Residential Building Permit in Unincorporated Emery County, Utah
Required for new residential construction, additions, alterations, and most structural work on unincorporated land in Emery County. The Emery County Building & Zoning Office (Castle Dale) issues and inspects permits for land outside the eight incorporated cities/towns. Outside-city-limits applicants must first satisfy the county's 10-acre (or qualifying minor-subdivision) lot-size threshold and complete the Building Permit Point System worksheet (1000 points required) before a permit is processed.
Verified 2026-07-08 · Source
When you need this permit
- New single-family dwelling construction, additions, and structural alterations
- Outside city limits: property must be at least 10 acres, or a minor subdivision of at least 2-acre lots, recorded in the applicant's name on County records
- Outside city limits: Building Permit Point System worksheet must total 1000 qualifying points (proximity to town, road access, lot size, culinary water, electrical, sewage disposal, dwelling size)
- Minimum dwelling size 800 sq ft (per plot-plan requirement in the Outside City Limits BP Packet)
- Zoning clearance/plot plan review by the County Zoning Administrator (plot plan submitted with application)
- Road Encroachment Permit from Emery County Road Department or UDOT if the driveway/access crosses a county or state road
- Health Department approval of septic system/drain field (Southeast Utah Health Department) where no sewer connection exists
- Letter of Intent for culinary water and/or sewer hookup from the applicable irrigation/water company or district
- Setbacks (outside city limits): front 55 ft from road center or 30 ft from right-of-way (whichever is greater; 50 ft for state/federal highways), side 10 ft, rear 10 ft minimum
- Unconventional construction (log, metal frame) requires an architect/engineer stamp; commercial buildings require a certified architect/engineer
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 9 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Temp Pedestal / Power to Panel / Gas Line
Pre-construction utility inspections as applicable
- 2
Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing)
Before concrete pour and before rough work is covered
- 3
Rough (Building, Electrical, Mechanical, Plumbing, Insulation, Weather Barrier, Shear Nailing, Shower Pan, Stucco Lathe, Bond Beam, Block Building)
After framing and rough-in MEP, before drywall/wall cover — specific rough inspections depend on construction type
- 4
Final (Building, Electrical, Mechanical, Plumbing, Grading)
All work complete; occupancy is prohibited until after final inspection and Certificate of Occupancy is issued
See the full Unincorporated Emery County inspection guide — scheduling & re-inspection fees →
Tips
- Inspections are scheduled by calling Katrina at Sunrise Engineering, 1-800-560-6151 — the county contracts inspection services to Sunrise Engineering. A minimum of 24 business hours' notice is required for all inspections.
- Outside city limits, a lot must be at least 10 acres (or part of a qualifying 2-acre minor subdivision recorded in the applicant's name) before a building permit will even be accepted — confirm eligibility with the Zoning Administrator before starting the application.
- The Building Permit Point System worksheet must total exactly 1000 points; qualifying categories include proximity to an incorporated town/city, distance from an improved road, lot acreage (50 pts minimum for 10 acres, up to 200 pts max at 40 acres), culinary water service type, electrical grid access, sewage disposal type, and dwelling square footage.
- All application documents must be emailed together to building@emery.utah.gov.
- Permits become null and void if work is not commenced within 180 days of issuance, or if work is suspended/abandoned for 180 days after commencement.
- An Emery Telcom Fiber Optic Service Request must be initiated during the construction phase — installing communications conduit after construction can incur significant added cost to the owner.
- For inside-city-limits construction (Castle Dale, Clawson, Cleveland, Elmo, Emery, Ferron, Green River, Huntington, Orangeville), applicants must contact the respective city hall for that city's own requirements — this file covers unincorporated land only.
- Rooftop or ground-mounted solar PV installations fall under this same Residential Building Permit process — the Emery County Building Permit Requirements page (emery.utah.gov/home/department-directory/bz/building-permit/) lists 'Electrical work' among the categories requiring a permit, but the county does not publish a distinct solar-specific fee line or process separate from the general valuation-based building permit described here.
- EV charger / EVSE installation is not itemized separately anywhere in Emery County's Outside-City-Limits Building Permit packet or its Building Permit Requirements page (re-checked 2026-07-20) — a full-text review found no 'EV,' 'electric vehicle,' or 'charging station' entry. Like solar (above), 'Electrical work' is the only related category the county lists as requiring a permit, so an EV charging circuit would be expected to fall under this same general valuation-based Building Permit process rather than a distinct fee line.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Emery County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Emery County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Emery County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Emery County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →