Commercial Tenant Improvement / Tenant Finish Permit — Farmington, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://farmington.utah.gov/wp-content/uploads/2026/05/CFS-as-adopted-on-2026-05-19.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement / Tenant Finish Permit in Farmington, Utah
Required for interior tenant-finish and remodel work within an existing commercial building in Farmington City. Farmington's Consolidated Fee Schedule does not publish a separate, discounted fee table for tenant improvement/tenant finish work — the same valuation-based Building Permit Fee formula, the 65% commercial Plan Check Fee, and the $250 commercial Plan Review Deposit apply as for new commercial construction, with valuation computed from the applicable occupancy group's per-square-foot rate in the Building Valuation Data table.
Verified 2026-07-19 · Source
When you need this permit
- Interior tenant-finish or remodel work within an existing commercial building
- Two complete plan sets, engineer-stamped where structural work is involved
- Site Plan Application review only if exterior/site changes are part of the scope (interior-only tenant finish typically does not trigger this)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing / Structural (if applicable)
Interior wall framing and structural connections verified before close-in, where the scope includes structural work.
- 2
MEP Rough-In
Electrical, plumbing, and mechanical rough-in for the tenant space, inspected before walls closed.
- 3
Fire / Life Safety (if applicable)
Fire sprinkler/alarm modifications inspected where required by the adopted IBC/IFC.
- 4
Final
All tenant-finish or remodel work complete before occupancy.
See the full Farmington inspection guide — scheduling & re-inspection fees →
Tips
- Unlike some neighboring Davis County cities (e.g., Clinton City's 0.35 Commercial Tenant Finish permit-fee multiplier), Farmington does not publish a discounted fee schedule for tenant-improvement work — the full 65% commercial plan check rate and the same valuation-based building fee table apply as for new commercial construction.
- Tenant-finish valuation is computed from the Building Valuation Data table's per-square-foot rate for the applicable IBC occupancy group (e.g., Group M Mercantile, Group B Business) — confirm the correct occupancy classification with the Building Department before estimating costs.
- If a redlined plan resubmission doesn't address required corrections, or involves major changes, an additional $55.55/hour plan review fee applies — same as for new construction.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Farmington.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Farmington
Commercial Tenant Improvement / Tenant Finish Permit in other cities
Compare commercial tenant improvement / tenant finish permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Farmington project checklist
Describe your project once and get every permit, document, and fee it triggers in Farmington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →