Commercial Building Permit in Farmington, Utah

Required for new commercial building construction in Farmington City, governed by the 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 2026-07-01, superseding the 2021 edition previously used in the City's design criteria). The building permit fee is valuation-based (1997 UBC Table No. 1-A, same table used for residential), with valuation derived from the City's own per-square-foot Building Valuation Data table by occupancy group and construction type; commercial plan check is a flat 65% of the building fee, versus 40% for residential — and shell-only buildings get a 20% valuation deduction.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial building construction (ground-up or shell)
  • Two complete plan sets, engineer-stamped, with structural calculations
  • Site Plan Application review by Planning Commission for Commercial, Industrial, or Apartment Dwelling Group projects, tiered by acreage
  • SPARC (Site Plan and Architectural Review Committee) Review
  • Excavation Permit from Public Works prior to building permit issuance

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review Deposit — CommercialFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section C1: 'Plan Review Deposit ... Commercial — $250.00' (versus $75.00 for Residential). PDF verified directly 2026-07-19.
$250.00
Building Permit Fee (1997 UBC Table No. 1-A, valuation-based)Farmington City Consolidated Fee Schedule, adopted 2026-05-19, Table No. 1-A (1997 Uniform Building Code); PDF verified directly 2026-07-19. Same table as residential — commercial valuation is computed from the City's own Building Valuation Data table (per-square-foot cost by IBC occupancy group and construction type, e.g., Group B (Business) ranges from $105.37/sq ft (Type VB) to $166.52/sq ft (Type IA)).
$1.00–$500: $23.00. $501–$2,000: $23.50 + $3.05 per additional $100. $2,001–$25,000: $69.25 + $14.00 per additional $1,000. $25,001–$50,000: $391.75 + $10.10 per additional $1,000. $50,001–$100,000: $643.75 + $7.00 per additional $1,000. $100,001–$500,000: $993.75 + $5.60 per additional $1,000. $500,001–$1,000,000: $3,233.75 + $4.75 per additional $1,000. Over $1,000,000: $5,608.75 + $3.65 per additional $1,000.
Plan Check Fee — CommercialFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section C2 and Table No. 1-A note: 'Commercial plan check fees are 65% of building fee' (versus 40% for Residential). PDF verified directly 2026-07-19.
65% of the building application permit fee
State Inspection FeeFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section C3.
1% of building application fee
Shell-Only Building Valuation DeductionFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Building Valuation Data table footnote: 'For shell only building deduct 20%.' PDF verified directly 2026-07-19.
20% deduction from Building Valuation Data table cost per sq ft
Site Plan Application — Commercial, Industrial, or Apartment Dwelling GroupFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Section A4; PDF verified directly 2026-07-19. Plus SPARC Review $250.00 and an Engineering and Professional Service Fee Initial & Quarterly Deposit of $500.00.
$650.00 first acre or portion thereof, plus $500.00/acre for acres 2–4, plus $350.00/acre for each acre over 4
Water Impact Fee — Commercial (per Equivalent Residential Connection)Farmington City Consolidated Fee Schedule, adopted 2026-05-19, Water Impact Fees table: 'Commercial / ERC — $4,263.00.' Collected at Building Permit.
$4,263.00 (minimum; one ERC = 24 Drainage Fixture Units)
Combined Impact Fees — Commercial (per 1,000 sq ft): Storm Water Drainage, Fire Facilities, Fire Equipment, Police Capital FacilitiesFarmington City Consolidated Fee Schedule, adopted 2026-05-19, Impact Fees table (other than Transportation and Water); PDF verified directly 2026-07-19. No Parks & Recreation impact fee applies to Commercial (dash in that column).
$2,376.71 storm water + $1,250.00 fire facilities + $130.00 fire equipment + $1,020.00 police capital facilities = $4,776.71 per 1,000 sq ft
Transportation Impact Fee — Commercial (examples, per 1,000 sq ft unless noted)Farmington City Consolidated Fee Schedule, adopted 2026-05-19, Transportation Impact Fee table (Cost per Average Daily Trip $509.41 x use-specific Adjusted Trip Rate); PDF verified directly 2026-07-19. Collected at Building Permit.
General Office Building $2,480.83; Business Park $3,168.53; Shopping Center/Strip Mall $6,347.25; Restaurant, Sit-Down $16,285.84; Fast Food w/o Drive-Through $50,268.58 (varies extensively by specific commercial use type — full table has 25+ categories)

Review timeline

Plan reviewTypical estimate — confirm current times with the Farmington building department
~14–28 business days

How long did your Commercial Building Permit permit actually take in Farmington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.

  2. 2

    Underground Plumbing

    Underground plumbing lines before slab pour.

  3. 3

    4-Way (Framing/Electrical/Plumbing/Mechanical Rough-In)

    Building enclosed, structural members still exposed, rough-in for heating, plumbing, and electrical work in place and visible.

  4. 4

    Fire / Life Safety

    Fire sprinkler/alarm systems inspected where required by the adopted IBC/IFC.

  5. 5

    Final

    All work complete; a final inspection is required or the permit becomes non-compliant.

See the full Farmington inspection guide — scheduling & re-inspection fees →

Tips

  • Farmington computes commercial building valuation from its own per-square-foot Building Valuation Data table (by 2006 IBC occupancy group and construction type), then runs that valuation through the same Table No. 1-A fee formula used for residential — commercial's discount comes from the higher-percentage plan check (65% vs. 40%), not a different base fee table.
  • Shell-only commercial buildings get a 20% deduction off the Building Valuation Data per-square-foot cost before the building fee is calculated.
  • Commercial/Industrial/Apartment Dwelling Group Site Plan Applications are reviewed separately by the Planning Commission, with fees tiered by acreage ($650 first acre, stepping down to $350/acre over 4 acres), plus a $250 SPARC Review fee and a $500 engineering deposit — this is on top of, not instead of, the Building Department's permit fees.
  • Transportation impact fees vary enormously by specific commercial use — a fast-food restaurant with a drive-through ($50,268.58/1,000 sq ft) costs roughly 20x a general office building ($2,480.83/1,000 sq ft) due to different trip-generation rates.

Frequently asked questions

Farmington requires a commercial building permit for: New commercial building construction (ground-up or shell); Two complete plan sets, engineer-stamped, with structural calculations; Site Plan Application review by Planning Commission for Commercial, Industrial, or Apartment Dwelling Group projects, tiered by acreage; SPARC (Site Plan and Architectural Review Committee) Review; Excavation Permit from Public Works prior to building permit issuance. If your project isn't listed, confirm with Farmington City Building Department at (801) 451-2383 before starting work.

Farmington does not provide advance fee estimates. The base Building Permit Fee follows the 1997 UBC Table No. 1-A, with valuation computed from the City's own per-square-foot Building Valuation Data table by occupancy/construction type. Commercial plan check is 65% of the building fee (vs. 40% residential), plus a $250 plan review deposit, 1% state fee, a Water Impact Fee of $4,263/ERC, combined impact fees of $4,776.71 per 1,000 sq ft (storm water, fire, police), and a use-specific transportation impact fee. Site Plan Application review by the Planning Commission is billed separately, starting at $650 for the first acre.

Farmington's published '3 to 4 weeks' plan-check estimate is stated in the residential application packet, not a commercial-specific document — no verified commercial-specific turnaround figure is published. Commercial projects also require separate Planning Commission Site Plan and SPARC review, which can extend the overall timeline. Call (801) 451-2383 for a current estimate.

You'll need: Building Permit Application; Site Plan Application (Commercial, Industrial, or Apartment Dwelling Group); Two Complete Plan Sets, Engineer-Stamped; $250 Commercial Plan Check Deposit. See the required-documents checklist on this page for details on each.

Farmington requires 5 inspection(s) for a commercial building permit, in order: Foundation / Footing, Underground Plumbing, 4-Way (Framing/Electrical/Plumbing/Mechanical Rough-In), Fire / Life Safety, Final. Schedule each through Farmington City Building Department ((801) 451-2383).

Apply through Farmington City Building Department at 160 S. Main St. / P.O. Box 160, Farmington, UT 84025-0160. Phone: (801) 451-2383. Office hours: Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 12:00 PM (Residential Building Permit Application Packet, H. Gordon rev. 4.24.2020). Official information: https://farmington.utah.gov/building-department/.

Farmington, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition previously used in Farmington City's design criteria (Residential Building Permit Application Packet, H. Gordon, rev. 4.24.2020, which had not been updated as of 2026-07-16); 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment. Farmington City design criteria (rev. 4.24.2020) and the Reroof & Roof Repair Policy (eff. July 1, 2024) are consistent with this; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in Farmington's own published materials, added here per statute; 2024 International Existing Building Code (IEBC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(i); supersedes the 2021 edition cited in Farmington's Reroof & Roof Repair Policy (eff. July 1, 2024), Sections 705 and 706, which had not been updated as of 2026-07-16; 2021 International Property Maintenance Code (IPMC) — cited in Reroof & Roof Repair Policy (eff. July 1, 2024), Sections 304.1, 304.7, 507; the IPMC is NOT among the codes adopted by Utah Code § 15A-2-103 (property-maintenance code, not a construction code), so no statewide edition change applies here — left as published by the City; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103(1)(f); not separately itemized in Farmington's own published design-criteria packet (rev. 4.24.2020), added here per statute since the City's own materials omit it; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); supersedes the 2021 edition previously used in Farmington's design criteria (rev. 4.24.2020, not updated as of 2026-07-16); 2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 amendment. Farmington City design criteria (rev. 4.24.2020) already correctly reflects 2023; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Farmington City's own published design-criteria packet (Residential Building Permit Application Packet, rev. 4.24.2020) and Reroof & Roof Repair Policy (eff. July 1, 2024) still reference 2021 editions for IBC/IEBC and had not been updated to reflect the 7/1/2026 transition as of this re-verification; this file now states the governing statutory code (2024 editions) as current per Utah's statewide-mandatory code regime (Utah Code § 15A-1-204), with the City's un-updated 2021 references preserved above as historical/local-document context. The Utah Code § 15A-2-103 citation in the sources array below has been updated to the current in-force version link. Local amendments apply — see the Farmington overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter