Residential Building Permit in Cedar Hills, Utah
Required for all new residential construction in Cedar Hills, regulated by the adopted 2021 IRC / 2024 IBC (per Utah Code § 15A-2-103, effective 7/1/2026 — Cedar Hills' own Building Permit Requirements form has not yet been updated to reflect the 2024 IBC as of 2026-07-16). The city's fee schedule charges a valuation-based Building Permit fee (no separate printed dollar table; assessed 'Based on valuation' per the International Building Code, i.e. IBC Section 109 / ICC Building Valuation Data methodology) plus a mandatory Residential Plan Check fee (65% of the building permit fee) and a tiered, square-footage-based Plan Check Deposit due at application. Cedar Hills' Master Fee Schedule lists a 'Temporary Power & Permanent Power Inspection (Residential)' fee of $65.00 and a separate 'Electrical Permit (Commercial)' fee category, both collected as part of the Building Permit, but no distinct EV charger/EVSE line item was found as of 2026-07-19 — a standalone home EV charger circuit would fall under the standard Temporary/Permanent Power Inspection fee rather than a dedicated EV charge.
Verified 2026-07-08 · Source
When you need this permit
- New single-family residential construction regulated by the adopted 2021 IRC / 2024 IBC (per Utah Code § 15A-2-103, effective 7/1/2026)
- Completed Building Permit Application (submitted via the online iworq permit portal or by print application)
- 2 sets of building plans drawn to scale, including a site plan (north arrow, lot dimensions, setbacks, easements, property lines, water meter/sewer lateral location, driveway/hard-surface locations, retaining walls, and topographical details if slope exceeds 10%)
- Construction plans: floor plans, footing/foundation details, structural framing, electrical/mechanical/plumbing design details, energy code compliance documentation (RES Check, COMM Check, Manual D/J/S as applicable)
- Structural calculations stamped by a Utah-licensed structural engineer (roof trusses may be a deferred submittal)
- Geotechnical report, including slope stability evaluation and retaining wall design, if lot slope exceeds 15%
- HOA approval if applicable
- Plan Check Deposit, based on gross square footage and/or valuation, due at application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building, Electrical, Mechanical & Plumbing
All inspections are performed by Sunrise Engineering under contract to the City of Cedar Hills (inspection services are contracted; permit issuance, plan review, and administration remain with the city's own Building Department). Scheduled by phone at 800-560-6151; 24 hours' notice required, no same-day inspections. Caller must have the permit number, site address, and inspection type ready.
- 2
Final Inspection (New Construction)
Governed by the city's official Final Inspection Checklist (new construction), downloadable from the Building Department page.
See the full Cedar Hills inspection guide — scheduling & re-inspection fees →
Tips
- Cedar Hills' Building Department is staffed directly by the city (Building Assistant / Zoning-Code Enforcement Officer Sarah Sampson, ext. 204) — it is not contracted to Utah County. Only field inspections are contracted out, to Sunrise Engineering.
- The Building Permit fee itself has no printed flat-dollar or per-square-foot table on Cedar Hills' fee schedule; it is assessed 'Based on valuation' per the adopted IBC. Applicants should confirm the specific valuation methodology (e.g. ICC Building Valuation Data table) directly with the Building Department at application.
- A Plan Check Deposit (tiered $300–$3,900 by gross square footage) is required for all construction except basement finishes, due at application — separate from and in addition to the building permit and plan check fees.
- Sunrise Engineering requires 24 hours' notice for inspections; no same-day inspections are available.
- The Owner/Builder path is available (write 'Owner/Builder' in the contractor field) but requires filing the state DOPL Owner/Builder Certification form with the city. Owner-builder
- Cedar Hills' Master Fee Schedule (fetched via 5il.co/34m6a) has no distinct EV charger/EVSE fee category as of 2026-07-19; a standalone charger install falls under the standard $65.00 Temporary & Permanent Power Inspection fee that also covers other residential electrical hookups.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cedar Hills building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Cedar Hills
Residential Building Permit in other cities
Compare residential building permit fees across Utah →