Roofing Permit — Draper, Utah · Requirements sheet
Verified 2026-07-13 · Source: https://www.draperutah.gov/business-development/building-and-renovating/building-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Roofing Permit in Draper, Utah
Required for roof replacement and re-roofing in Draper. Listed as 'Re-Roof' in Draper's Online Services Portal. Fees are valuation-based under the ICC Schedule per Resolution 26-29.
Verified 2026-07-13 · Source
When you need this permit
- Complete roof replacement (tear-off and re-roof)
- Overlay of new roofing over existing (where code allows — max two layers)
- Structural roof repairs or modifications
- Changes to roofing material type
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Assessed on project valuation per Draper's building permit fee schedule: Draper Consolidated Fee Schedule, Resolution 26-29 (Jul 2026), item 44. Show full citationHide
Assessed on project valuation per Draper's building permit fee schedule: Draper Consolidated Fee Schedule, Resolution 26-29 (Jul 2026), item 44. Resolution 26-29 superseded Resolution 25-52 (Oct 2025) at the same media URL, with identical fee figures. Re-Roof is a distinct permit type in Draper's Online Services Portal but is billed as a Building Permit (100% ICC Schedule), per Draper's published Applications/Licenses/Permits type list.Review timeline
Inspection process
- 1
Deck / Substrate
After tear-off — verify sheathing condition, replace damaged decking before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
See the full Draper inspection guide — scheduling & re-inspection fees →
Tips
- Draper's permit portal lists 'Re-Roof' as a separate permit category — apply through the Online Services Portal at draper.onlama.com.
- The adopted 2021 IRC governs roofing material and installation requirements.
- Ice and water shield is required in valleys and at eaves per the adopted IRC.
- A maximum of two roofing layers is permitted; full tear-off is required if two layers already exist.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Draper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Draper's permit history is searchable by address
8,134 permits in our copy of Draper's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Draper has issued.
None of Draper's records carry an issued date, so this history cannot be filtered or sorted by date. The permits are here and searchable by address — but “when” is not a question they can answer.
Other permits in Draper
Roofing Permit in other cities
Compare roofing permit fees across Utah →
Look up this fee in a different city →