Skip to main content
PermitBase

Certificate of Occupancy / Change of Use (Business License Route) in Pleasant View, Utah

Pleasant View City Code Section 18.60.020(C) makes a Certificate of Occupancy a distinct legal requirement, separate from the construction-permit process: 'No land shall be used or occupied and no building hereafter structurally altered or erected shall be used or changed in use... until a certificate of occupancy shall have been issued.' The Code specifically extends this to nonconforming-use changes: 'A like certificate shall be issued for the purpose of maintaining, renewing, changing or extending a nonconforming use.' Pleasant View does not publish a standalone change-of-use application, however -- in practice, a new occupant or a changed use in an existing commercial building is verified through the City's Business License process, which requires a Fire Department inspection and, for new applicants, a Safety Inspection performed by the City's contracted building inspector (Sunrise Engineering) before the license -- and lawful occupancy -- is granted.

Reviewed 2026-07-20 · Source

When you need this permit

  • A building 'used or changed in use' (Pleasant View City Code Section 18.60.020(C)) requires a certificate of occupancy before that use may lawfully commence, aside from agricultural uses
  • Maintaining, renewing, changing, or extending a nonconforming use likewise requires a new certificate of occupancy, per the same section
  • For a new business/occupant, a completed Pleasant View City Business License Application (new applicant or renewal)
  • Fire Department inspection, scheduled with the North View Fire Marshal (801-782-8159) -- required for most license types (Contractor, Wholesale & Professional, Preschool/Day Care, General/Retail, Storage Units)
  • Safety Inspection performed by the City's contracted building inspector (Sunrise Engineering, 800-560-6151) -- marked 'new applicants only' on the official Business License Application, consistent with verifying occupancy/use compliance for a new tenant or use

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

General/Retail Business LicensePleasant View City Consolidated Fee Schedule, as of July 1, 2026 (pleasantviewut.gov/DocumentCenter/View/441), Business License Fees section, live-read 2026-07-20: 'Retail...$65.00.' Matches the 'General/Retail $65.00' line on the official fillable Business License Application packet. Requires a Fire Dept. inspection per the application form.
65.00 dollars
Storage Units Business LicensePleasant View City Consolidated Fee Schedule, as of July 1, 2026, Business License Fees section: 'Storage units...$65.00.' Requires a Fire Dept. inspection per the application form.
65.00 dollars
Wholesale / Professional & Occupational / Contractor Business LicensePleasant View City Consolidated Fee Schedule, as of July 1, 2026, Business License Fees section: 'Wholesale...$43.25,' 'Professional & occupational businesses...$43.25,' 'Contractors...$43.25.' Each requires a Fire Dept. inspection per the official application form.
43.25 dollars
Home Occupation Business LicensePleasant View City Consolidated Fee Schedule, as of July 1, 2026, Business License Fees section: 'Home Occupation...$40.00.'
40.00 dollars

Review timeline

Plan review
Not published — contact the department

How long did your Certificate of Occupancy / Change of Use (Business License Route) permit actually take in Pleasant View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Department Inspection

    Scheduled with the North View Fire Marshal (801-782-8159); required for most business license types (Contractor, Wholesale & Professional, Preschool/Day Care, General/Retail, Storage Units) per the official Business License Application.

  2. 2

    Safety Inspection (new applicants only)

    Performed by the City's contracted building inspector, Sunrise Engineering (800-560-6151); marked as required for new applicants only on the official Business License Application, consistent with verifying occupancy/use compliance when a use changes.

See the full Pleasant View inspection guide — scheduling & re-inspection fees →

Tips

  • Pleasant View does not publish a standalone 'Change of Use Permit' or a separately-priced Certificate of Occupancy fee. The legal requirement is real -- City Code Section 18.60.020(C) requires a certificate of occupancy whenever a building 'shall be used or changed in use,' including maintaining, renewing, changing, or extending a nonconforming use -- but in practice it is verified through the Business License process, priced per license type (40.00 to 65.00 dollars) rather than through a dedicated change-of-use application.
  • The Safety Inspection (performed by Sunrise Engineering, the City's outsourced building inspector) is marked 'new applicants only' on the official Business License Application -- this is the practical building-compliance check that lines up with a change-of-use/new-occupant scenario, distinct from the Fire Department inspection required more broadly.
  • Physical inspections in Pleasant View are outsourced to Sunrise Engineering (1-800-560-6151) rather than performed by in-house City staff -- the same contractor used for the City's regular building permit inspections.
  • Re-chased 2026-07-20 with additional avenues: full-text search of Pleasant View City Code Title 18 (Zoning, 203 pages, direct PDF fetch) for every certificate-of-occupancy mention -- found only 18.60.020(C) (the general CO requirement already cited) and 18.24.690 (a narrower certificate-of-occupancy provision specific to mobile home parks, Ord. 2010-6), neither of which states a dollar fee; also checked Ordinance 2022-21 (a 2022 Title 18 amendment) and the Consolidated Fee Schedule PDF directly for any occupancy-fee line item -- none found. No dedicated, separately-priced Certificate of Occupancy fee exists anywhere in Pleasant View's published code or fee schedule; the Business License route documented above remains the genuine, fully-chased answer.
  • A second re-chase on 2026-07-20 read the entire 19-page Consolidated Fee Schedule (as of July 1, 2026) page-by-page rather than section-searching, covering Subdivisions, Building Permits, Planning & Zoning, Utilities, Animal Impound, Other Fees, and Business License Fees -- confirmed there is still no 'Certificate of Occupancy' line item anywhere in the document. It did surface one adjacent, genuinely distinct fee not previously logged: a 'Zoning Verification Letters' fee of $75.00 under 'Other Fees' -- confirmed via a Pleasant View City Council meeting (August 2024) to have been deliberately added to the Consolidated Fee Schedule as its own new line item ('possible action to amend the Consolidated Fee Schedule by adding fees for Zoning Verification Letter Requests'). A Zoning Verification Letter is a distinct administrative product (used to confirm a property's zoning designation/permitted use, typically for lenders, title companies, or a prospective tenant) and the record does not establish it is charged as, or substitutes for, the certificate of occupancy required by Code 18.60.020(C) -- so it is logged here as a related fee to be aware of, not folded into the CO answer as an invented match. Also checked: North View Fire District (which performs the Fire Department inspection referenced above) for its own published fee schedule -- no District-published inspection-fee document was found via search or its official site (northviewfire.gov); Weber County (Pleasant View's home county) for any county-level building/CO fee applicable to Pleasant View -- none found, consistent with Pleasant View contracting inspections directly to Sunrise Engineering rather than routing through county fee schedules. No new avenue turned up a dedicated, dollar-figure Certificate of Occupancy fee; the Business License route remains the genuine, now twice-chased answer.

Frequently asked questions

Pleasant View requires a certificate of occupancy / change of use (business license route) permit for: A building 'used or changed in use' (Pleasant View City Code Section 18.60.020(C)) requires a certificate of occupancy before that use may lawfully commence, aside from agricultural uses; Maintaining, renewing, changing, or extending a nonconforming use likewise requires a new certificate of occupancy, per the same section; For a new business/occupant, a completed Pleasant View City Business License Application (new applicant or renewal); Fire Department inspection, scheduled with the North View Fire Marshal (801-782-8159) -- required for most license types (Contractor, Wholesale & Professional, Preschool/Day Care, General/Retail, Storage Units); Safety Inspection performed by the City's contracted building inspector (Sunrise Engineering, 800-560-6151) -- marked 'new applicants only' on the official Business License Application, consistent with verifying occupancy/use compliance for a new tenant or use. If your project isn't listed, confirm with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529 before starting work.

In Pleasant View, the published General/Retail Business License is: 65.00 dollars. Additional published fees: Storage Units Business License — 65.00 dollars; Wholesale / Professional & Occupational / Contractor Business License — 43.25 dollars; Home Occupation Business License — 40.00 dollars. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Pleasant View does not publish a plan-review timeline for this permit. Contact Pleasant View City Planning, Zoning & Building Department at (801) 782-8529 for current turnaround.

You'll need: Pleasant View City Business License Application; Fire Department / Safety Inspection sign-off. See the required-documents checklist on this page for details on each.

Pleasant View requires 2 inspection(s) for a certificate of occupancy / change of use (business license route) permit, in order: Fire Department Inspection, Safety Inspection (new applicants only). Schedule each through Pleasant View City Planning, Zoning & Building Department ((801) 782-8529).

Apply through Pleasant View City Planning, Zoning & Building Department at 520 W Elberta Dr, Pleasant View, UT 84414. Phone: (801) 782-8529. Office hours: Mon–Thu 8:00 AM – 5:00 PM; Fri 8:00 AM – 12:00 PM. Official information: https://www.pleasantviewut.gov/168/Planning-Zoning-Building.

Pleasant View, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026, under the statewide preemption mandate of § 15A-1-204 (State Construction and Fire Codes Act); Pleasant View's own codified Title 15.04 text still references the 2000 IBC (Ord. 2002-10), but that codification is stale and superseded by the mandatory statewide cycle.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's Consolidated Fee Schedule (as of July 1, 2026) still labels its Table for Permit Fees 'Appendix L, 2015 IRC,' which is stale fee-table boilerplate, not evidence the city enforces an outdated code edition — plan review and inspections apply the current statewide IRC per § 15A-1-204.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d); Pleasant View's codified Title 15.16.010 references the 2000 IPC (stale codification), superseded by § 15A-1-204.; 2024 International Mechanical Code (IMC) / International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(e)/(f); Pleasant View's codified Title 15.12.010 references the 2000 IMC (stale codification), superseded by § 15A-1-204.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide code per Utah Code § 15A-2-103(1)(h) (a single edition applies statewide, no separate residential/commercial split); Pleasant View's codified Title 15.28.010 references the 2000 IECC (stale codification), superseded by § 15A-1-204.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's codified Title 15.20.010 references the 1999 NEC (stale codification), superseded by § 15A-1-204.. Local amendments apply — see the Pleasant View overview page for the full list.

Pleasant View City Code Section 18.60.020(C) requires a certificate of occupancy whenever a building 'shall be used or changed in use,' including changing or extending a nonconforming use. There is no separately-named change-of-use permit application, however -- this is verified in practice through the Business License process (40.00 to 65.00 dollars depending on license type), which requires a Fire Department inspection and, for new applicants, a Safety Inspection by the City's contracted building inspector (Sunrise Engineering) before the license and lawful occupancy are granted.