Roofing Permit in Bountiful, Utah
Required for roof replacement, re-roofing, and structural roof repairs in Bountiful. The Reroof & Roof Repair Policy (revised March 31, 2025) governs all roofing work under the 2021 IRC. Apply through Cityinspect.
Verified 2026-07-17 · Source
When you need this permit
- Complete roof replacement (tear-off and re-roof) — all layers must be removed per IRC R908.3
- Roof recover (overlay) — permitted only where IRC R908.3.1 conditions are met; maximum two total layers
- Structural roof repairs or modifications
- Roof repairs over 20% of one roof surface or over 10% of total roof area require a permit; minor repairs below these thresholds do not (Reroof Policy)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Deck / Substrate
After tear-off — verify sheathing condition; structurally unsound decking must be repaired before new roofing. Bountiful (Seismic Zone D2): spaced lumber sheathing must be covered with 7/16" min plywood/OSB overlay.
- 2
Final
Completed roof — verify ice barrier at valleys/eaves, drip edge, flashing, and nailing per manufacturer instructions
See the full Bountiful inspection guide — scheduling & re-inspection fees →
Tips
- Bountiful Reroof Policy (revised March 31, 2025): roof recover (overlay) is only permitted where two or fewer total layers exist; if two layers already exist, full tear-off is required.
- Bountiful is in Seismic Zone D2 — spaced lumber sheathing decks must be covered with 7/16" min plywood/OSB before re-roofing (Reroof Policy, rev. March 31, 2025).
- Ice barriers are required per 2021 IRC R905.1.2/R905.2.8.5; drip edge is required per R905.2.8.5.
- Roof repairs under 20% of one surface or under 10% of total roof area do not require a permit (Reroof Policy). Call (801) 298-6125 to confirm.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-17.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bountiful
Roofing Permit in other cities
Compare roofing permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Bountiful project checklist
Describe your project once and get every permit, document, and fee it triggers in Bountiful — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →