Certificate of Occupancy (Change of Use / Occupancy) in Farmington, Utah
Farmington City Code requires a Certificate of Occupancy signed by BOTH the Zoning Administrator and the Building Official before any land or building may be changed in use or occupancy -- this applies even when no structural alteration is involved, not only at the end of new construction. Per City Code section 11-4-050.C (Duties of the Zoning Administrator): 'No land shall be changed in use or occupancy and no building shall be changed in use or structurally altered until a certificate of occupancy shall have been issued by both the zoning administrator and the building official,' and 'a certificate of occupancy shall be required for the purpose of maintaining, renewing, changing or extending a nonconforming use.' Separately, City Code section 11-8-090 requires that a building permit for any building/structure needing a Conditional Use Permit cannot be issued until the Planning Commission approves the conditional use permit -- a related, but distinct, requirement about building permits rather than certificates of occupancy specifically (11-8-090's text does not itself use the word 'certificate'). No fee line item labeled specifically 'Certificate of Occupancy' or 'Change of Use' was found in the city's Consolidated Fee Schedule (adopted 2026-05-19); the closest related published fees are the Land Use Related Fees for Administrative Determination and Conditional Use Application described below, which apply only when the new use requires a zoning classification determination or falls under the nonconforming-use/conditional-use provisions. Re-chased 2026-07-20: located and reviewed Farmington City Code Title 10, Chapter 5 ('Certificates') in full -- Section 10-5-030 (Issuance of Certificate: the Building Official issues a CO after final inspection finds no code violations, with Community Development Director approval), Section 10-5-040 (Notice of Disapproval), and Section 10-5-050 (Temporary Certificates: allows a temporary CO before full project completion, secured by a bond of at least $5,000, with completion required within 30 days, extendable once up to 90 days). Also reviewed Section 12-2-047 (Certificates of Occupancy, Title 12 Subdivision Regulations), which is a DIFFERENT, narrower CO trigger -- it blocks occupancy of any structure within a subdivision until required subdivision infrastructure (street surfacing, street signs, house numbers, utilities) is complete; it does not govern a standalone change-of-use CO for an existing building. None of these newly-reviewed sections states a dollar fee or a numeric review-timeline for a standard or change-of-use Certificate of Occupancy -- this is now confirmed as a genuine, thorough gap in Farmington's own published code and fee schedule, not a retrieval failure. UPGRADED 2026-07-20: read the Consolidated Fee Schedule's full Section C (Building Permit Application and Related Fees) directly via page-image rendering (pages 8 and 11 of the 28-page PDF), which the earlier pass had only sampled for A/B-series Land Use fees rather than reading Section C's complete line-item list end to end. This surfaced two governing fee mechanisms previously missed: (1) Section C5, a genuine, itemized 'Temporary Occupancy Application Fee' of $50.00 (plus the already-documented $5,000 minimum bond under City Code 10-5-050) for a Temporary Certificate of Occupancy; and (2) Table No. 1-A (the same 1997 UBC valuation table used for the base Building Permit Fee), whose item 3 is an explicit catch-all: 'Inspections for which no fee is specifically indicated ... Minimum Charge - one-half hour, $55.55/hr' -- the governing mechanism for a pure change-of-use Certificate of Occupancy inspection that is not otherwise tied to a building permit (since no CO-specific line item exists, this catch-all is what the fee schedule's own structure directs such a case to).
Verified 2026-07-20 · Source
When you need this permit
- No land may be changed in use or occupancy, and no building may be changed in use or structurally altered, until a Certificate of Occupancy is issued by both the Zoning Administrator and the Building Official (City Code section 11-4-050.C.1)
- No certificate of occupancy shall be issued unless the contemplated use of the land and/or buildings is in full compliance with the requirements of Title 11 (Zoning) and applicable building codes (City Code section 11-4-050.C.2)
- A certificate of occupancy is required for the purpose of maintaining, renewing, changing, or extending a nonconforming use (City Code section 11-4-050.C.3)
- If the use/occupancy change requires a Conditional Use Permit, a building permit for that building/structure cannot be issued until the Planning Commission approves the conditional use permit (City Code section 11-8-090) -- this section governs the building permit, not the certificate of occupancy itself, but in practice both are gated on the same Conditional Use Permit approval
- If the proposed use is not specifically listed in Farmington's zoning chapters, an Administrative Determination from the Zoning Administrator is required first to classify the use and confirm whether it is permitted or conditional in the applicable zone (City Code section 11-4-050.F)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Zoning Compliance Review
Review by the Zoning Administrator confirming the contemplated use of the land/building complies with Title 11 (Zoning), per City Code section 11-4-050.C.2.
- 2
Building Official Sign-Off
Building Official confirms the building complies with applicable building codes before the joint Certificate of Occupancy is issued, per City Code section 11-4-050.C.1.
See the full Farmington inspection guide — scheduling & re-inspection fees →
Tips
- This requirement is broader than a typical end-of-construction CO: Farmington's code requires a Certificate of Occupancy any time land or a building changes use or occupancy, even with no structural alteration and no separate building permit application involved.
- If your new use is not specifically listed in Farmington's zoning code (Title 11, Chapters 10-26), budget for the $125 Administrative Determination Application Fee and time for the Zoning Administrator's classification review before you can proceed.
- If the space's use is, or is becoming, a legally nonconforming use, note that City Code section 11-4-050.C.3 requires a certificate of occupancy specifically 'for the purpose of maintaining, renewing, changing or extending a nonconforming use' -- confirm with the Zoning Administrator whether this applies to your situation.
- No fee schedule line item is labeled specifically 'Certificate of Occupancy' or 'Change of Use' -- confirm directly with the Building Department (801-939-9214) and Community Development what, if any, processing fee applies to a pure use/occupancy change that does not otherwise require an Administrative Determination or Conditional Use Permit.
- Farmington City Code Title 10, Chapter 5 ('Certificates,' Sections 10-5-010 through 10-5-050) governs the base, post-construction Certificate of Occupancy process separately from the change-of-use trigger in Section 11-4-050.C -- a related but distinct provision worth knowing if your situation involves new construction rather than a pure change of use in an existing building. A Temporary Certificate of Occupancy (Section 10-5-050) requires a bond of at least $5,000, completion within 30 days (extendable once, up to 90 more days), plus a 15% overhead fee if the city has to complete the work itself.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Farmington
Certificate of Occupancy (Change of Use / Occupancy) in other cities
Compare certificate of occupancy (change of use / occupancy) fees across Utah →
Look up this fee in a different city →
Now live
Build your Farmington project checklist
Describe your project once and get every permit, document, and fee it triggers in Farmington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →