Commercial Tenant Improvement / Tenant Finish Permit in Farmington, Utah

Required for interior tenant-finish and remodel work within an existing commercial building in Farmington City. Farmington's Consolidated Fee Schedule does not publish a separate, discounted fee table for tenant improvement/tenant finish work — the same valuation-based Building Permit Fee formula, the 65% commercial Plan Check Fee, and the $250 commercial Plan Review Deposit apply as for new commercial construction, with valuation computed from the applicable occupancy group's per-square-foot rate in the Building Valuation Data table.

Verified 2026-07-19 · Source

When you need this permit

  • Interior tenant-finish or remodel work within an existing commercial building
  • Two complete plan sets, engineer-stamped where structural work is involved
  • Site Plan Application review only if exterior/site changes are part of the scope (interior-only tenant finish typically does not trigger this)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review Deposit — CommercialFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section C1: 'Plan Review Deposit ... Commercial — $250.00.' PDF verified directly 2026-07-19. The fee schedule does not publish a separately lower tenant-improvement deposit.
$250.00
Building Permit Fee (1997 UBC Table No. 1-A, valuation-based)Farmington City Consolidated Fee Schedule, adopted 2026-05-19, Table No. 1-A; PDF verified directly 2026-07-19. No separate, lower valuation table is published for tenant-improvement/remodel work — valuation is derived the same way, from the Building Valuation Data per-square-foot table for the applicable occupancy group.
Same tiered table as new commercial construction — e.g., $5,608.75 plus $3.65 per additional $1,000 over $1,000,000
Plan Check Fee — CommercialFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section C2 and Table No. 1-A note: 'Commercial plan check fees are 65% of building fee.' PDF verified directly 2026-07-19 — this is the same rate that applies to new commercial construction; the schedule does not carve out a discounted plan-check percentage for tenant-improvement work (unlike, for example, Clinton City's separate 0.35 tenant-finish multiplier).
65% of the building application permit fee
State Inspection FeeFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section C3.
1% of building application fee
Second/Additional Plan Review (after redlined resubmission without corrections, or major changes)Farmington City Consolidated Fee Schedule, adopted 2026-05-19, Table No. 1-A, item 4: 'Additional plan review required with changes, additions or revisions to plans ... $55.55/hr*.' Also applies to tenant-finish resubmittals.
$55.55/hour

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Farmington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Structural (if applicable)

    Interior wall framing and structural connections verified before close-in, where the scope includes structural work.

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in for the tenant space, inspected before walls closed.

  3. 3

    Fire / Life Safety (if applicable)

    Fire sprinkler/alarm modifications inspected where required by the adopted IBC/IFC.

  4. 4

    Final

    All tenant-finish or remodel work complete before occupancy.

See the full Farmington inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike some neighboring Davis County cities (e.g., Clinton City's 0.35 Commercial Tenant Finish permit-fee multiplier), Farmington does not publish a discounted fee schedule for tenant-improvement work — the full 65% commercial plan check rate and the same valuation-based building fee table apply as for new commercial construction.
  • Tenant-finish valuation is computed from the Building Valuation Data table's per-square-foot rate for the applicable IBC occupancy group (e.g., Group M Mercantile, Group B Business) — confirm the correct occupancy classification with the Building Department before estimating costs.
  • If a redlined plan resubmission doesn't address required corrections, or involves major changes, an additional $55.55/hour plan review fee applies — same as for new construction.

Frequently asked questions

Farmington requires a commercial tenant improvement / tenant finish permit for: Interior tenant-finish or remodel work within an existing commercial building; Two complete plan sets, engineer-stamped where structural work is involved; Site Plan Application review only if exterior/site changes are part of the scope (interior-only tenant finish typically does not trigger this). If your project isn't listed, confirm with Farmington City Building Department at (801) 451-2383 before starting work.

Farmington charges tenant-improvement/tenant-finish work the same way as new commercial construction: a valuation-based Building Permit Fee (1997 UBC Table No. 1-A, using the Building Valuation Data per-square-foot table for the applicable occupancy group), a 65% commercial Plan Check Fee, a $250 Plan Review Deposit, and a 1% State Inspection Fee. No separate, lower tenant-improvement fee table is published.

Farmington does not publish a plan-review timeline for this permit. Contact Farmington City Building Department at (801) 451-2383 for current turnaround.

You'll need: Building Permit Application; Construction Plans; $250 Commercial Plan Check Deposit. See the required-documents checklist on this page for details on each.

Farmington requires 4 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Structural (if applicable), MEP Rough-In, Fire / Life Safety (if applicable), Final. Schedule each through Farmington City Building Department ((801) 451-2383).

Apply through Farmington City Building Department at 160 S. Main St. / P.O. Box 160, Farmington, UT 84025-0160. Phone: (801) 451-2383. Office hours: Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 12:00 PM (Residential Building Permit Application Packet, H. Gordon rev. 4.24.2020). Official information: https://farmington.utah.gov/building-department/.

Farmington, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition previously used in Farmington City's design criteria (Residential Building Permit Application Packet, H. Gordon, rev. 4.24.2020, which had not been updated as of 2026-07-16); 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment. Farmington City design criteria (rev. 4.24.2020) and the Reroof & Roof Repair Policy (eff. July 1, 2024) are consistent with this; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in Farmington's own published materials, added here per statute; 2024 International Existing Building Code (IEBC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(i); supersedes the 2021 edition cited in Farmington's Reroof & Roof Repair Policy (eff. July 1, 2024), Sections 705 and 706, which had not been updated as of 2026-07-16; 2021 International Property Maintenance Code (IPMC) — cited in Reroof & Roof Repair Policy (eff. July 1, 2024), Sections 304.1, 304.7, 507; the IPMC is NOT among the codes adopted by Utah Code § 15A-2-103 (property-maintenance code, not a construction code), so no statewide edition change applies here — left as published by the City; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103(1)(f); not separately itemized in Farmington's own published design-criteria packet (rev. 4.24.2020), added here per statute since the City's own materials omit it; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 amendment. Farmington City design criteria (rev. 4.24.2020) already correctly reflects 2023; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Farmington City's own published design-criteria packet (Residential Building Permit Application Packet, rev. 4.24.2020) and Reroof & Roof Repair Policy (eff. July 1, 2024) still reference 2021 editions for IBC/IEBC and had not been updated to reflect the 7/1/2026 transition as of this re-verification; this file now states the governing statutory code (2024 editions) as current per Utah's statewide-mandatory code regime (Utah Code § 15A-1-204), with the City's un-updated 2021 references preserved above as historical/local-document context. The Utah Code § 15A-2-103 citation in the sources array below has been updated to the current in-force version link. Local amendments apply — see the Farmington overview page for the full list.

No. Farmington's Consolidated Fee Schedule applies the same 65% commercial plan-check rate and valuation-based fee table to both. This differs from some neighboring Davis County cities that publish a separately discounted tenant-finish multiplier.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Farmington.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.