Basement Finish Permit — Bountiful, Utah · Requirements sheet
Verified 2026-07-01 · Source: https://www.bountifulutah.gov/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Basement Finish Permit in Bountiful, Utah
Required for finishing or remodeling an unfinished basement in Bountiful, including framing, electrical, plumbing, and mechanical work. Governed by the 2021 IRC. Apply through Cityinspect.
Verified 2026-07-01 · Source
When you need this permit
- Framing walls in an unfinished basement
- Adding a bedroom (requires egress window per IRC R310)
- Adding a bathroom (requires separate plumbing permit)
- Electrical wiring for new rooms
- Any structural modifications
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing
Wall framing, fire blocking, egress window openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
See the full Bountiful inspection guide — scheduling & re-inspection fees →
Tips
- Every basement bedroom in Bountiful requires an egress window — minimum 5.7 sq ft clear opening, sill height no more than 44 inches above floor per 2021 IRC R310.
- Window wells deeper than 44 inches require a permanently attached ladder or steps.
- The furnace/water heater room needs combustion air — do not fully enclose it without adequate air supply.
- Smoke detectors required in every bedroom, outside sleeping areas, and on every level.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bountiful
Basement Finish Permit in other cities
Compare basement finish permit fees across Utah →
Look up this fee in a different city →