Roofing Permit (Reroof / Roof Recover) in Farmington, Utah

Required for residential re-roof or roof recover in Farmington City, governed by the Reroof & Roof Repair Policy (effective July 1, 2024), which cites 2021 IBC/IEBC/IRC; IBC and IEBC are now 2024 statewide per Utah Code § 15A-2-103(1)(a)/(i) effective 7/1/2026 (the City policy document itself has not been updated), while IRC remains 2021 per § 15A-2-103(1)(b). Minor repairs under specified thresholds do not require a permit.

Verified 2026-07-03 · Source

When you need this permit

  • Full roof replacement (tear-off of all existing layers)
  • Roof recover (overlay), permitted only where the existing roof covering is not water-soaked, is not slate/clay/cement/asbestos-cement tile, and has fewer than two existing layers
  • Repairs exceeding 20% of one roof surface or 10% of total roof area require a permit; smaller repairs do not

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Reroof/Recover PermitFarmington City Reroof & Roof Repair Policy, effective July 1, 2024, page 2; matches the flat-rate 'Solar' line item cross-reference in the Consolidated Fee Schedule (adopted 2026-05-19), Section C, Miscellaneous Residential Building Permit Fees table, which separately lists a $378.01 Solar flat rate distinct from roofing
$111.10 ($110.00 permit + $1.10 state fee)
Commercial Re-Roof PermitFarmington City Reroof & Roof Repair Policy, effective July 1, 2024, page 2
Valuation-based per City and State standards

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit (Reroof / Roof Recover) permit actually take in Farmington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Sheathing

    For a recover, the existing roof is inspected; ensures the roof surface is smooth with proper fastening and spacing of solid sheathing, and crickets installed if needed

  2. 2

    Ice Barrier

    Proper placement of ice barrier per 2021 IRC R905.1.2/R905.2.8.5

  3. 3

    Final

    Confirms roof was installed properly with all required vents, flashings, and drip edges

See the full Farmington inspection guide — scheduling & re-inspection fees →

Tips

  • Farmington is in Seismic Design Category D2 — existing spaced-lumber (plank) roof decks MUST be overlaid with minimum 7/16" plywood or OSB sheathing, properly fastened with finished gaps under 1/4 inch, before new roofing is installed (Reroof & Roof Repair Policy, eff. July 1, 2024).
  • Roof recover is NOT permitted where the existing roof is water-soaked/deteriorated, is slate/clay/cement/asbestos-cement tile, or already has two or more layers of roof covering — full tear-off and replacement is required in those cases.
  • Residential roof repairs limited to less than 20% of one roof surface or less than 10% of the total roof area do NOT require a permit from the City, per the Reroof & Roof Repair Policy.
  • Commercial reroofs (depending on scope) ARE subject to seismic and parapet strengthening requirements under the IEBC and applicable Utah State Building Code amendments.

Frequently asked questions

Yes, for a full reroof or roof recover — the fee is $111.10 ($110 permit + $1.10 state fee), issued over the counter by appointment (call 801-882-8954). Repairs under 20% of one roof surface or 10% of total roof area do not require a permit. (Reroof & Roof Repair Policy, effective July 1, 2024)

In Farmington, the published Residential Reroof/Recover Permit is: $111.10 ($110.00 permit + $1.10 state fee). Additional published fees: Commercial Re-Roof Permit — Valuation-based per City and State standards. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Farmington does not publish a plan-review timeline for this permit. Contact Farmington City Building Department at (801) 451-2383 for current turnaround.

You'll need: Over-the-Counter Permit Application. See the required-documents checklist on this page for details on each.

Farmington requires 3 inspection(s) for a roofing permit (reroof / roof recover), in order: Sheathing, Ice Barrier, Final. Schedule each through Farmington City Building Department ((801) 451-2383).

Apply through Farmington City Building Department at 160 S. Main St. / P.O. Box 160, Farmington, UT 84025-0160. Phone: (801) 451-2383. Office hours: Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 12:00 PM (Residential Building Permit Application Packet, H. Gordon rev. 4.24.2020). Official information: https://farmington.utah.gov/building-department/.

Farmington, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition previously used in Farmington City's design criteria (Residential Building Permit Application Packet, H. Gordon, rev. 4.24.2020, which had not been updated as of 2026-07-16); 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment. Farmington City design criteria (rev. 4.24.2020) and the Reroof & Roof Repair Policy (eff. July 1, 2024) are consistent with this; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in Farmington's own published materials, added here per statute; 2024 International Existing Building Code (IEBC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(i); supersedes the 2021 edition cited in Farmington's Reroof & Roof Repair Policy (eff. July 1, 2024), Sections 705 and 706, which had not been updated as of 2026-07-16; 2021 International Property Maintenance Code (IPMC) — cited in Reroof & Roof Repair Policy (eff. July 1, 2024), Sections 304.1, 304.7, 507; the IPMC is NOT among the codes adopted by Utah Code § 15A-2-103 (property-maintenance code, not a construction code), so no statewide edition change applies here — left as published by the City; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103(1)(f); not separately itemized in Farmington's own published design-criteria packet (rev. 4.24.2020), added here per statute since the City's own materials omit it; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 amendment. Farmington City design criteria (rev. 4.24.2020) already correctly reflects 2023; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Farmington City's own published design-criteria packet (Residential Building Permit Application Packet, rev. 4.24.2020) and Reroof & Roof Repair Policy (eff. July 1, 2024) still reference 2021 editions for IBC/IEBC and had not been updated to reflect the 7/1/2026 transition as of this re-verification; this file now states the governing statutory code (2024 editions) as current per Utah's statewide-mandatory code regime (Utah Code § 15A-1-204), with the City's un-updated 2021 references preserved above as historical/local-document context. The Utah Code § 15A-2-103 citation in the sources array below has been updated to the current in-force version link. Local amendments apply — see the Farmington overview page for the full list.

Only if the existing roof has fewer than two layers, is not water-soaked or deteriorated, and is not slate/clay/cement/asbestos-cement tile. Existing spaced-lumber decks must first be overlaid with 7/16" min. plywood/OSB due to Farmington's Seismic Design Category D2. Otherwise, full tear-off and replacement is required. (Reroof & Roof Repair Policy, eff. July 1, 2024)

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.