina at Sunrise Engineering, 1-800-560-6151 — the county contracts inspection services to Sunrise Engineering. A minimum of 24 business hours' notice is required for all inspections. (Residential Building Permit)
- Inspections are scheduled through Sunrise Engineering (1-800-560-6151, ask for Katrina), which the county contracts for inspection services — a minimum of 24 business hours' notice is required. (Commercial Building Permit)
Inspection sequence
Applies to: Residential Building Permit
- 1
Temp Pedestal / Power to Panel / Gas Line
Pre-construction utility inspections as applicable
- 2
Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing)
Before concrete pour and before rough work is covered
- 3
Rough (Building, Electrical, Mechanical, Plumbing, Insulation, Weather Barrier, Shear Nailing, Shower Pan, Stucco Lathe, Bond Beam, Block Building)
After framing and rough-in MEP, before drywall/wall cover — specific rough inspections depend on construction type
- 4
Final (Building, Electrical, Mechanical, Plumbing, Grading)
All work complete; occupancy is prohibited until after final inspection and Certificate of Occupancy is issued
Applies to: Commercial Building Permit
- 1
Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing)
Before concrete pour and before rough work is covered.
- 2
Rough (Building, Electrical, Mechanical, Plumbing, Weather Barrier, Bond Beam, Block Building)
After framing and rough-in MEP, before drywall/wall cover.
- 3
Final (Building, Electrical, Mechanical, Plumbing, Grading)
All work complete; occupancy is prohibited until after final inspection and Certificate of Occupancy is issued.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Rough (Building, Electrical, Mechanical, Plumbing)
As applicable to the tenant-improvement scope, before wall closure.
- 2
Final
All work complete; occupancy prohibited until after final inspection and Certificate of Occupancy.
Applies to: Solar PV Installation Permit
- 1
Electrical Inspection
Inspection of the PV system's electrical work — panel/interconnection, inverter, and wiring — part of the standard building-permit inspection sequence administered by Emery County Building & Zoning.
- 2
Final
For roof-mounted arrays, confirms structural attachment and completed work before the system is placed in service.
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Emery County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Emery County building permits
Get alerts for Unincorporated Emery County
We'll email you when Unincorporated Emery County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.