Residential Building Permit — Bountiful, Utah · Requirements sheet
Verified 2026-07-01 · Source: https://www.bountifulutah.gov/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit in Bountiful, Utah
Required for new residential construction, additions, structural alterations, and work requiring plan review in Bountiful, governed by the 2021 IRC. All permits are applied for through the Cityinspect online portal.
Verified 2026-07-01 · Source
When you need this permit
- New single-family, duplex, or townhome construction
- Additions requiring structural work
- Structural modifications — load-bearing wall removal, foundation alterations
- Conversion of non-habitable space to habitable space
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
See the full Bountiful inspection guide — scheduling & re-inspection fees →
Tips
- Bountiful operates on a 4-day work week (Mon–Thu only). If you want a Friday inspection, request it by the prior Tuesday — the city will adjust the inspector's schedule. (Building Inspection Policy, rev. Aug 19, 2024)
- By Utah law (UCA 10-6-160), if Bountiful cannot provide an inspection within 3 business days, you may use authorized third-party firms: WC-3 Code Consultants (801) 547-8133, North Salt Lake City Building Dept (801) 335-8721, or Farmington City Building Dept (801) 939-9214. Notify the city first.
- Seismic Zone: D2. Frost depth: 30 inches. Design wind speed: 140 mph (Vasd=108 mph), Exposure Category B. (Bountiful Design Criteria, rev. Oct 13, 2025)
- Building Official: Don Simons, (801) 660-8105 cell / (801) 298-6128 direct / Don@Bountiful.gov.
- Sign permits are not a separate fee line in Bountiful City — the Planning Fees table in Ordinance 2023-01 (Schedule of Rates and Fees, FY2023-2024, eff. May 9, 2023) lists 'Sign Permit' with the note 'See Engineering Dept. Fees (building permits)', meaning signs are permitted and priced through this same Building Permit fee structure rather than a distinct sign fee. Sign design/placement standards are still separately regulated under City Code Chapter 19 (Sign Regulations, Ord 2020.01), which requires a sign permit from the Planning Department (§ 14-19-118) before erecting, installing, or painting any sign.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bountiful
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →